Delivery and planning
A quarter is a capacity budget, not a wish list: subtract what the team does not control, commit below the line, name the slip you expect, and report it the week its tripwire fires
Your team has seven engineers and the quarter has thirteen weeks: 91 engineer-weeks. Last quarter about a fifth of the team's time went on unplanned work, one engineer is on call each week, and there are leave and public holidays. Roughly how much project work should you commit to?
As an engineering manager you own two delivery documents: the quarter’s plan for your team, and the reports that tell people how it is going. The product manager owns what the team works on and why; prioritisation and saying no is their side of it. Your side is how much the team can do, in what order it can safely be done, what could stop it, and when the people relying on it will hear bad news. The organisation’s annual plan and its run, grow and transform split belong to the head of engineering and are taught in engineering strategy and planning. Your quarter is one team’s slice of that plan, made honest.
The model: a quarter is a capacity budget
Start with the number nobody can argue with: engineers times weeks. Seven engineers over a thirteen-week quarter is 91 engineer-weeks. That is the gross figure, and planning against it is the most common mistake new managers make. Then subtract, in this order, everything the team does not choose.
| Deduction | Where the number comes from | Typical failure |
|---|---|---|
| Leave and public holidays | The leave calendar and the public holidays in each engineer’s country | Forgotten for distributed teams with different holidays |
| On-call | Your rota: if the primary does no project work, one engineer per week | Assuming the on-call engineer still delivers half a ticket |
| Unplanned work | The share of tickets or time tagged unplanned over the last two quarters | Guessed instead of measured, and guessed low |
| Mandated work with a fixed date | Scheme changes, regulatory deadlines, a vendor retiring an API | Left out because nobody chose it |
| Onboarding and hiring | Interviews you have scheduled, new joiners, their buddies | New hires counted at full capacity from day one |
What remains is plannable capacity. It is often around half the gross number, and that is not a failing of the team; it is what running a live system costs. The Google SRE book’s chapter on dealing with interrupts recommends that the primary on-call engineer does on-call and nothing else, so that the rest of the team can concentrate. Plan that way and count the on-call engineer as zero. Keeping that rota humane is the subject of on-call and incidents for managers.
Measure unplanned work before you deduct it. Ask the team to tag tickets planned or unplanned for a month if they do not already. The first measurement is usually higher than anyone guessed, and that alone changes the conversation with your director.
Then commit to less than the plannable number. A common rule of thumb is to commit about 80% and hold the rest as buffer and stretch. The reason is queueing, not caution. Don Reinertsen’s The Principles of Product Development Flow argues that product teams ignore the queues their work sits in, and that queues grow sharply as utilisation rises. In the simplest queueing model, average waiting time is proportional to utilisation divided by spare capacity: at 80% that ratio is 4, at 90% it is 9, at 95% it is 19. The same effect is taught for servers in backpressure, where a backlog at 100% utilisation never drains. A team is not an M/M/1 queue, but the shape holds: a team planned to the last hour turns every surprise into a delay on the plan.
Work in progress and Little’s law
The second lever is how many things the team works on at once. Little’s law, a result from queueing theory published by John Little in 1961, says that in a stable system average time in progress equals average work in progress divided by average throughput. If your team has twelve items in progress and finishes four a week, an item takes three weeks on average. Halve the work in progress to six at the same throughput and the average drops to a week and a half, with no one working harder.
This is why limiting work in progress, the core practice of kanban, finishes things sooner. It is also why a team running five projects in parallel with seven engineers finishes all five late. Will Larson’s model of four team states, in the reading, names the team that is treading water: it keeps up with demand but cannot pay down debt or innovate. His fix is to consolidate the team’s effort to finish more and reduce concurrent work. In a quarterly plan that means a ranked list of two or three bets, started in order, rather than five started together.
Estimating the quarter: ranges, from your own history
How estimates are made and why they slip, from story points to the cone of uncertainty, is covered from the PM’s side in working with engineering. Read it. Your job as the manager adds three things.
Get ranges, and keep them. Each bet in the plan carries a low, likely and high figure in engineer-weeks, from the tech lead and the engineers who will build it. Put the likely figures above your commit line and check that the high figures still fit inside plannable capacity. If they do not, either the plan or the bet is too big.
Use the team’s own history. The best reference class for your team is your team. Count how many items it finished per week over the last two quarters and how long items of each rough size actually took. A forecast made from throughput, counting finished items, needs no story points and is hard to argue with. Joel Spolsky’s evidence-based scheduling, linked from the PM chapter, runs the same idea as a Monte Carlo simulation.
