Production readiness reviews
Before a service takes real traffic, or before you take its pager, check with evidence that it can be run: a checklist built from your own incidents, tiers that keep small launches light, and a plain answer to who carries the risk that remains
A new service has passed its architecture review, and its first release has QA sign-off. Which question is still open, and belongs to a production readiness review?
A production readiness review, PRR, checks that a service can be run before it takes real traffic, or before a team other than its authors takes its pager. At Lead level you rarely run every review yourself. You own the programme: the checklist, the tiers that decide which launches get a full review, the reviewers and their coaching, the rule for what blocks, and the evidence that it works. Lead-level SREs are judged partly on outages that did not happen, and this is the mechanism aimed most directly at them.
Three reviews, three questions
Two neighbouring reviews share the territory, and teams confuse all three. Architecture reviews and governance covers the design review a principal engineer runs. Release management and sign-off covers the go/no-go for each release. Read both; this chapter draws the borders.
| Architecture review | Production readiness review | Release sign-off | |
|---|---|---|---|
| Question | Is this the right design? | Can this service be run, by whom, at what reliability? | Does this change meet the go/no-go criteria agreed for it? |
| When | Before building, while the design can change | Before the service takes real traffic or changes who supports it; again each year | Every release, before deploy |
| Unit | A design that crosses a one-way door | A service, or a launch that changes one | A release candidate |
| Evidence | An RFC: options, numbers, failure modes on paper | The running system: dashboards, alert routes, a rehearsed restore, a load test, a rota with names | Test results, a defect query, a rehearsed rollback for this change |
| Who runs it | A principal or staff engineer | A Senior or Staff SRE, or the Platform Lead | QA holds the evidence; a release owner decides |
| Output | An ADR, with conditions | A verdict, findings with owners and dates, and a support decision: who holds the pager | Go, go with conditions, or no-go, in the release record |
The QA release checklist has an operational readiness row (rollback rehearsed, dashboards for the new paths, on-call told what changed), and that row is where the overlap lives. Treat it as the per-release top-up of a PRR. A go/no-go can confirm that a change keeps a ready service ready. It cannot make an unready service ready in fifteen minutes.
The overlap runs the other way too. AWS starts its readiness review during design, and Mercari’s public checklist has a design checklist met before development begins. That is the PRR telling teams early what they will be asked at the end, so the alert route and the restore get built in rather than bolted on. The verdict still waits for the built system.
What a PRR is for
The idea has two origins, and most companies need both.
At Google, the PRR is a handover gate. Chapter 32 of the SRE book, by Acacio Cruz and Ashish Bhambhani, defines it as “a process that identifies the reliability needs of a service based on its specific details”, and says that “A PRR is considered a prerequisite for an SRE team to accept responsibility for managing the production aspects” of a service. Its first objective is to “Verify that a service meets accepted standards of production setup and operational readiness”. “Usually one to three SREs” run it, through engagement, analysis, improvements and refactoring, training, and onboarding, after which the pager moves.
Google also had a launch gate. Chapter 27, “Reliable Product Launches at Scale”, describes Launch Coordination Engineering, LCE: engineers who drive the technical side of launches and act as “gatekeepers and signing off on launches determined to be ‘safe’”. Google defines a launch as “any new code that introduces an externally visible change to an application”.
AWS builds its Operational Readiness Review, ORR, from incidents. The whitepaper says AWS created it “to distill the learnings from AWS operational incidents into curated questions with best practice guidance”, so a risk found in one team’s post-incident analysis, a Correction of Errors, stops recurring elsewhere. The stated aim is “shorter, fewer, and smaller” incidents. AWS calls the ORR “a complementary process to Well-Architected”: the Well-Architected reliability pillar is a general best-practice review anyone can apply, and the ORR adds the questions only your own failures could have taught you.
Most companies have no central SRE team waiting to take pagers. For them the PRR does both jobs: it decides whether a service may take traffic, and it decides who carries the pager and with what support behind them. Keep both questions explicit. A verdict of ready that does not name the on-call has answered half the question, which is what happened to the seat-map service.
The checklist comes from your incidents
The checklist is the PRR’s main tool, and it goes wrong by growing. Every incident adds a line, nobody removes one, and in two years teams tick 140 boxes in an afternoon. Google’s LCE chapter warns that “it is easy for the checklist to grow to an unmanageable size”, and records the remedy Google used for a while: “adding new questions to Google’s launch checklist required approval from a vice president.” Its rule for every question: “Every question’s importance must be substantiated, ideally by a previous launch disaster.”
