Providers, circuits and vendors
How to order a circuit so the paper says what you need, read a service level for what it does not promise, write the escalation path before the fault, and decide at renewal what a missed month is worth
Your circuit contract promises 99.5% availability each month, and credits if the provider misses it. The circuit is down for 4 hours in a 30-day month, as your own monitoring shows. What do you have?
A circuit is a service you rent, not a cable you own. Someone else owns the fibre, the equipment at both ends and the help desk, and what you own is the paper that says what you bought and the path you follow when it fails. This chapter is about that paper and that path, from your side. How the provider runs its network is its business. Which of the techniques behind it you need (routing across the handoff, translation, tunnels) is taught in the Networking path and the Networking and Cloud Networks course, which is planned.
Two companion topics sit elsewhere. For the vendor relationship in general, with exit clauses and who pays when it goes wrong, see Contractors, outsourcing and vendors. For how an operations centre raises and chases a ticket, the raising-a-fault chapter in the NOC engineer track is planned. Here the angle is the engineer who orders the circuit and lives with it.
All prices, credits and outage figures in this chapter are illustrative, not benchmarks from any real provider.
The model: four things you buy
Every circuit is four things, and a contract can be strong on one and silent on another.
The path. A physical route between two places, the equipment that lights it and the interface it hands to you. You care about capacity, the type of handoff (often an Ethernet port), and where the fibre goes.
The promise. The service level: what is measured, over what period, by whom, and what the provider owes when it misses. It is a commercial promise, not a guarantee that the circuit stays up.
The people. A help desk, an escalation ladder, an account manager. When the path fails, the people decide how long you wait.
The way out. The term, the renewal rules, the notice period and whatever lets you leave when the promise is broken. Most buyers read this last and need it first.
An order that covers the path and the price and leaves out the other three is the usual cause of the Tuesday morning in the Why.
Ordering a circuit
Write the order as a table before you talk to a sales team, so quotes arrive in the same shape and can be compared. The fields:
| Field | What to write | Why it matters |
|---|---|---|
| Purpose | What traffic it carries and what stops without it | Sets how much availability is worth paying for |
| Endpoints | Both addresses, the room and the rack, and who gives access | The far end is often a building you do not control |
| Capacity | What you need now and in two years | Upgrades are slow; ask whether the same circuit can be raised and at what price |
| Handoff | Interface type, speed and who supplies the cable | A wrong optic or a wrong port type costs weeks |
| Addressing | The subnet on the link and the ranges you will route | The provider may propose a range that collides with yours |
| Route | The physical route and the building entrance, in writing | The basis of any claim of diversity |
| Service level | Availability, restore time and what counts | See below |
| Lead time | The provider’s date and what could move it | New fibre often takes weeks or months; ask, because it varies |
| Term and exit | Length, renewal rules, notice and exit rights | See renewal |
The addressing row deserves care. A provider’s default handoff range can sit inside your own space. Compare it against the plan before you sign, as An addressing plan describes, and keep the link ranges in the reserved block for links. At Crustwell the plan gives head office 10.10.0.0/16, Agbara 10.20.0.0/16, the second factory 10.30.0.0/16 and the cloud ERP 10.50.0.0/16, and head office keeps 10.10.255.0/24 for links and loopbacks. A provider that proposes a handoff inside 10.10.9.0/24 is proposing a collision with the servers, and the order is the cheap moment to say so.
Treat the order like a change. The cut-over has a plan, a window and a rollback, and the old circuit stays up until the new one has passed its post-checks. Changes: the plan, the window and the rollback shows how.
Service levels: what 99.5% means
A service level is written as a percentage, and the percentage hides the minutes.
| Monthly availability | Downtime allowed in a 30-day month (43,200 minutes) |
|---|---|
| 99% | 432 minutes (7.2 hours) |
| 99.5% | 216 minutes (3.6 hours) |
| 99.9% | 43.2 minutes |
| 99.99% | 4.32 minutes |
Read the clause for six things before you accept the number.
- Who measures. Often the provider, from its own monitoring. Yours can differ, and the contract decides whose count wins. Ask for the right to dispute.
- When the clock starts. From the moment the circuit fails, or from the moment a ticket is opened? The two can be an hour apart.
- What is excluded. Planned maintenance, faults on your side, and events outside the provider’s control are common exclusions. Ask what notice maintenance needs and whether an overrun counts.
- What counts as down. A circuit that is up but dropping 20% of packets may count as available. The percentage covers a full outage, not a poor link, unless the contract adds loss or delay limits.
