Changes: the plan, the window and the rollback

How a network engineer writes a change plan that someone else could run at 2 am: post-checks that can fail, a rollback with a clock on it, and a decision time worked out before the night begins

40 MINNETWORK ENGINEERUPDATED 2026-11-21
PREDICT

Your window closes at 02:00. The rollback has been tested at 15 minutes, and checking that the network is back to normal afterwards takes another 10. What is the latest time at which you can decide to roll back and still finish inside the window?

A network change is a bet that you understood the network, placed at a time when nobody is looking. A change plan is how you make that bet in writing, in a form a colleague could pick up and run if you fell ill at 21:00. It is also the document a change advisory board reads, and the first thing an incident reviewer or an auditor asks for.

This chapter is about the plan, and about three things inside it that people get wrong: the post-checks, the rollback and the clock. The principles behind them are in network philosophies: write the way back first, capture evidence before and after, keep each mistake small. The calendar cost of a window is in a network engineer’s week. The pipeline side, where a change is code that is reviewed and applied, is in infrastructure as code and delivery, and the testing view of go and no-go criteria and of verifying a rollback is in release management and sign-off. Here you learn what goes on the page, and why each line is there.

The people are at Northmere Bank, the national bank with 4,800 staff and a head office in Lagos. Its network is the head office, the data centres and the branch WAN, changed under a change advisory board. The times, counts and thresholds in this chapter are illustrative.

The model: eight parts of a plan

A plan is complete when a stranger can answer eight questions from the page.

Part The question it answers What goes wrong without it
Scope What changes, and what must not? A change that quietly touches a second thing
Pre-checks and baseline What does normal look like tonight? “It looks fine” with nothing to compare against
Steps with times What do we do, in what order, by when? Drift, and nobody knowing the plan is behind
Post-checks What result means pass, and what means fail? A success declared against a check that cannot fail
Rollback How do we undo it, and how long does that take? A rollback that takes longer than the window
Decision time By when must we choose? Hope, in place of a decision
People Who drives, who checks, who may call it off? One tired person deciding alone
Communication Who is told before, during and after? Branch staff finding the change before the bank does

Notice that three of the eight are about deciding: the post-checks, the rollback and the decision time. The steps are the easy part. Most plans that fail on the night fail in these three.

Scope: what changes and what must not

Write the scope as two lists. The first says what you will change: these two firewalls, this routing policy, these 14 branch routers. The second says what must be the same at the end: the other region’s routes, the internet banking path, the access list on the management network. The second list is where the checks come from, because a check is a statement that something on that list is still true.

Scope also sets the size of the mistake. If the change touches many devices, split it into waves and say why each wave is the size it is. Start with the least important device, leave the core for last, and do not change both halves of a redundant pair at once. This is the failure-domain habit from the philosophies chapter, written into the plan as a number: the first wave is five branches, not sixty. Each wave then has its own checks and its own go or stop.

Post-checks that can fail

A post-check is a measurement with a threshold, fixed before the change. A good one has four parts: what you measure, where you measure it from, the line that means pass, and the line that means fail.

Choose checks from three layers, because each catches a different kind of failure.

The control plane. The device agrees with itself: the pair is in sync, the tunnels are up, the expected routes are in the table. These are quick and exact, and they say nothing about whether traffic flows.

The data path. A packet goes where it should. A ping from the head office to a branch tests one path in one direction. Use the path the real traffic takes, in both directions, and for the service the bank cares about.

The service. Something a customer would do: a login to internet banking from outside, a test transaction through the card switch. This is the check that would have saved Ochigbo’s Saturday. It is slower and messier, and it is the only one that tests the thing the change is for.

One check from each layer is a sensible minimum. Five is about right for a change of this kind; more than that and the engineer at 01:30 is reading output instead of deciding.

The ambiguous check

Some checks do not give a clean answer, and you meet them on the night, when you can least afford it. A check is ambiguous when its result can be read as a pass or as a fail. Three causes come up again and again.

A small sample. At night an ATM approval rate is computed over a few dozen transactions, so two declines move it by five points. The number is real, but it cannot tell a fault from bad luck: a healthy 99% rate gives two or more declines in 38 about one night in eighteen.

Noise. A latency figure that wanders by 20 ms on its own cannot tell you that your change added 15.

Lag. Some effects appear after a delay: a session count that settles over ten minutes, a cache that expires after an hour, a lease that renews at the half-way point. A check run too early passes, and one run at the wrong moment fails.

