The CEO, the board and your peers
At the top of engineering your work reaches the company through three relationships: a CEO who needs engineering to be predictable, a board that oversees the money and the risk, and peers who are your first team. All three run on one currency: what you say will happen does, and when it will not, they hear it from you first
In the executive meeting the CEO asks when the new EU data region will be live, because she wants to give a prospect a date this week. Your platform team has broken the work down: 50% likely by 1 May, 85% likely by 15 June. What date should leave the room?
At Practitioner level you own engineering. At Head level, as CTO, you also own engineering’s place in three relationships: with the CEO, who hired you and is judged on whether the company does what it said; with the board, which oversees the CEO and approves the plan, the money and the risk; and with your peers, the other executives, with whom every trade-off that matters is made. Your horizon is three years and you are judged by the board as much as by the CEO.
Much of the mechanics is taught elsewhere. The no-surprises habit with the CEO, the pre-read and the shape of a board update are in Product leadership; the risk register and the board’s risk appetite are in Security risk management and the board; the monthly report that feeds the board pack is in Delivery metrics and reporting. This chapter is the engineering executive’s part: dates, the engineering board slide, and the executive team as your first team.
The model: one currency, three accounts
Think of each relationship as an account that holds one currency: predictability. Not the absence of bad news, which no engineering organisation can promise, but the reliability of what you say. When you say a date at 85% confidence, it lands about 85% of the time. When something moves, the CEO hears it from you before anyone else, the board hears it before it reads it in the minutes, and your peers hear it before their customers do.
Every executive spends from these accounts. You spend when you ask the CEO to delay a launch, the board to approve unbudgeted spend, or the CFO to absorb a cloud overrun. You earn by being right about dates, by surfacing problems early and by solving other executives’ problems as readily as your own. Will Larson, in “Balancing your CEO, peers and Engineering”, a draft chapter of The Engineering Executive’s Primer, describes the states this produces: an executive whose work is actively supported by peers, the CEO and their own team; one who is tolerated, where work gets done and nobody helps; and one who is resented, whose requests are treated as distractions until escalated. The accounts are what moves you between them.
The model explains why the date is the hardest part of the job. Engineering is the function whose output is least visible to the rest of the company, so dates become the proxy by which the CEO, the board and your peers judge it. A missed date that was flagged early costs little. A missed date that nobody saw coming costs more than the delay, because it tells every reader that your other numbers might be wrong too.
The CEO
Larson’s draft starts from an uncomfortable point: “CEOs only hire new executives when there is a problem to solve.” The CEO arrives with a narrative about engineering, usually that it is slow or unpredictable, and that narrative is real and incomplete. Engineering will have its own, often that the CEO changes direction too often. Your peers and the board will have a third and a fourth. Larson’s advice is to listen to all of them and then “dig in with the team directly before switching from listening to problem solving”, and he adds a warning worth keeping in your notebook: that engineering having problems does not mean engineering is the problem.
What the CEO needs from you, in rough order:
- Predictable delivery of what was promised, or early warning when it will not happen, with options.
- Engineering translated into business decisions. Not “the ledger needs a backfill” but “multi-currency cards move from March to May unless we cut the reporting feature; I recommend the cut”.
- A view of technology risk they can repeat to the board: what could hurt the company, what you are doing about it, and what you need.
- A peer, not a supplier. A CTO who only answers engineering questions is running a department. The CEO needs someone who will argue about pricing, hiring and the sales plan from the engineering point of view.
Ben Horowitz’s essay “Peacetime CEO/Wartime CEO”, collected in The Hard Thing About Hard Things, adds a calibration. “Peacetime CEO strives for broad based buy in. Wartime CEO neither indulges consensus-building nor tolerates disagreements.” Know which mode your CEO is in this quarter. In peacetime, a long written proposal and a consultation round are the right way to move a decision. In wartime, the CEO wants your recommendation in two sentences and your disagreement once, in private, before the decision is taken. Bringing peacetime process to a wartime CEO reads as obstruction; bringing wartime brevity to a peacetime one reads as arrogance.
The weekly one-to-one with the CEO is where this relationship is kept. A written agenda helps, as the chapter on a head of engineering’s week describes: a decision you want their view on, a risk they should hear first, and something you need. Add one line at Head level: any date the CEO has said or is about to say outside the company, and whether you can stand behind it.
