LEADCHAPTER 13

Managing across teams and upward

With two or three teams, most of your job is moving the right information in three directions: a weekly update your manager can act on in a minute, dependencies written down as commitments with dates, and no surprises for anyone above you

40 MINENGINEERING MANAGERUPDATED 2026-11-07
PREDICT

Your VP reads weekly updates from six managers, usually on a phone between meetings. Which first line makes yours most useful?

At practitioner level you run one team, and most of the information you need is in the room. At Lead level, as a Senior or Group Engineering Manager, you run two or three, usually through tech leads or a first-time manager. Your information arrives second-hand. Your teams depend on teams you do not manage. And the people above you, a director, a VP or a head of engineering, make promises to customers, finance and the board from what you tell them. This chapter is about the three flows that keep that working: upward, across and down.

The rest of the job at this level is covered elsewhere. Planning one team’s quarter, tripwires and the slip report are in delivery and planning, which this chapter assumes. The move from managing engineers to managing managers is in from manager to executive. Influencing decisions you do not own, the pyramid principle and pre-wiring are taught from the PM’s side in stakeholders and influence. Executive communication of hard news, such as a reorganisation or a layoff, belongs to communication and change.

The model: you own the picture between the teams

Think of your role as a junction. Information comes in from your teams, from peer groups and from above, and every piece of it has a reader somewhere else who needs it in a different shape. A tech lead’s note that the bank’s sandbox is flaky is, to your VP, a question about whether the launch date holds; to the peer manager whose team shares that sandbox, it is a warning; to your other tech lead, it is irrelevant. Forwarding it unchanged to everyone is not communication. Deciding who needs it, in what form and when is.

Each direction carries a different question:

Direction Who The question they need answered What fails
Up Your manager, their manager, the executives they report to Is it on track, what changed, what do you need from me, what should I worry about? Green until the last fortnight; problems without a proposed answer
Across Peer managers, their PMs, the teams you depend on and that depend on you What do you need from us, by when, and has anything changed? Dependencies agreed in a chat thread and never written down
Down Your tech leads and managers, through them the engineers What has changed above us, why, and what does it mean for our plan? Decisions arrive as rumour, or as orders with no reason

The most expensive failure at this level is the gap between teams. Each team reports its own work accurately, and nobody reports the joint. A launch that needs three teams and a dependency is not on track because all three teams are; it is on track if the whole path to launch is, and you are the only person whose job covers the whole path. Status that is green on the outside and red on the inside is sometimes called a watermelon report. It is rarely dishonest. It is usually an aggregation of honest local reports that nobody joined up.

The status update executives read

The weekly written update is your main tool upward, and most of them are not read past the first screen. The ones that are read share four properties.

The answer comes first. Will Larson, in How to present to executives, lists reporting status as one of the three reasons to communicate with executives, and recommends opening with Barbara Minto’s situation, complication, question and answer. For a weekly update that compresses to one sentence: what changed and what you need. “The Vietnam corridor moves from week 12 to week 13 because of the screening dependency; the recovery plan is agreed and needs nothing from you” is a complete first line. If nothing changed, say that. A reader who learns in five seconds that nothing needs them will trust the next update that says something does.

Status is set by rule, not by mood. Red, amber and green mean nothing unless they are defined, and undefined colours drift towards green because red invites scrutiny. Write the rule into the update’s footer and agree it with your manager once:

Status Rule
Green The forecast is inside the committed range and no help is needed
Amber The forecast is outside the committed date but a recovery plan exists that needs no new decision from outside the group, or a tripwire falls due within two weeks
Red The committed date or outcome will be missed without a decision from someone outside the group

With a rule, a red is not a confession. It is a request for a decision, and a good manager will thank you for it. The tripwires that move an item to amber come from the team plans described in delivery and planning.

It reports the joints, not only the teams. List the outcomes your group is committed to, not the teams. Under each, its status, what changed and the next date that matters. Then a separate dependencies section for anything another group owes you or you owe them. Your tech leads’ updates are inputs; you read them, ask the questions they did not answer, and write a group view. Do not paste three team updates together and call it a summary.

It brings a proposed answer. Larson’s advice in the same essay is that raising a problem without a proposed solution invites doubt about whether you are ready for the role. Each red item carries the options you see, their cost and your recommendation. Your manager may choose differently. They should never have to start from nothing.

Keep it to one screen, written in prose and short tables, sent at the same time every week. Length is a cost you impose on the reader; detail lives behind links. If the update takes you more than about an hour a week, a rule of thumb rather than a measured figure, the inputs from your teams are not good enough and that is the problem to fix.

Dependencies: written commitments with dates

Most slips at this level come from work your teams do not control. A dependency handled well is boring: it is written down, it has an owner on each side, it has two dates and somebody checks it every week.