The cure is in the plan, written at your desk. For every check, write three lines instead of two: a pass line, a fail line and a middle band, with a rule for the band. The rule can be short: wait ten minutes, run it once more, and if it is still in the band, treat it as a fail. That rule makes the call before the pressure arrives. It also tells you what to prepare. If the ATM check is going to be ambiguous at night, plan a second check that asks a different question, such as ten test transactions on a test card with the right PIN. Ten cannot prove a 99% rate, since a clean ten is likely even at 95%. They can separate a broken path, which fails most of the ten, from a few stray wrong PINs.

Two cautions. First, a middle band is not a licence to widen the pass line until everything passes. Set the lines from the baseline you captured, and write the reason for each next to it. Second, an ambiguous check is information. It often means the check is badly designed, and you can improve it for next time. The synthetic monitoring chapter in the observability course covers how to build a service-level check that does not depend on real traffic.

The rollback: written, timed and tested

The philosophies chapter says the rollback is written before the change and tested. Here is what the plan must hold about it.

The method and the saved state. The old configuration is saved off the device, tonight, and you have looked at it. The exact commands are listed. Where the device supports it, use a timed rollback: with a NETCONF confirmed commit, defined in RFC 6241, the device undoes the change itself unless you confirm it before a timer runs out. Check that your platform supports it before you rely on it.

The duration. Time it, on a lab device or a quiet one, and write the figure. The duration is the input to the decision time, and a rollback whose duration you have guessed gives you a decision time you have guessed.

The checks. A rollback is a change, so it has post-checks. They are usually a subset of the change’s own, and they take time. Write both figures.

What it cannot undo. Some effects outlast the rollback: leases already handed out, sessions already dropped, routes other networks have learned. Name them, and say what you will do about each.

Working out the decision time

The decision time is the end of the window, minus the rollback, minus the rollback’s checks. With a 15-minute rollback and 10 minutes of checks, a window that closes at 02:00 gives 01:35. After 01:35 you cannot both roll back and prove it worked. Put the time on the page and tell the checker. At the decision time, one of two things is true: the post-checks have passed, or you roll back. The rule is as blunt as that, and it works because it was agreed when nobody was tired.

The same sum shows why big changes are often done in stages. Suppose the change to the second unit of a firewall pair cannot be undone with a quick failover, because both units now run the new version. After the first unit, a rollback is a five-minute failover back to a unit still on the old version. After the second, it is a downgrade of both, tested at an hour. The decision time moves from near the end of the window to well before it, and the plan should show both.

Testing the rollback

Test it on the ladder the philosophies chapter gives. A routine change gets its rollback run on a lab or quiet device. An unusual change gets a comparable device. At the very least, read the rollback aloud line by line to the checker, as if someone else had written it. A tested rollback costs time before the night, and the time pays itself back the first time it saves a window. The release management chapter lists four things to verify about any rollback: that it works, that it is fast enough, that the old version survives what the new one wrote, and that someone owns the call. All four apply to a network.

The window and the board

A window is the time in which the bank has agreed that this part of the network may be disturbed. Branches that open at 08:00 and a payments switch that runs all night set it more than your convenience does. Size it from the plan, not the other way round: preparation happens before it, and inside it you need the steps, the checks, the rollback and its checks, and a buffer. As a rule of thumb from practice, not a measured figure, the steps and post-checks should use about half the window. If they use more, the plan has no room for the bad night, and you should split the change or ask for a longer window.

A change advisory board, a CAB, is the body that approves changes against a plan. It is part of ITIL’s change process, which distinguishes standard changes (pre-approved, low risk, repeated), normal changes (assessed and approved before they run) and emergency changes (done fast, reviewed afterwards). Treat the board as a reader of your plan, not as an obstacle. It does not approve the change. It approves the scope, the checks, the rollback and the window, which is why a plan with no tested rollback gives the board nothing to approve. A board that meets on Monday afternoon needs your plan by the start of the meeting, so the plan date goes on the calendar. If you extend a window on the night, you have made a change to the thing the board approved, and you should say so to its chair rather than discover afterwards that nobody agreed.

The record matters again afterwards. An auditor sampling the quarter’s changes asks for the approval, the plan and the result of each. Compliance and audits explains what is tested; the habit here is to attach the baseline, the post-check output and the decision, with its time, to the change record before you close it.

Where practitioners disagree

Roll back at the first doubt, or fix forward. One camp says that when a post-check is unclear you roll back, because a known good state beats an unknown one and a rollback is cheap when it has been tested. The other says a rollback is itself a change that can go wrong, and that a small, understood fault is better fixed in place. Both are right in their own circumstances. The honest question is which action has the smaller and more predictable failure, and you answer it in the plan, not on the night.