Dates: where promises come from
Most dates you cannot make were not set by engineering. They were said by a CEO in a sales call, by a founder on a podcast, by a salesperson closing a quarter, or by the board when it approved a plan with a launch in it. Nobody involved was lying. A date is the most natural thing for a customer or an investor to ask for, and the person in the room wants to give one.
The failure has a name. The FCA’s Final Notice on TSB uses right-to-left planning: a plan built backwards from a fixed end date, squeezing each phase to fit, as opposed to a left-to-right plan built forwards from the work. Board deep-dive papers quoted in the notice had described the original plan as “designed back from the y/end 2017 deadline” and “aspirational”, created “on a top-down and ‘right-to-left’ basis”. The notice records what happens next: the date for the migration “was ultimately met following the deferral of certain pieces of banking functionality to after MME, or putting in place manual workarounds”. Right-to-left plans usually meet their dates. They do it by moving the risk somewhere the date does not measure.
Four habits keep dates honest.
Three kinds of date, named differently. A target is what the team aims for, roughly the 50% date. A commitment is what you tell the company, roughly the 85% date. An external date is what the company tells customers or investors, and it is never earlier than a commitment. The percentages are a rule of thumb; the point is that everyone uses the same words. When the CEO says “the date”, ask which one.
No external date without a left-to-right plan. Make it the executive team’s rule, written down and agreed with the CEO and the head of sales, that no date leaves the building until engineering has broken the work down and given a range. The plan takes days, not months. The strategy and planning chapter covers how the annual plan is built; this rule covers the dates said between plans.
Ranges with confidence, not points. “1 May at 50%, 15 June at 85%” carries the uncertainty with the date. A single date strips it out, and whoever repeats the date will not add it back.
The trade, offered the same day. When a date cannot be met, the CEO needs options more than an apology. There are four levers: scope (ship less by the date), date (ship everything later), people (add engineers, which Fred Brooks warned in The Mythical Man-Month tends to make a late project later, so it works only early and only for work that splits cleanly) and risk (ship by the date with less testing or fewer safeguards, which is the lever TSB pulled). Name the lever you recommend and what it costs.
When the CEO has already promised a date you cannot make, the order matters. Tell the CEO first, privately, within a day of knowing. Bring the plan, the range and the options. Then let the CEO decide how the customer and the board hear it, because the CEO owns both relationships. Disagree in that room, once and fully. If the decision goes against you, commit to it in public and write down the risk you raised. The one line you do not cross is telling the board something you know is false, or staying silent while the CEO does. In April 2023 the PRA fined TSB’s former chief information officer personally, finding that he gave the board assurance about the supplier’s readiness without first confirming there was enough evidence for it. Outside regulated banking the penalty is rarely personal, but the principle holds: what you tell a board is yours.
The board
The board does not run engineering. It oversees the CEO, approves the annual plan and budget, decides on financing, acquisitions and the CEO’s own job, and carries legal duties to the company. Its members are generalists: investors, former operators, perhaps one director with a technical background. The CEO owns the relationship. You present the engineering section with the CEO’s agreement on every line, and directors never hear about engineering for the first time in the meeting.
What a board needs from engineering is narrower than most CTOs expect. Four questions.
- Is the money buying what we were told it would? Delivery against the plan the board approved, and spend against budget. The headcount and budget chapter covers the numbers; the board sees them as plan against actual.
- What could hurt the company? Reliability against target, security, key-person dependencies, vendor concentration, and technical debt stated as business risk. The security track’s chapter on security risk and the board covers the risk register; your slide shows the few risks a director should hold in their head.
- Can this team get us to the next stage? Hiring against plan, regretted attrition, and whether the leadership bench will hold at twice the size.
- What do you need from us? A decision only the board can take, such as an unbudgeted commitment above the CEO’s authority, a major technology bet, or a change of risk appetite. Or a plain statement that nothing is needed.
Sequoia’s guide “Preparing a Board Deck”, by Bryan Schreier, recommends distributing the materials “one to two days in advance” so that “you can spend the meeting discussing rather than presenting”, and warns that “we’ve attended many board meetings where things looked great, but they actually weren’t.” Boards with independent directors often expect the pre-read a week ahead; that is a rule of thumb, and your chair will tell you. The engineering section is usually one slide in the deck and two or three pages in the pre-read.
One slide, same shape every quarter. Four boxes: delivery against what the board was told, reliability and risk, people and cost, and the ask. A director who saw last quarter’s slide should be able to see what moved. A slide whose layout changes when the news is bad teaches directors to look for what is missing.