Find them during planning, not during delivery. When your teams plan the quarter, ask each tech lead one question for every bet: what has to come from outside the team for this to land? Then talk to the owning team before their plan locks. A request that arrives in week three of their quarter is competing with work they have already committed; the same request in their planning week is an input.

Write each one as a commitment. A dependency register has one row per dependency: what you need, the named person who owns it in the other team, your need-by date, their committed date, their latest forecast, the slack between need-by and forecast, and the date you last confirmed it with that person. “Platform team, sometime in Q3” is not a commitment. “Sara’s team, sanctions screening support for the VND partner format, committed week 7, we need it by week 8” is. Share the register with the owning managers so the dates are theirs as well as yours.

Choose the interaction, not only the date. Apply the three interaction modes from org design at scale to each dependency. If the other team’s service already does nearly what you need, you are consuming it as a service and need a date. If it needs new design, you are collaborating for a defined period, and that may be cheaper if one of your engineers works inside their team under their review. If the thing you need is small and they are overloaded, they may facilitate while your team builds it. The worst default is a ticket in their backlog with no agreed mode.

When a dependency will miss, agree the facts before the options. The temptation is to escalate at once. The better first move is a conversation with the other team’s manager: what changed, what is their new range, and what would bring it in. Their team usually slipped for a reason that would also persuade you, such as an incident, a regulator’s request or a priority call above them. Then write one note together with the options and their costs, and send it to the people who own the trade-off, usually both your managers. Stakeholders and influence calls this joint escalation and explains why it costs less trust than going over a peer’s head. Tell your own manager the same day you learn of the miss, before the joint note is written, in two lines.

Managing up: no surprises

Managing up is not flattery or managing impressions. It is keeping your manager’s picture of your area accurate so they can do their job: defending your headcount, making promises they can keep, and giving you the context you cannot see from below.

Larson’s short essay Partnering with your manager gives the two-way version. Your manager needs to know the problems you are working on and how, your progress and workload, your goals and how you believe you are being measured. You need to know their priorities, how stretched they are and what they are measured on. He suggests keeping this in a shared document, updated as it changes, and using one-to-ones to fill the gaps rather than recite status. The written update carries the status; the one-to-one is for what does not fit in writing. How to run a one-to-one from either side is in one-on-ones and feedback.

The rule that matters most is no surprises. In Staying aligned with authority, written for staff engineers but true for managers, Larson puts it bluntly: “Nothing destroys trust faster than surprising your manager.” He suggests treating each surprise as an incident to learn from. A surprise is not the same as bad news. Bad news delivered early, with options, builds trust. The same news arriving from the head of sales destroys it, even if your update would have said it the next day.

Three habits follow:

  • Tell them first, in two lines, the day you know. The full analysis can follow. “The screening dependency will land in week 11, not week 7; that breaks the week-12 launch. I am with Sara this afternoon and will send options tomorrow.”
  • Know how they are measured. If your VP has promised the corridor to the board, a one-week slip is a board conversation. If they are measured on cost, a request for contractors is a different ask. Translate your news into their currency, as the stakeholders chapter shows.
  • Disagree in private, commit in public. When your manager decides against your recommendation, say so to them, write the decision and its reasoning down, and then carry it to your teams as your decision too. Undermining a decision you lost spends trust you will need for the next one.

Across and down: peers, tech leads and managers

Your peers are a team. Larson’s Make your peers your first team observes that many people feel they belong to no team, and argues that treating your peer group as your first team, ahead of the teams you support, builds the cooperation that dependencies need. He lists what makes it work: knowing each other’s work, knowing each other as people, someone to referee bad-faith behaviour, a culture where success is not won by capturing scarce resources, and making the commitment explicit. In practice, a peer manager whose team you depend on should hear your quarter’s needs from you in their planning week, should be in your dependency register by name, and should never learn of an escalation about their team from their own boss.

Your tech leads and first-line managers write the team picture. You now see your teams through them. Ask each for a short written note before you write your update: progress against each committed outcome, status by the same rule you use, what changed, what they need. Read it before you talk to them, so the conversation is about the questions it raises. Let them own working-level conversations with other teams; you own the commitment and the escalation. If you go around a tech lead to get status from their engineers, you teach the team that the tech lead is not the source, and you will spend the rest of the year doing their job.

Down means context, not only decisions. When something changes above you, a priority, a date, a reorganisation, your managers and leads should hear it from you with the reason, before the engineers hear it from someone else. Not everything travels down. A director’s half-formed idea about merging two teams is not news yet; passing it on creates anxiety you cannot answer. Pass down decisions and their reasons, and say plainly what is still undecided.

Where practitioners disagree

Red, amber, green or narrative. Some leaders want colours because they scan fast across many teams. Others ban them, arguing that colours get gamed and that a two-sentence narrative carries more truth. The rule-based colour plus one sentence of narrative per item gets most of both.