Heavy boards or light ones. Some banks route every change through a weekly board; others pre-approve a large class of routine changes and review only the risky ones. The first gives a record and a second pair of eyes. It can also turn into approval of paperwork that nobody read. The infrastructure as code chapter has a section on approval without a gate, and it is a useful read for anyone who wonders what a board adds that a reviewed, tested pipeline does not.

Windows or small continuous changes. If a change is made in small steps, behind automation and tests, you may not need a night at all. Many branch networks cannot get there yet, because the devices are old or the service is the one that must not stop. Until they can, the plan and the window are the safety.

Hand-typed or scripted. A script makes the steps repeatable and the rollback the same each time, and it can run the checks for you. It also makes a mistake faster and wider. Test the script as you would a rollback, and run it in waves.

Day to day

At Practitioner level, a Network Engineer or Cloud Network Engineer, you write the plans others run, and sometimes run yours with a colleague checking.

Before the board. Write the plan with the eight parts. Capture the baseline on a quiet day and use it to set the post-check lines. Time the rollback on a lab or quiet device and write the figure down. Read the plan aloud to the person who will check you, and change what they could not follow.

The day before. Re-run the pre-checks: if the saved configuration or the baseline has moved, the plan is out of date. Confirm that you and your checker are both free, and that whoever may call the change off can be reached. Tell the people the plan says to tell.

In the window. Keep a log with the time of each step as you go. Run each post-check as written and say the result aloud to the checker. At the decision time, say the decision aloud, whichever way it goes. If anything arises that the plan did not foresee, stop and agree what to do, before doing it.

After. Rerun the checks in daylight. Attach the baseline, the outputs, the log and the decision to the record, and close it only then. Note what the night taught you: a check that was ambiguous, a step that overran, a rollback figure that was wrong.

Monthly. Read the month’s change records against their plans. Which checks never failed? A check that has never failed in a year may be unable to. Which windows ran over?

Quarterly. Run a rollback drill on a real device pair, and re-time every rollback that supports a recurring change.

When it breaks. If a change goes wrong and the rollback fails too, you are in an incident. Stop changing things, say so, and move to incident management. Write down afterwards which part of the plan let it happen.

Where changes go wrong

A check that cannot fail. A ping over the old path, or a dashboard that shows the link up. The change is declared a success against evidence that was never about it.

A rollback that has never run. It restores the routes and not the access list, or it needs a software version the device no longer has.

No decision time. The plan says “we will see how it goes”, and at 02:40 nobody remembers who decides.

A window filled with steps. The steps use the whole window, and the first surprise leaves no room to undo anything.

Extending in silence. The window is stretched on the night and the board, the branches and the auditor are told afterwards.

BY ORG SIZE
STARTUPunder 30 people

There is no board, and probably no checker. One engineer changes the firewall and the office router on a Friday evening, and the plan lives in their head. A written plan is still worth ten minutes: save the configuration before you start, write the one check a customer would notice, and keep a way back that does not depend on the connection you are changing. If a second person exists, even by phone, let them hold the decision time. The risk is the change that only its author could undo.

SCALE-UP30 to 300

The first formal process appears, and it is often a form. A template with the eight parts, a baseline and a timed rollback does more good than a board that meets rarely. Pick a standard set of post-checks for the common changes, so each new plan starts from checks that already work. Name who may call a change off. The danger is a process copied from a bank, with approvals and no tests, which gives the paperwork of safety without the checking.

ENTERPRISE300 and up

A change advisory board meets weekly and hundreds of changes a month pass through it. The challenge is making the plan, not the meeting, the thing that is reviewed. Standardise the template and the post-check library, classify routine changes as standard so the board’s time goes to the risky ones, and report overruns and failed rollbacks the same way everywhere. Ask what the board catches that the plan did not. Where the answer is nothing, the board is theatre, and where it is a missing rollback, it is working.

ARTEFACT Write a change plan with a rollback and a test ~50 MIN
YOU PRODUCEA change plan with scope, five post-checks with pass, fail and middle lines, a timed rollback, and a decision time

Template

# Change plan: <title>
Driver · Checker · May call it off · Board date · Window (start to end)

## Scope
Changes: <devices, policies, sites>
Must stay the same: <paths, routes, services>

## Baseline (captured <date and time>)
<the figures for each check, taken from a normal period>

## Steps
| Time | Step | Done by |
|---|---|---|

## Post-checks
| Check | Measured how and from where | Pass | Middle band and rule | Fail |
|---|---|---|---|---|

## Rollback
Method · Saved state kept at · Tested on <device, date> · Takes <min> · Its checks take <min>
Cannot undo: <effect> -> <what we do>

## Decision time
Window end <time> - rollback <min> - checks <min> = <time>
At that time: all checks pass, or we roll back.