Misses beside hits. Every commitment the board saw last quarter appears this quarter, including the ones that missed, with the reason and a new date at a stated confidence. The board will forgive a slip it saw coming. It will not forgive one it discovers.
The pre-read carries the detail. The slide is what is on the screen; the pre-read is what directors read the weekend before. It explains each number on the slide, lists the questions you expect and answers them, and spells out the decision with its options and cost. If a director has to ask what a number means in the meeting, the pre-read failed.
Delivery metrics stay inside engineering. Whether DORA belongs in the board deck is argued in the delivery metrics chapter; either way, the slide reports outcomes the board approved.
Pre-wire. The CEO sees the draft first. Then, with the CEO’s agreement, you or the CEO walk the chair, and any director who will be surprised, through the bad news before the pack goes out. The meeting confirms what was agreed in those calls.
Your peers: the first team
Patrick Lencioni’s The Five Dysfunctions of a Team is a fable about an executive team that does not work, and the idea most executives take from it is the first team: your primary team is the executive team you sit on with your peers, not the department you run. An executive who arrives at the leadership meeting to win resources for engineering treats every peer as a competitor, and the CEO ends up arbitrating trade-offs the team should have made itself. Larson makes the same argument for managers at every level in “Make your peers your first team”, covered in from manager to executive.
At Head level the first team is where most of engineering’s real decisions are made:
| Peer | What they need from you | Where it goes wrong |
|---|---|---|
| CFO | A budget you can defend line by line; cloud and vendor spend with no surprises | You treat the budget as a fight rather than a shared model |
| Head of product | Capacity they can plan with; honest dates; shared ownership of the roadmap | Engineering and product present different dates to the CEO |
| Head of sales or CRO | Dates they can promise; a fast answer on what a big deal needs | Sales promises dates engineering has never seen |
| Head of people | A hiring plan, levelling, and early warning on attrition | You run hiring as a private process |
| CISO, if separate | Risk accepted by the right owner; fixes funded | Security risk is argued in the board meeting rather than before it |
Two habits make the first team work. Agree the commitment policy with sales and product, the rule that no external date is given without a plan from engineering, and write it down so it survives a quarter-end. Resolve conflicts in the room, not through the CEO. Horowitz’s essay “How to Minimize Politics in Your Company”, also in his book, defines politics as “people advancing their careers or agendas by means other than merit and contribution”, and his advice to CEOs on complaints about another executive is “Do not attempt to address behavioral issues without both executives in the room.” Apply it to yourself: when you have a problem with a peer, take it to the peer first, and if it must go to the CEO, go together.
Where practitioners disagree
Talking to directors without the CEO. Some CTOs keep one-to-one relationships with directors, especially a director with a technical background, and find that the board trusts engineering more for it. Others never meet a director alone, because a back channel to the board is the fastest way to lose the CEO. The working position: meet directors with the CEO’s knowledge, tell the CEO what was said, and never use a director to win an argument you lost with the CEO.
Whether engineering should give dates at all. Some leaders argue that estimates are waste and that teams should commit to outcomes and a cadence of delivery instead. Others argue that a company selling to enterprises, raising money or meeting a regulatory deadline cannot operate without dates. Most CTOs land in between: dates for the few commitments that leave the building, given as ranges; no dates for the rest.
Loyalty to the first team against protecting your own. Read crudely, the first team asks you to side with peers against your engineers; Larson’s warning above is the counterweight. The test is whether you would make the same trade-off if you ran the company.
Day to day
The relationships live in a rhythm. Most of it is meetings with people outside engineering.
| Cadence | What happens | With whom | Output |
|---|---|---|---|
| Weekly | One-to-one with a written agenda: decisions, risks, dates said or about to be said | CEO | Decisions taken, no surprises |
| Weekly | Executive team meeting | CEO and peers | Trade-offs made in the room |
| Fortnightly | One-to-ones with each peer, 30 minutes | CFO, head of product, CRO | Problems solved before they reach the CEO |
| Monthly | Engineering report to the executive team | CEO and peers | The numbers the board will later see |
| Quarterly, week −4 | Draft the slide and pre-read from the monthly reports | Your directors, finance | First draft |
| Quarterly, weeks −3 to −2 | Review every line with the CEO | CEO | Agreed slide |
| Quarterly, week −2 | Pre-wire bad news and the ask | Chair, any director who will be surprised, with the CEO’s agreement | No surprises in the room |
| Quarterly, week −1 | Pre-read sent | Board | Directors arrive having read it |
| Quarterly | Board meeting: 15–20 minutes for engineering in most decks (rule of thumb) | Board | Decision recorded, questions noted |
| Twice a year | One-to-one with the director who follows technology, with the CEO’s knowledge | Director | A director who can explain engineering to the rest of the board |
| Yearly | Annual plan and budget presented for approval | Board | The baseline every later slide is judged against |
Two habits matter more than the calendar. Keep a list of every date said outside the company, who said it, to whom, and whether engineering has a plan behind it; review it in the CEO one-to-one each week. And answer every director’s question within a week of the meeting, in writing, copied to the CEO, because an unanswered question becomes the first item next quarter.