- Restore time. Availability is a monthly average. A separate promise to restore within a stated number of hours is the one that matters in the middle of a fault.
- The remedy. Usually a credit, a share of the month’s fee, capped, and claimed by you within a stated window. SLOs in practice makes the same distinction from the other side: an objective you set and manage is not the agreement a customer can hold you to, and Google’s SRE book separates indicators, objectives and agreements for that reason.
Then do the arithmetic against your own service. If a circuit at 99.5% is the only way a service reaches its destination, that service cannot be more available than the circuit, however well you build everything else. Your own objective for the service has to start from that ceiling, and the only ways to raise it are a second path or a better promise.
Diversity: the question after the number
Two paths improve availability only if they fail separately. If each has 99.5% availability and they fail independently, both are down at the same time for about 0.0025% of the month, roughly a minute in 43,200. That is the arithmetic that sells second circuits. The word doing the work is independently.
Paths stop being independent in ordinary ways: the same duct along the same road, the same building entrance, the same power feed or the same upstream exchange. Two providers can rent fibre in one duct. One provider selling you two circuits can send both over one route. So ask for the route in writing, and for the entrance into each building, and put the answer in the order. Cloud providers publish their own advice for their private links, and AWS’s resiliency recommendations for Direct Connect describe separate connections ending on separate devices in more than one location as its highest model, and say it targets a 99.99% service level only when the customer meets the conditions in the agreement. That is the same lesson from another vendor: the number belongs to a topology and a set of conditions, not to a product name.
The escalation path
An escalation path is a table you write before the fault. It names who opens a ticket, when, with what, and who you call when nothing happens. Its parts:
- The opening rule. A confirmed fault gets a ticket within a stated time, 15 minutes in the example below, by one named role. Do not let two people each assume the other has called.
- The evidence pack. Circuit ID, time of first loss in one time zone, interface state and error counters on your side, a ping or trace from each direction, and what you have ruled out. Provider agents close tickets as no fault found when the evidence stops at “it is down”. Troubleshooting a live fault shows how to build it.
- The provider’s ladder. The help desk, then a duty manager, then the account manager, each with a number and a time limit: no engineer assigned in 30 minutes goes up one level, for instance. Get the ladder from the provider in writing and test it once a quarter.
- The far end. If the circuit joins you to a carrier or a partner, a third party can see the problem from their side. Tell them when you open the ticket. At Wrenpost, Lumora Mobile’s operations centre is the other end, and the Interconnect chapter in the mobile networks course shows why a link between two networks needs a named contact on each.
- Inside the company. Who is told at 60 minutes, at 2 hours, and who decides to send customers a notice. The person who owns the money for the circuit should hear about a long fault from you before the provider’s report.
- Decision times. At what point you stop waiting and move traffic to another path, if there is one.
An escalation path nobody has used is a guess. Call every number once a quarter and fix the ones that do not answer.
Renewal: where the leverage is
The date the contract renews is the only time the provider needs something from you. Most buyers arrive at it with the provider’s offer in their inbox and no plan. A better sequence runs backwards from the date.
Find the notice period. Many contracts renew automatically for a full term unless you give notice a stated number of days ahead, often 60 or 90. Read yours. Missing the notice date can cost a year or more.
Build your own record. Your monitoring log of every outage, with start and end times in one time zone, against the provider’s monthly report. Where the two differ, find the reason: the clock start, a maintenance exclusion, a difference in what counts as down. Claim the credits the contract allows, within the claim window.
Count what the outages cost. Not the credit: the cost to you. Messages delayed, customer notices sent, hours of staff time. The credit is a price rebate. The cost to you is what the decision should weigh.
Get a second quote. Even if you will stay. It tells you what the market charges, and what a different provider will write about route and service level.
Choose the terms, then the price. Several terms are worth more than a discount: a shorter term, a clause that lets you leave without penalty after repeated misses, a written route, a restore-time promise with a bigger credit. Longer terms lower the monthly fee, and they also lock in the provider’s record.
The options at renewal are four, and each is right somewhere. Renew and take the credits when the failures were one-off and the cause has been fixed. Add a second provider when the failures come from a single path you cannot change. Move when the provider’s response and the route are the problem and a competitor offers both in writing. Renew for a short term when you expect to change anything soon, such as a site move or a new design. Contractors, outsourcing and vendors covers the exit side in general; the Decide at the end is a version of this for Wrenpost.