Do not trade people for months. Brooks’s essay The Mythical Man-Month makes the point in its title: men and months are interchangeable only for work with no communication between the people doing it. Software is not that work. Brooks’s law, that adding people to a late project makes it later, follows. A new joiner in week five is a cost to the team for several weeks before they add anything; count them at half capacity at best, as engineering strategy and planning advises.
Sprints, kanban and cycles
Every team picks a cadence, and the choice should follow the shape of the work rather than fashion.
| Method | How it plans | Fits | Breaks when |
|---|---|---|---|
| Scrum sprints | Commit to a set of items every one or two weeks, then review and retrospect | Stable teams with mostly planned work | Interrupts take a large, uneven share, so every sprint misses |
| Kanban | A continuous flow of items with explicit WIP limits per stage | Interrupt-driven and operational work | Nobody looks up from the board at the quarter’s bets |
| Shape Up cycles | Bet on shaped pitches for six weeks with a fixed appetite, then two weeks of cool-down | Small senior teams who can protect their time | The team also carries on-call and customer escalations |
Ryan Singer’s Shape Up is the clearest statement of the protected-time position. Basecamp runs six-week cycles followed by a two-week cool-down with no scheduled work, does not extend a project that runs out of time by default, and argues that bugs are not automatically more important than planned work. That works for a team whose interrupts are rare. Most teams that run a payments or payroll system cannot promise six interrupt-free weeks.
For those teams, the SRE book’s answer is better than any method: separate the interrupts from the project work. It recommends that tickets are a full-time role for a manageable period, that the load is not spread across the whole team, and that time is polarised so each engineer knows whether they are doing project work or interrupts that day. In practice one or two engineers rotate onto an interrupt role, working a kanban board with a WIP limit, and everyone else plans in sprints or cycles against capacity that already excludes them. The interrupt log then becomes the evidence for which causes to fix, which is how the share of unplanned work comes down next quarter.
Risks, tripwires and the slip you report early
A risk list that says “dependency on the bank” is decoration. A useful risk entry has five parts: what could happen, what it would cost the plan in weeks, what you are doing now to make it less likely, a tripwire, and who hears about it when the tripwire fires.
A tripwire is a condition with a date, decided in advance. “Partner bank sandbox access by the end of week 3; if not, same-day settlement slips one week for each week of delay, reported in that week’s update.” It does two things. It turns a vague worry into a test you will pass or fail on a known day. And it settles the hardest question before emotions are involved: when do I tell people? You already decided.
Find the risks with a pre-mortem, Gary Klein’s technique from his 2007 Harvard Business Review article: the team imagines the quarter has already failed and writes down why. People who would not raise a doubt in a planning meeting will write one under that framing. Keep the three to five risks that would cost most, give each a tripwire, and name in the plan the slip you think is most likely. Naming it in advance is not pessimism. It tells your director you have looked.
Brooks’s chapter on how projects get late, “Hatching a Catastrophe”, gives the two rules that make tripwires work. Milestones must be concrete and measurable, defined so sharply that nobody can argue about whether one has been met, because a task reported as 90% done for half the project hides the slip. And the boss must not act on problems the manager can solve, so that managers report honestly; he keeps status-review meetings separate from problem-action meetings. Shape Up’s hill charts, in the reading, make the same point visually: a piece of work is either still uphill, working out the approach, or downhill, executing, and a dot that does not move is a raised hand.
When a tripwire fires, the slip report goes out that week, in writing, to the PM, your director and anyone who made a promise on the date. It has five parts: what changed, the new range for the date, what you have already tried, the options with their costs (cut scope, move the date, borrow capacity from the stretch item), and what you need from the reader. Cutting scope to protect the outcome is a joint decision with the PM; the method is in working with engineering. Writing for executives who are not engineers is covered in communication and change, and the weekly status update and managing a dependency on another team are the subject of managing across teams and upward.
What delivery metrics tell one team
Your director will see a monthly report built from the measures in delivery metrics and reporting. For one team, the DORA software delivery metrics, defined in quality metrics, are an instrument for your own improvement. DORA’s guide says they are meant to be applied at the application or service level, and lists setting them as a goal and competing against other teams among its pitfalls.
Use them as a team, monthly, for the service you own: is change lead time falling, are deploys smaller and more frequent, is the change fail rate steady? Long lead time is often a planning problem in disguise: items too large, too much in progress, or a review queue nobody owns. Two numbers of your own belong beside them: the share of unplanned work, and planned work delivered against committed, per quarter. If the second is near 100% every quarter you are committing too little; if it is below 70% two quarters running, your capacity model is wrong, and the deduction table is where to look.
Where practitioners disagree
Commit or forecast. Some managers give the business a commitment, a list the team will deliver. Others give only a forecast with a confidence level and refuse to call it a promise. The commit line in this chapter is the middle: a short list you commit to, sized to land in most quarters, and stretch work that is explicitly a forecast.