Expect around a third of a CTO’s week to go on the CEO, peers and the board, rising in board weeks and planning season. It is a rule of thumb. The sign it is too low is a board slide written the night before; the sign it is too high is a CTO who no longer knows what the teams are building.
The CTO is usually a founder, the CEO is a co-founder, and the board is the founders and one or two investors. There is no board deck; there is a monthly investor update with the numbers, the misses and the asks, and engineering is two lines in it. The dates that hurt are the ones a founder gives the first big customer on a sales call. Agree now, between the two of you, that no date goes to a customer until you have looked at the work for a day. It is the habit that later becomes the commitment policy.
The first independent director joins, the board pack becomes formal, and the CTO or VP Engineering presents engineering for the first time. The executive team forms around you: a first CFO, a head of sales with a quota, a head of people. Dates promised to close deals are now the main source of conflict, so write the commitment policy with sales and product in your first quarter. The first board appearance sets how directors read engineering for years: bring the same four boxes every quarter, misses beside hits.
The board has committees: audit, risk, sometimes a technology committee, and you may see the full board once a year and a committee each quarter. Your section passes through a company secretary, a pack template and several reviews before a director reads it. In regulated sectors, what you tell the board can carry personal accountability, as the PRA’s action against TSB’s former CIO showed. Peers run divisions with their own P&L, and the first team is harder to hold together when each peer is also competing for the next CEO job.
Template
# Engineering — <quarter> board slide
Presenter: <CTO> · Reviewed with CEO: <date> · Pre-wired with: <chair, others>
## 1. Delivery against what the board was told
| Commitment (from last quarter's pack) | Status | If moved: reason · new date (50% / 85%) |
|---|---|---|
| <commitment> | shipped / late / cut | |
Knock-on to the annual plan: <milestones that move, or "none">
## 2. Reliability and technology risk
<Tier-1 SLO: target · actual by month · incidents (count, worst one in one line)>
<Top risks (3 at most): what could happen · trend · what we are doing>
## 3. People and cost
Headcount <actual> vs plan <n> · hires <n> · leavers <n> (<n> regretted)
Spend <actual> vs budget <n> · cloud <n> as <unit cost or % of revenue>, trend
## 4. Decision asked of the board
<One decision, with the amount and the date it is needed by — or "None this quarter">
---
# Pre-read (two to three pages)
## Summary — three sentences the CEO could repeat
## Delivery — each row of box 1 explained; what changed in how we plan
## Reliability and risk — each incident and risk in a paragraph; link to the reviews
## People and cost — plan vs actual, why, and the forecast for next quarter
## The decision — options, cost, funding, risk of each, our recommendation, what happens if the answer is no
## Questions we expect — and the answers WORKED EXAMPLE
Zinnia is a fictional business payments company selling corporate cards and spend management: 310 people, $64M ARR, Series C. Engineering is 92 people in 12 teams. The board has six directors: the CEO, the co-founder COO, three investor directors and an independent director who chairs the audit committee. The CTO wrote this for the Q3 meeting on 14 October, reviewed it with the CEO on 30 September, walked the chair through the ledger slip and the ask on 2 October, and sent the pre-read on 7 October.
1. Delivery. Six commitments from the Q2 pack. Four shipped on time. Receipt matching shipped three weeks late. The ledger migration, committed for 30 September, slipped: reconciliation found 0.3% of historic transactions with mismatched foreign-exchange rounding, which need a backfill. New date 4 November at 50%, 18 November at 85%, seven weeks late at the 85% date. Knock-on: multi-currency cards, in the annual plan for Q1, move to 21 April at 50% and 12 May at 85%. The CEO and CTO considered cutting multi-currency reporting to hold March and chose not to, because the three launch customers asked for it.