AWS gives the same rule from the other side. Draw questions from “Real incidents that you’ve had in the past”, “Near-misses that you’ve had in the past”, and “The failure modes that haven’t occurred, but that you’re concerned about”. Keep only the critical ones: “The ORR checklist is most effective when it’s focused on incidents that present critical risks”, and medium and low risks are left out “to keep it a lightweight process”.
So the checklist is a document with provenance. Each question carries the incident, near-miss or feared failure that justifies it, and a question nobody can justify is deleted at the next revision. Start from your last eighteen months of postmortems, which the incident management programme should already hold, not from someone else’s list. Google’s 2005 launch checklist, AWS’s example questions and Mercari’s checklist are good for spotting gaps. Copied whole, they ask about risks you do not have and miss the ones you do.
Ask for something a reviewer can open, not a yes. AWS’s example questions show the register: not “do you have a failure model?” but “Please construct a failure model listing soft and hard failure modes for each of your components and dependencies.” Not “do you have alarms?” but whether you have “performed a gameday to verify that your service’s monitoring and alarming function as expected”. The areas below are the usual spine. The mechanisms behind them are taught elsewhere; the PRR checks they are in place.
| Area | Ask to see | The mechanism is taught in |
|---|---|---|
| Dependencies and failure modes | A failure model: each dependency, how it fails, what users see | Failure models, cascading failures |
| Defence against dependencies | Timeout and retry settings for every outbound call, in config | Timeouts, retries, backoff and jitter |
| Defence against load | A load test at forecast peak, and what sheds first | Load shedding, capacity and cost |
| Monitoring and alerting | An agreed SLO with burn-rate alerts that route to a person | SLOs in practice, alert design |
| Emergency response | A runbook linked from each page, a rota with names, a test page answered | Runbooks and on-call, on-call done right |
| Change management | Progressive rollout with a rehearsed or automatic rollback | Testing in production |
| Data | Backups, and a timed restore rehearsal | Disaster recovery and continuity, failover |
The checklist shrinks as the platform grows. When a golden path gives every service dashboards, alerts and a rollout pipeline by default, several questions become one: is the service on the path? Security usually runs its own review. Agree with the security team which of you asks about secrets, certificates and access, so a launch does not answer the same question twice on two forms.
Tiers: keep small launches light
One review for every launch is either too heavy for small launches or too light for big ones. Google’s LCEs “identified categories of low-risk launches that were highly unlikely to face or cause mishaps”: “a feature launch involving no new server executables and a traffic increase under 10% would be deemed low risk”, and such launches “were faced with an almost trivial checklist”. “By 2008, 30% of reviews were considered low-risk.” Mercari ties the tier to the SLO: its Production Readiness Level A is for critical services with an SLO above 99.9%, Level C for experimental ones, and the level decides which checklist items are required.
A three-tier shape works for most companies. Treat it as a rule of thumb, not a standard.
| Tier | Trigger (observable facts) | Review |
|---|---|---|
| 1 | Moves money, holds personal data, has an SLO of 99.9% or tighter, or will page someone outside the owning team | Full checklist, two reviewers, a session with the system running |
| 2 | Customer-facing, none of the above | A subset, one reviewer, asynchronous |
| 3 | Internal tools, or flagged experiments on a small share of traffic | A short self-assessment, recorded; a sample spot-checked each quarter |
Do the sums before you publish the tiers. Suppose your company makes 110 production launches a year and 15 of them are tier 1, each taking two reviewers three days. That is 15 × 2 × 3 = 90 reviewer-days, about four and a half months of one SRE at twenty working days a month, before any tier-2 work. These figures are illustrative; use your own launch count. If the result does not fit beside on-call and project work, narrow tier 1 or fund reviewers.
Evidence, not attestation
The seat-map spreadsheet said alerting was configured, and it was: to an email alias. Self-attestation answers the question the team understood, not the one you meant. A PRR asks for links. Mercari’s guide tells teams to tick each item and link evidence such as tickets, screenshots, documents or test results, and warns: “If evidence is not provided the review process will take much longer.”
Some evidence only exists with the system running. Mercari’s guide expects a service to be deployed to production, invisible to users, before the review opens, because capacity estimates, dashboards and alerting can only be checked with live traffic. Three checks catch most attestation:
- Fire a test page through the real route at an agreed time. The engineer on call acknowledges it and opens the runbook the alert links to.
- Ask for the restore log, not the backup schedule: the date, how long it took against the target, and what was checked afterwards.