## Communication
Before: <who> · During: <who> · After: <who>
WORKED EXAMPLE

Northmere Bank, a Saturday window, 22:00 to 02:00 (240 minutes). Ochigbo drives and Rutger checks. The change is a software upgrade on the head-office internet firewall pair. The head of IT infrastructure may call it off. The board approved the plan on Tuesday.

Scope. Changes: the two firewalls’ software. Must stay the same: internet banking logins from outside, the tunnels to the hubs, the rules on both units.

Steps. 22:00 baseline. 22:15 upgrade the standby unit, 30 minutes. 22:45 check it. 23:00 fail over to it. 23:05 post-checks. 23:20 decision one. 23:20 upgrade the other unit. 23:50 final checks, to 00:10. Steps and checks end at 00:10, which is 130 of 240 minutes, a little over half.

Post-checks.

Check Pass Middle band and rule Fail
Pair in sync, both units healthy Yes None Anything else
Session count against baseline of 48,000 43,200 to 52,800 (within 10%) 36,000 to 60,000: wait 10 minutes, recheck once; still in band is a fail Outside 36,000 to 60,000
Internet banking test login from outside 5 of 5 succeed None Any failure
Hub tunnels All up None Any down
New denied flows in the log None in the top ten One: read it before deciding Two or more

Rollback. After the first unit: fail back to the unit still on the old software, 5 minutes plus 10 of checks. After both: downgrade both, tested on the lab pair at 60 minutes, plus 15 of checks. Decision time after both: 02:00 less 75 minutes is 00:45. Final checks end at 00:10, which leaves 35 minutes.

Cannot undo. Sessions dropped at failover: the banking team is told at 22:50 that users may sign in again.

Now you

You are Ochigbo. On Sunday between 01:00 and 05:00 (240 minutes) you must change the DNS resolver addresses that 60 branch routers hand out to their branch’s computers, moving them from the old resolvers to two new ones. The old resolvers stay up for a month, so both sets answer. A branch router takes 2 minutes to change and 2 minutes to change back, one after another. Each wave needs 10 minutes of checks, and so does a rollback. The branches hand out addresses with an eight-hour lease, so computers pick up the new resolvers only as their leases renew, from about four hours later. Eight branches have no test computer, and nobody is on site at night. A branch cannot resolve names if its computers are given a resolver address they cannot reach. Rutger checks, and the board needs the plan by its meeting on Monday afternoon. Write the plan. Choose the waves, and show that a rollback of the wave in progress fits inside the window.

Self-check

DECIDE

Ochigbo and Rutger are moving 14 of Northmere's branches onto a new provider circuit, in a window from 22:00 to 03:00. It is 02:20. The first four post-checks pass. The fifth, the region's ATM approval rate over the last 15 minutes, should be at least 99%, and reads 36 approved of 38, which is 94.7%. At night two declines could be wrong PINs or a misrouted path, and the plan does not say what to do. The rollback is tested at 20 minutes plus 10 minutes of checks, so the decision is due by 02:30. Rutger notes that the payments team's test card can send ten test transactions through the region's ATM switch link in about five minutes. What do they do?

READING
  1. BOOK
    The Practice of System and Network Administration, 3rd edition, Volume 1 Thomas A. Limoncelli, Christina J. Hogan and Strata R. Chalup, 2016

    The general text for the job. Read its change management and maintenance windows chapters against your own plan template and see which of the eight parts you leave to memory. Read: Chapter 32, Change Management, and chapter 34, Maintenance Windows.

  2. DOC
    RFC 6241: Network Configuration Protocol (NETCONF) R. Enns, M. Bjorklund, J. Schoenwaelder and A. Bierman (eds.), 2011

    The standard behind the device that undoes a change by itself. Read section 8.4 so you know what your platform's timed rollback does when a session ends, and test it before relying on it. Read: Section 8.4, the confirmed commit capability.

  3. DOC
    Canarying Releases Google, in The Site Reliability Workbook, 2018

    A software chapter on testing a change on a small share first and choosing the metrics to judge it by. The thinking about picking checks that can fail transfers directly to a network wave. Read: Chapter 16, the sections on selecting and evaluating metrics.

  4. POST
    Cloudflare outage on June 21, 2022 Cloudflare, 2022

    Cloudflare's own account of an outage that affected 19 data centres. Read it as a case of a change that reached many locations, and ask what your own wave plan would have limited.

All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.