2. Reliability and risk. Card-authorisation SLO 99.95% a month. July 99.98%, August 99.97%, September 99.91%. One sev-1 on 2 September: 38 minutes, about 41,000 card payments declined, caused by a configuration change on the single connection to the card processor. The month’s error budget is 21.6 minutes; September used 176% of it. Top risk: that single processor connection.
3. People and cost. Headcount 92 against a plan of 96: seven hires, three leavers, two of them regretted. Spend $4.9M against a $5.1M budget, under because of four unfilled roles. Cloud $1.15M, 7.2% of revenue, down from 7.6% in Q2.
4. Decision. Approve $380,000 for a second card-processor connection over Q4 and Q1. Unbudgeted commitments above $250,000 need board approval. Funded within the annual budget: $200,000 from the Q3 underspend and $180,000 by moving two Q4 hires to Q1. Live by 31 March at 85%. If the board says no, the risk behind the September sev-1 stays in place until next year’s budget.
The pre-read ran to two and a half pages and answered the questions the chair raised on 2 October: why the backfill was not found in testing, and whether the two deferred hires delay anything else.
Now you
You are CTO of Gorse, a fictional customer-engagement platform that sends retailers’ marketing and order messages: 260 people, $52M ARR, 90 people in engineering in eleven teams. The five-person board meets in three weeks and engineering has 15 minutes. Last quarter you committed five projects: three shipped, one shipped four weeks late, and the WhatsApp template editor was cut to make room for the EU data-residency region. There was one sev-1: message delivery delayed for 2 hours 10 minutes, no messages lost. Headcount is 90 against a plan of 98. Cloud spend rose 22% while message volume rose 30%. At the last meeting the CEO told the board the EU region would be live on 1 March, to win a European retailer worth $1.1M a year. Your platform team’s plan says 1 May at 50% and 15 June at 85%. You told the CEO the day the plan was done, and the retailer has signed with a 15 June date. The CEO now wants the date left off your slide and covered in her letter as ‘a slight slip’. Write the slide and the pre-read, decide what you ask the board for, and decide what you say to the CEO about the slide.
Self-check
You are CTO at Gorse, a 260-person customer-engagement platform with 90 people in engineering. At the last board meeting, and on a call with a European retailer worth $1.1M a year, which would be the largest customer in the company's history, the CEO said the new EU data-residency region would be live on 1 March. The contract, due for signature in two weeks, names that date. Your platform team has now built the plan from the work: 1 May at 50% confidence, 15 June at 85%. The board meets in five weeks. What do you do?
- BOOK The Engineering Executive's Primer Will Larson, 2024
A book written for the engineering executive's side of these relationships. Read the CEO and peers chapter before your first quarter and the measurement material before your first board pack. Read: The chapter on working with your CEO, peers and engineering, and the material on measuring and reporting engineering to the CEO and the board.
- POST Balancing your CEO, peers and Engineering Will Larson, 2023
The free draft of the Primer's chapter: why the CEO's narrative about engineering is real and incomplete, supported versus tolerated versus resented, and how to survive a peer in a panic.
- BOOK The Hard Thing About Hard Things Ben Horowitz, 2014
How the job looks from the CEO's chair, by a former CEO turned investor. Read it to understand what your CEO is carrying when they promise a date. Read: Harper Business. The essays on peacetime and wartime CEOs and on minimising politics.
- POST How to Minimize Politics in Your Company Ben Horowitz, 2010
The definition of politics this chapter uses and the rule of handling an executive complaint with both executives in the room. Written for CEOs; apply it to how you treat your peers.
- BOOK The Five Dysfunctions of a Team Patrick Lencioni, 2002
The source of the first-team idea and of the five failures, from absence of trust to inattention to results, that stop an executive team working as one. Read: Jossey-Bass, an imprint of Wiley. The fable of the executive team, then the model section after it.
- POST Preparing a Board Deck Bryan Schreier (Sequoia)
An investor's view of what a board meeting is for and how to structure the pack: send it early, calibrate the board with the fewest correct metrics, and spend the meeting discussing rather than presenting.
- DOC Final Notice: TSB Bank plc Financial Conduct Authority, 2022
The public record of a date set before the plan, a public announcement before the re-plan, and a re-plan that did not show the board clearly how far behind the programme was. Read section 4 on the decision to re-plan.
All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.