- Ask the engineer who will be on call, not the tech lead, to walk the failure model. If only one person can answer, the support decision has to reflect that.
Running the review
Start early and decide late. A shape that matches AWS’s description of its ORR running through the lifecycle:
- Kick-off, at design. Thirty minutes. Agree the tier, hand over the checklist, name the business owner who will accept any remaining risk. The team now knows the questions months before the answers are due.
- Mid-build check-in. Dependencies, the load plan, the SLO draft. Anything that needs a redesign surfaces here, while it is still cheap.
- The review, two to three weeks before launch. A rule of thumb: long enough to fix a missing timeout, too short to replace a datastore, which is why the datastore question belongs to the design review.
In the session, the owning team’s engineering manager and the engineers who will be on call answer; the reviewers ask. For tier 1, invite someone from each critical dependency. Walk the failure model against live dashboards, fire the test page, and classify every finding as it is made:
- Blocking: a risk of the kind the checklist exists to stop. Money moved twice, data that cannot be restored, failure that spreads beyond the service, or nobody paged. Write these criteria down before the first review, not during one.
- Follow-up: real, contained, given an owner and a date in the team’s own backlog.
- Accepted: a risk the business owner has chosen to carry, signed, with an expiry date.
The review ends in one of three verdicts. Ready. Ready with conditions, each condition with an owner, a date and the milestone it gates, such as widening a rollout past 10% of traffic. Not ready, with the blocking findings and a re-review date. Every verdict carries a support decision: which team is primary on call, who is secondary, and what SRE support exists until when. At AWS, “Any high-criticality findings are escalated to leadership as input to a go or no-go launch decision.”
What a PRR can block, and who carries the risk
This part has no clean answer. A PRR that can never stop a launch is advice, and teams learn to file it. One that can always stop a launch makes SRE the queue teams route around, the failure the staff chapter describes for architecture boards.
Separate two decisions the word “block” runs together. The first is whether the service takes traffic. That is a business risk, owned by whoever owns the business outcome: a product director, an engineering director, sometimes the CTO. AWS’s wording is careful: findings go to leadership “as input to” the decision. Google’s LCEs were responsible for “keeping stakeholders informed of the nature and likelihood of such failures” whenever corners were cut to reach the market faster. Neither makes the reviewer the owner of the launch.
The second is whether your team carries the pager, and that one is yours. Google’s model makes SRE support conditional: the service has to merit it, and the SRE team and the development organisation have to agree on staffing. A service that is not ready can launch if the business chooses, with its own team on call. SLOs in practice describes the same lever used after launch, when a service that keeps missing its SLO has its SRE support revoked.
So when a launch fails the PRR, your job is to make the risk legible and the choice explicit: what could go wrong, how likely, how bad, how far it spreads, what would contain it, and who holds the pager meanwhile. Write the risk acceptance as a short paragraph the business owner signs, with an expiry date. Some date fights end there: a director asked to sign “members may be charged twice and we cannot restore the ledger” may find the week after all.
Hold one line yourself. When the blast radius reaches beyond the launching service, into other teams’ services or their customers, the launch owner cannot accept that risk alone, because it is not only theirs. Make that finding a precondition, or escalate to the person who owns both.
| Question | One camp | The other camp |
|---|---|---|
| Can the PRR block a launch? | Yes, for tier 1, or it is theatre | No; it informs the business owner, and SRE’s lever is the pager |
| Who answers the checklist? | The team self-assesses, as at AWS and Mercari, and reviewers inspect | SREs do the analysis, as in Google’s PRR, because teams cannot see their own gaps |
After launch: inspect the mechanism
AWS expects teams to run an ORR on their full service “at least annually”, and its weekly operational metrics meeting looks at when each team last ran one and how many action items remain open. It also tests the mechanism through incidents: the Correction of Errors template asks “When was your last ORR performed?” and “Would any ORR recommendations have reduced or avoided the impact of this event?” Add both to your postmortem template.
| Measure | What it tells you |
|---|---|
| Incidents in the first 90 days after launch, by tier, reviewed and unreviewed | Whether the PRR catches what it exists for |
| Postmortems where a checklist question covered the cause and was answered yes | Attestation where you needed evidence |
| Postmortems where no question covered the cause | Candidates for a new question |
| Conditions closed by their date; accepted risks past expiry | Whether “with conditions” means anything |
| Working days from review request to verdict, median and slowest tenth | Whether teams can afford to come |
Day to day
At Lead level the work is the programme, with some reviews of your own.