Where practitioners disagree
One provider or two. Two providers protect against one provider’s failures and double the contracts, help desks and invoices. One provider with two diverse routes is cheaper and leaves you exposed to its billing, its staffing and its core. Most teams that carry money or one-time passcodes choose two, and most small teams choose one and accept it.
Long term for a lower price or short term for the exit. A three-year price is attractive in a year when the budget is tight. A one-year term costs more and keeps your options. The deciding question is how likely you are to change the circuit.
Credits or exit rights. Credits are easy to negotiate and do little. A right to leave after two misses in six months is harder to get and is the clause that makes the provider care.
Dedicated circuit or internet VPN. A leased circuit has a defined path and a promise. A VPN over ordinary internet is cheaper and has none. Many teams use the circuit as primary and the VPN as a slower fallback. That choice belongs to the design, and the chapter on network strategy and budget takes it up.
Day to day
A circuit takes little of the week until it fails, and then it takes all of it. The routine keeps the failure cheap.
On a fault. Confirm loss from your side, open the ticket within the stated time, attach the evidence pack, tell the far end, and note the times as you go. Keep a timeline: it is the record you will need for the credit claim and for the renewal.
Monthly. Compare the provider’s availability report with your own log. Where they differ, write to the provider with the difference and the evidence. File credit claims inside the claim window, and write the date the window ends on your calendar when the month closes. Hold the monthly service review with the provider if the contract has one.
Quarterly. Test the escalation path by calling each number, reading the contacts, and checking that the evidence pack still matches your tools. Test the failover on a quiet evening if there is a second path, as a change with a rollback. Check the plan for the link addresses and the circuit register: ID, provider, capacity, endpoints, term, notice date.
Calendar. Put the renewal date, the notice date and a date 120 days before the notice date in the team calendar. The first is when the contract renews, the second is when you lose the right to leave, and the third is when you start collecting quotes. A circuit that renews by surprise is a decision somebody else made for you.
Meetings. The weekly change review sees every circuit order and cut-over as a change. The monthly provider review is the place to raise a pattern. The renewal review, with whoever signs the spend, happens before the provider’s offer, not after.
Where it goes wrong
The register is a spreadsheet nobody opens. The circuit ID is not at hand when the help desk asks. Keep it where the on-call looks.
The ticket opens late. Each person waits for the other to ring. Name the role.
The provider’s count wins by default. You never logged your own, so the dispute has no evidence.
Diversity on paper. Two circuits and one duct. The first cut proves it.
The credit is mistaken for the remedy. The invoice shrinks and the next outage arrives on schedule.
The renewal date passes. Auto-renewal for a full term on the same terms, because nobody had the notice date.
One voice on the far end. The carrier at the other end can see its side of the fault, and nobody told it.
One circuit, probably from whoever the office landlord or the cloud provider recommended, and nobody whose job it is. Keep a one-page register: provider, circuit ID, help desk number, term, notice date. Write the escalation path as five lines on the same page. Check the contract for one thing before signing: how to leave. The most useful single step is a calendar entry 120 days before the notice date, so the renewal is a decision and not a surprise.
Several circuits, one or two providers, and a first outage that cost real money. Build the register, the evidence pack and the escalation path, and start comparing the provider’s reports with your own log each month. Put renewals in the calendar and ask for a second quote on any circuit that carries something customers see. This is the size at which a second provider on the critical link begins to pay for itself, and at which one named engineer needs the job.
Dozens of circuits, several providers, and a procurement team that signs the contracts. The problem is consistency and leverage. A central register covers every circuit, standard service-level and exit terms go into a template that procurement uses, and a quarterly provider review looks at misses across all sites. The network team feeds procurement its own outage log, because the provider’s report suits the provider. Expect negotiations to involve legal, finance and a regional account manager, and set the escalation path as a named ladder.
Template
# Circuit order: <purpose> · <date> · owner: <role>
Traffic and what stops without it: <text>
| Field | Ask |
|---|---|
| Endpoints | <both sites, room, access contact> |
| Capacity | <now>, <in two years>, because <reason> |
| Handoff | <interface, speed, who supplies the cable> |
| Link addressing | <proposed range> checked against <plan row>: <ok or collision and fix> |
| Route and entrance | <written route for each end> |
| Service level | <availability %> = <minutes allowed in a 30-day month>; measured by <who>; clock starts <when>; excluded <what>; restore within <hours> |
| Lead time | <date and what could move it> |
| Term and exit | <months>, notice <days> before <date>, exit after <n> misses in <months> |
## Quotes compared
| Provider | Monthly fee | Term | Service level | Route | Restore time |
|---|---|---|---|---|---|
## Escalation path
Open the ticket: <role>, within <minutes> of confirmed loss.