Story points or counts. Points help a stable team argue productively about size in sprint planning. They do not add up across teams, and converting them to days for one item misleads. Many teams now forecast from counts of finished items, which need no estimation meeting. Pick one, and never report points upward.
Plan a quarter at all? Shape Up teams decide six weeks at a time and keep no backlog. A team carrying contractual dates, scheme mandates or a regulator’s deadline cannot. Most teams plan the quarter in outline and the next two to six weeks in detail.
Day to day
Two to three weeks before the quarter. You build the capacity table from the leave calendar, the on-call rota and two quarters of unplanned-work tags. The PM brings the ranked bets; the tech lead and engineers bring ranges. You hold one ninety-minute planning session with the whole team, which includes a thirty-minute pre-mortem. You draft the plan, review it with the PM, and agree it with your director in your weekly one-to-one.
Weekly. On Monday the team’s planning or replenishment meeting, thirty to sixty minutes, pulls the next items. On Thursday you spend twenty minutes checking each tripwire and each bet’s position, uphill or downhill. On Friday you send a short written update: bets with a status by rule, tripwires checked, and the risks that moved. If a tripwire fired, the slip report goes the same day.
Fortnightly. A retrospective, forty-five minutes, with the interrupt log as one input: what kept pulling people off the plan and which cause you will remove.
Monthly. With the PM, review planned against delivered and the unplanned share. With the team, look at the DORA trend for your service. Tell your director what you have learned about capacity before the quarter-end review does it for you.
At quarter end. A one-page readout: committed against delivered, the slips and when each was reported, unplanned share, and what changes in next quarter’s deduction table. This is the document that makes your next plan believable.
In a normal week, delivery costs you about two to three hours: the Thursday check, the Friday update and the meetings. Planning week costs two days.
There is no quarter, no director and often no PM; the founder sets priorities in a weekly conversation. The capacity arithmetic still applies, and it is more brutal: with four engineers, one person on call is a quarter of the team, and a single customer escalation can take the week. Plan two to six weeks ahead, keep one bet in progress at a time, and give the founder a forecast as a range. Tripwires matter more here, because the founder will promise a date to an investor or a customer without asking. Tell them the day the date moves.
This is where the quarterly plan becomes real. A head of engineering is building a planning cycle, several teams share one platform, and dependencies between teams start causing most slips. Your plan is now read by people who will make promises from it: sales, finance, the PM’s leadership. Expect to measure unplanned work for the first time and to have the uncomfortable conversation when it comes in at a third. Write the tripwires into the plan your director signs, so reporting a slip is following the plan rather than confessing.
The planning calendar is set centrally, often with a template, a portfolio tool and a programme office that tracks milestones across dozens of teams. Your risk is that the official plan and the real one drift apart, with status reported as green until the last fortnight because red invites scrutiny. Keep your own capacity table and tripwires, and report status by rule rather than by mood. Dependencies may sit three reporting lines away; name an owner and a date for each one, and raise a missed date through your director the same week.
Template
# <Team> plan, <quarter>
EM · PM · Tech lead · Agreed with: <director>, <date>
## Outcomes this quarter
1. <outcome and how we will know: metric, baseline, target>
2. <outcome>
## Capacity (engineer-weeks)
| Line | Weeks | Source |
|---|---|---|
| Gross: <n> engineers x <w> weeks | | headcount |
| Leave and public holidays | - | leave calendar |
| On-call (primary does no project work) | - | rota |
| Unplanned work (<x>% of remainder) | - | tags, last two quarters |
| Mandated work with fixed dates | - | <scheme, regulator, vendor> |
| New joiners and hiring load | -/+ | <start dates, at half capacity> |
| **Plannable** | | |
| **Commit line (~80%, rule of thumb)** | | |
## Bets, in order
| # | Bet | Outcome | Low | Likely | High | Status |
|---|---|---|---|---|---|---|
| 1 | | | | | | committed |
| 2 | | | | | | committed |
| 3 | | | | | | stretch |
Committed likely total: <n>. Committed high total: <n> (must fit in plannable).
## Risks and tripwires
| Risk | Cost if it happens | Mitigation now | Tripwire (condition, date) | Who hears |
|---|---|---|---|---|
## The slip we expect
<Which bet, why, the tripwire that will tell us, and the week we would report it.>
## Reporting
Weekly written update <day> to <people>. Slip reports the week a tripwire fires.
Quarter readout: committed vs delivered, slips and when reported, unplanned share. WORKED EXAMPLE
Kitenge is a fictional merchant payments company that sells POS terminals and acquires card payments: 250 people, 75 engineers in nine teams. The Settlement team has seven engineers and an EM, who wrote this plan for Q1 2027 (13 weeks) and agreed it with the Director of Engineering for Payments.