Weekly. Triage new readiness requests and set their tiers, about thirty minutes. One or two tier-1 sessions, as reviewer or as coach beside a senior SRE running their first. A pass over open conditions and accepted risks near expiry. An office hour for teams early in a build, where findings are cheapest.
Monthly. A thirty-day look at last month’s launches: were the conditions closed, and did anything page that the review should have caught? Read every postmortem for the two questions above. Propose additions and deletions. Report the measures to the head of platform, including the reviewer-days spent.
Quarterly. Spot-check a sample of tier-3 self-assessments. Revise the checklist, and delete at least as readily as you add. Rotate and coach reviewers so the programme does not depend on you.
Yearly. Schedule the annual re-review of every tier-1 service, and ask whether the tier triggers still match the SLOs.
The meetings that matter: the review session, the conversation in which a business owner decides whether to accept a risk, and the monthly postmortem read, where the checklist learns.
There is no SRE team and probably no formal on-call. The PRR is a one-page list of ten questions in the repository, written from your first incidents, run by the most operationally minded engineer with the CTO before anything moves money or holds personal data. The questions that matter: who is paged, can we restore, what happens when the payment provider is slow. Skip the tiers. Risk acceptance is the CTO writing one sentence in the launch thread, which is enough, because it is written.
This is where the PRR is born, usually by the first platform lead after an outage like the seat-map one. A platform or SRE team of three to eight reviews tier 1; everyone else self-assesses. Keep the checklist under 25 questions, drawn from last year’s postmortems. Build it alongside the on-call policy and the first SLOs, because a PRR needs an SLO to measure against and a rota to route to. The risk is copying Google’s model whole, including an SRE team taking pagers it has no people to carry.
Several reviews already exist: an architecture board, a security review, a change advisory board, a PRR, each with its own form, and a launch can answer the backup question five times. The work is consolidation: shared questions agreed between reviews, tiers so most launches stay light, and readiness records other reviews and auditors can reuse. Annual re-reviews across hundreds of services need tooling. Expect politics from both sides: product directors used to treating the PRR as a formality, and SRE leaders who want a veto.
Template
# Production readiness review: <service or launch>
Tier: 1 | 2 | 3 · Reviewers: <names> · Owning team and EM: <name>
Business owner (signs any accepted risk): <name>
Kick-off: <date> · Review: <date> · Launch: <date>
## Scope
What is launching, the traffic it takes, its SLO (link), what it depends on,
who depends on it, and its blast radius if it fails.
## Checklist (answer with a link; "yes" is not an answer)
| # | Area | Question | Why it is here (incident / near-miss / risk) | Tiers | Evidence | Finding |
|---|---|---|---|---|---|---|
| 1 | Emergency response | Fire a test page through the production route. Who acknowledged, and how fast? | <ref> | 1, 2, 3 | | |
| 2 | Data | Link the last restore rehearsal: date, duration against target, what was checked | <ref> | 1, 2 | | |
| ... | | | | | | |
## Blocking criteria (fixed before any review)
- <e.g. money can move twice; data cannot be restored; failure spreads beyond the service; nobody is paged>
## Findings
| # | Finding | Blocking / follow-up / accepted | Owner | By | Status |
|---|---|---|---|---|---|
## Verdict
Ready | Ready with conditions (condition, owner, date, milestone it gates) | Not ready (re-review date)
## Support decision
Primary on-call: <team, rota link> · Secondary: <team> · SRE support: full | consulting | none, until <condition>
## Accepted risks
| Risk | Likelihood, impact, blast radius | Contained by | Accepted by | Expires |
|---|---|---|---|---|
## Checklist maintenance
Owner: <name> · Revised: <cadence> · Last revision: <n> added, <n> removed
A question is removed when: <rule, e.g. no incident or credible risk cites it, or a pipeline check now enforces it> WORKED EXAMPLE
Agate is a fictional digital consumer lender: 300 people, 90 engineers in 12 teams, one of them a platform team of seven, three of whom are SREs. Kekeli, the Platform Lead, wrote Agate’s first PRR checklist from the last 18 months: 14 SEV-1 and SEV-2 postmortems and 3 near-misses.
Tiers. Tier 1 moves money, makes a credit decision or has an SLO of 99.9% or tighter: all 22 questions, two reviewers, a 90-minute session. Tier 2 is customer-facing with no money: 14 questions, one reviewer, asynchronous. Tier 3 is internal tools and flagged experiments under 5% of traffic: 8 questions, self-assessed, a quarter of them spot-checked. Agate expects about 8 tier-1 launches a year at 2 reviewers × 3 days, which is 48 reviewer-days, or 16 days per SRE.