Evidence: <list>.
| Level | Who | Number | Move up if |
|---|---|---|---|
Far end told: <who, when>. Inside the company: <who at 60 minutes, who at 2 hours, who decides on a customer notice>.
Last tested: <date>. Renewal date: <date>. Notice date: <date>. WORKED EXAMPLE
Wrenpost, a second circuit to Lumora Mobile, ordered by Sodiq with Jaya, the head of infrastructure, who signs the spend. The first circuit costs ₦850,000 a month and failed its 99.5% target in two months running, with a cut on the same duct both times.
| Field | Ask |
|---|---|
| Traffic | Messages to Lumora subscribers, including one-time passcodes. Without it they queue and retry on the first circuit’s repair |
| Capacity | 100 Mbit/s now, 200 Mbit/s in two years, because message volume grows with customers |
| Route | A different road and a different entrance to the building from circuit one, in writing with a route map |
| Service level | 99.9% = 43.2 minutes in a 30-day month; the provider’s clock starts at first loss; restore within 4 hours |
| Fee and term | ₦780,000 a month, 24 months, so ₦18.72m in all; exit without penalty after two misses in six months |
Escalation path. Sodiq’s on-call opens the ticket within 15 minutes of confirmed loss. Evidence: circuit ID, first loss in UTC, interface counters, a ping from each side. Levels: help desk; duty manager if no engineer is assigned in 30 minutes; account manager at 2 hours. Lumora’s operations centre is told when the ticket opens. Jaya is told at 60 minutes. Last tested: quarterly.
Result. With two independent paths at 99.5% each, both are down together for about a minute in a 30-day month. That figure holds only if the route is truly separate, so the written route is the line the order is conditional on.
Now you
You are a network engineer at Crustwell. The second factory has used an internet VPN to head office since the acquisition, and the head of IT infrastructure has approved a leased circuit to carry ERP traffic to the cloud ERP through head office. The second factory has 517 devices and its IT lead is your contact there. Quotes: provider A offers 200 Mbit/s at ₦620,000 a month on 36 months, 99.5% monthly, restore in 8 hours, and its fibre uses the same duct into head office as the existing internet line. Provider B offers 200 Mbit/s at ₦690,000 a month on 24 months, 99.9% monthly, restore in 4 hours, by a different road. Lead time is ten weeks for A and twelve for B. Complication: B’s default handoff subnet is 10.10.9.0/30, which sits inside head office’s server subnet 10.10.9.0/24, and the ERP administrator needs the factory’s servers to reach the cloud ERP at 10.50.0.0/16 when the circuit opens. Produce the order, compare the two quotes and write the escalation path, including who at the factory, at head office and at the provider is called.
Self-check
You are Sodiq. Wrenpost's single circuit to Lumora Mobile has missed its 99.5% monthly target twice. In September your monitoring shows 310 minutes down and the provider counts 232. In October you show 250 and the provider counts 205, which meets the target because it excludes a 45-minute maintenance overrun. Both outages were a cut on the same duct, and about 61,000 and 48,000 messages were delayed by more than ten minutes. The credits are 5% of a month's fee, ₦42,500 each. The provider offers renewal at ₦850,000 a month for 36 months, or ₦935,000 for 12. A second provider offers a circuit on a different route at ₦780,000 a month for 24 months. Jaya asks what you recommend.
- BOOK The Practice of System and Network Administration (3rd ed.) Thomas A. Limoncelli, Christina J. Hogan and Strata R. Chalup, 2017
The standard reference for running IT services, including how to buy from and manage outside providers. Read: The sections on working with vendors and on service levels; check the contents page of your edition.
- BOOK Chapter 4: Service Level Objectives, Site Reliability Engineering Google
Gives the vocabulary for reading a provider's service level as an agreement, and for setting your own objective beneath it. Read: The terminology section, which separates indicators, objectives and agreements.
- DOC AWS Direct Connect resiliency recommendations Amazon Web Services
A vendor's published model of separate connections in more than one location, and the conditions under which it states a higher availability target.
- DOC AWS Direct Connect Resiliency Toolkit Amazon Web Services
Shows how a cloud provider's own ordering tool is built around resilience models, which is a useful pattern for your own circuit order.
All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.