Outcomes. 1. Top-tier merchants are paid the same day (T+0) instead of next day; target 150 merchants live by quarter end. 2. Scheme fee mismatches reconcile automatically, cutting the team’s unplanned work.
Capacity. Gross 7 x 13 = 91. Leave 5 and public holidays 4: 82. On-call, one engineer a week at zero: 69. Unplanned work 20% (19% and 22% over the last two quarters, from ticket tags): 14, leaving 55. Card-scheme mandated changes due in the quarter: 8. Plannable: 47. Commit line: 38.
Bets, in order. 1. Auto-reconciliation of fee mismatches: 8 / 10 / 14, committed, ranked first because it reduces interrupts for the rest of the quarter; one pair. 2. T+0 settlement: 18 / 22 / 30, committed, starting in week 2 with the other four project engineers. 3. Multi-currency settlement for the new market: 12 / 15 / 20, stretch. Committed likely 32, under the line; committed high 44, inside 47.
Risks. Partner bank’s T+0 sandbox: cost 1 week per week late; tripwire, access by end of week 3; the EM and the Director hear. Acquiring Gateway must add a field to authorisation records: tripwire, merged by week 5; their EM has it in their plan. Only Esi knows the reconciliation engine: she pairs on bet 1 so a second engineer can own it.
Expected slip. T+0, via the bank sandbox. If the tripwire fires, the week-3 update says so, with the new range and the option of starting with 50 merchants.
Now you
You manage Kitenge’s Terminal Software team: six engineers who build the payment app on the company’s Android POS terminals. Plan Q2 2027, thirteen weeks. Last quarter about 30% of the team’s time went on field escalations of terminal bugs, and one engineer is on call each week. The terminal OS vendor stops security updates for the old OS version at the end of the quarter, so the fleet must be migrated: the team estimates 10 to 16 engineer-weeks. The PM has told sales that offline store-and-forward mode, which lets merchants take payments while the terminal has no connection, ships this quarter: 20 to 34 engineer-weeks. Every new firmware build must pass an external test lab’s certification, which takes four to six weeks and which you do not control. One engineer starts parental leave in week 6 and is away for the rest of the quarter. Write the plan, including the capacity table, the commit line, the tripwires and the slip you expect, and say what you tell the PM about offline mode.
Self-check
You manage the Payroll team at Shweshwe, a fictional HR and payroll SaaS company for small businesses: 55 people, 16 engineers in three teams. Your team has six engineers. About 2,400 customers run payroll, and in the last five working days of each month escalations about failed or incorrect payslips take over the team. Last quarter about 40% of the team's time was unplanned, and the last six two-week sprints delivered between 45% and 60% of committed points. The revenue authority requires a new e-filing format from the start of the next tax year, about five months away. The PM wants a date she can trust. What do you change?
- BOOK The Principles of Product Development Flow Donald G. Reinertsen, 2009
The case that unpriced queues and high utilisation are the hidden cost of product development. Read the queues chapter before you plan a team to 100%. Read: The chapters on the economics of delay and on managing queues.
- BOOK The Mythical Man-Month: Essays on Software Engineering, Anniversary Edition Frederick P. Brooks Jr., 1995
Why people and months do not trade, and how projects slip a day at a time behind fuzzy milestones. Chapter 14 is the best short text on status reporting ever written for managers. Read: Chapter 2, 'The Mythical Man-Month', and chapter 14, 'Hatching a Catastrophe'.
- DOC Dealing with Interrupts Dave O'Connor, Google SRE book, 2016
Separating interrupt work from project work: a full-time ticket role, polarised time, and an on-call engineer who does nothing else. The basis for the interrupt rotation in this chapter.
- HANDBOOK Shape Up, chapter 8: The Betting Table Ryan Singer
Six-week cycles, two weeks of cool-down, no extensions by default, and the argument that bugs are not automatically urgent. The strongest written case for protected time.
- HANDBOOK Shape Up, chapter 13: Show Progress Ryan Singer
Hill charts, imagined versus discovered tasks, and why a task count cannot tell you whether a project is nearly done. Borrow the uphill and downhill question for your weekly check.
- POST Staying on the path to high performing teams Will Larson, 2018
Four team states, falling behind, treading water, repaying debt and innovating, each with its system fix. Use it to diagnose your team before you plan its quarter.
- DOC DORA's software delivery performance metrics DORA
The five metrics, applied per application or service, and the pitfalls list: metrics as goals, disparate comparisons, competing between teams. Read it before you show your team's numbers to anyone.
- POST Performing a Project Premortem Gary Klein, 2007
The one-page method for finding the risks your team already suspects but will not raise in a planning meeting. Run it in your quarterly planning session.
All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.