Sample questions. Q4: “Show the expiry date and renewal alert for every certificate the service presents.” Why: INC-031, a 2-hour-10-minute stop in credit decisions when the client certificate for the credit bureau expired. Q9: “Show that a retried debit carries an idempotency key the payment provider honours, and the test that retries it.” Why: INC-027, 1,140 customers debited twice in February, refunded within three days. Q15: “Fire a test page; record who acknowledged and how fast.” Why: NM-02, an alert routed to a retired channel. Q18: “Link the last restore rehearsal: date, duration against target, what was checked.” Why: a feared failure; in the incident review, no Agate database had a restore on record.
Upkeep. Kekeli revises the list each quarter; a question is removed when no incident, near-miss or written risk from the last two years cites it.
Blocking criteria. Money can move twice; data cannot be restored within its target; nobody is paged.
Applied. Hoda’s collections team brought the new repayments scheduler, tier 1, three weeks before its first collection run. Two blocking findings: Q9 failed, as the debit request had no idempotency key, and Q18 had no rehearsal on record. Three follow-ups got owners and dates. Verdict: not ready, re-review in eight working days. The team added the key and a retry test in four days; the restore took 47 minutes against a 60-minute target. Re-review verdict: ready with one condition, a runbook for a failed collection run, due before the second run. Support: collections team primary, platform SRE secondary.
Now you
You are a Staff SRE at Chert, an airline booking and loyalty platform: 1,200 people, 250 engineers in about 30 product teams, and an SRE team of 12. Selorm, the Head of Platform, has asked you to replace the readiness spreadsheet: 140 yes/no lines, filled in by the launching team and read by nobody. The seat-map service passed it. Chert makes about 110 production launches a year, from flagged copy changes to new services that take card payments and spend loyalty points. Three of last year’s eight SEV-1s happened within 60 days of a launch. The SRE team can give about 60 reviewer-days a year to readiness reviews alongside on-call and project work. The loyalty team warns that any new gate before the holiday season will be routed around, and the security team’s review already asks four of the spreadsheet’s questions. Write the PRR checklist: the tiers and their triggers, no more than 25 questions each with its provenance, the blocking criteria, the verdict and support sections, and how the checklist is revised. Show that the tier-1 load fits in 60 reviewer-days.
Self-check
You are a Staff SRE at Chert and own the PRR programme. Mawuli has reviewed Pay with Points, which lets loyalty members buy seat upgrades with points. It launches in nine days with a campaign email to 9 million members. Two findings are blocking. The load test reached 240 redemptions a minute against a forecast campaign peak of 600. And calls to partner airlines' seat-availability API have no timeout, inside the shared booking API process, so one slow partner could stall every booking on the platform. Aster, the team's engineering manager, says the timeout is a two-day fix. Mateus, the loyalty product director, says the campaign date is agreed with a partner airline. What do you do?
- BOOK The Evolving SRE Engagement Model Acacio Cruz and Ashish Bhambhani, 2016
The original PRR: its objectives, its phases from analysis to onboarding, and the early-engagement and frameworks models that followed. Read it for the PRR as a handover gate. Read: Site Reliability Engineering (O'Reilly, 2016), chapter 32.
- BOOK Reliable Product Launches at Scale Rhandeev Singh and Sebastian Kirsch, with Vivek Rau, 2016
Launch coordination engineering, the launch checklist, low-risk launch categories, and how Google kept the checklist from growing out of control. Read: Site Reliability Engineering (O'Reilly, 2016), chapter 27.
- BOOK Launch Coordination Checklist 2016
Google's original launch checklist from about 2005, abridged. Useful for spotting gaps in yours; read it as a list of areas, not as questions to copy. Read: Site Reliability Engineering (O'Reilly, 2016), appendix E.
- DOC Operational Readiness Reviews (ORR) Amazon Web Services, 2022
How AWS builds readiness questions from its own incidents, tiers checklists by occasion, and inspects the programme. Read the appendices for real example questions with guidance.
- DOC Reliability Pillar, AWS Well-Architected Framework Amazon Web Services, 2024
The general best-practice review that the ORR complements, aimed at strong foundations, resilient architecture, consistent change management and proven failure recovery. A good source of areas, not of your questions.
- CODE Production Readiness Checklist Mercari
A public checklist with a design phase and a pre-production phase, required items set by an SLO-based readiness level, and a guide that asks for evidence links on every item.
All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.