Shield or transparent. One school says the manager absorbs pressure from above so the team can focus. The other says hiding context from engineers makes them worse at decisions and treats them as children. Most experienced managers filter noise, such as an executive’s passing idea, and pass on anything that changes what the team should do, with the reason.

Escalate early or solve locally. Escalating a dependency early protects the date and can feel like a lack of trust in a peer. Solving locally protects the relationship and can let a slip run for weeks. Tripwires decide this in advance: when the tripwire fires, the joint note goes, whatever the relationship.

Written updates or a status meeting. A weekly meeting lets people ask questions; a written update is faster to read and leaves a record. Brooks’s advice, discussed in delivery and planning, to keep status reviews separate from problem-solving still holds. Many groups send the written update and use the meeting only for the red items.

Day to day

Monday, forty-five minutes. Your staff meeting with your tech leads and managers. Each red or amber item from last week gets two minutes; the dependency register gets ten. Anything that changed above you over the weekend goes out here, with the reason.

Tuesday to Wednesday. Thirty-minute syncs with the two or three peer managers whose teams you depend on most, fortnightly when things are calm and weekly when a dependency is close to its need-by date. You confirm each register row with its owner and update the date you last confirmed it.

Thursday by noon. Your tech leads and managers send their team notes. You read them in the afternoon, ask the questions they leave open, and check every tripwire due in the next two weeks.

Friday morning, about an hour. You write the update: the first line, the outcomes with status by rule, the dependencies, the risks that moved, the asks with dates. You send it before lunch, and post a shorter version to your teams’ channel so the engineers see what their managers see.

Weekly one-to-one with your manager. The shared document is open. You spend the time on what the update cannot carry: the risk you are not sure about yet, the peer relationship that is strained, how you think you are being measured, and what they are worried about.

Monthly. Walk the dependency register with each partner manager for the next quarter as well as this one. Ask your manager directly whether anything in your area has surprised them; if it has, treat it as an incident.

Quarterly. In planning, collect your teams’ dependencies before other groups’ plans lock, and negotiate them in their planning week. After the quarter, write a one-page readout of committed against delivered across your teams, with every slip and the week it was reported.

BY ORG SIZE
STARTUPunder 30 people

There are no layers to manage across. The other team is two engineers across the room, and the founder hears status in standup. Write things down anyway, because the founder will promise dates to investors and customers from a conversation, and nobody will remember what was said. A five-line weekly note to the founder, with what changed and what you need, is enough. If you run two small teams here, you are probably also the most senior engineer; your dependency problem is usually your own calendar.

SCALE-UP30 to 300

This is where the role appears. A new head of engineering asks for weekly written updates for the first time, a platform team starts owning shared services, and dependencies between teams become the main cause of slips. Nobody has defined red, amber and green yet, so define them for your group and offer the rule to your peers. Peer managers are new to the job too; making them your first team pays back quickly. Expect the CEO to read your update, and write the first line for them.

ENTERPRISE300 and up

A programme office runs a portfolio tool, the status template is fixed and the colours are political: a red may trigger a review you would rather avoid. Dependencies sit in other directorates with their own planning calendars, so a request outside their planning window may wait a quarter. Your update is summarised by someone else before an executive sees it, so write the sentence you want copied. Keep your own register and rules, and report by them even when the template invites green.

ARTEFACT Write a weekly status update executives read ~45 MIN
YOU PRODUCEWeekly status update for a group of teams

Template

# <Group> update, week <n> of <quarter>
<Your name> · to <manager>, cc <peers who depend on you>

**Headline:** <One sentence: what changed since last week and what you need, from whom, by when. Or: "No change; nothing needed this week.">

## Outcomes
| Outcome | Status | Committed | Forecast | What changed | Next date that matters |
|---|---|---|---|---|---|
| <outcome, not a team> | G/A/R | <week> | <range> | | |

<For each red item: options, cost of each, recommendation, who decides, by when.>

## Dependencies
| We need | From (owner) | Need by | Their commit | Their forecast | Slack | Last confirmed |
|---|---|---|---|---|---|---|

## Risks that moved
- <risk>: <what moved, the tripwire, when it fires>

## Asks
- <person>: <decision or help> by <date>

## Decisions made this week
- <decision>, <who>, <link>

---
Status rule: Green = forecast inside committed range, no help needed. Amber = outside committed date with a recovery plan that needs no new decision from outside the group, or a tripwire due within two weeks. Red = needs a decision from outside the group.
WORKED EXAMPLE

Madras is a fictional cross-border B2B payouts company: 300 people, 85 engineers, about $1.4bn a month paid out for 2,100 business customers across 38 corridors. Anika is Group Engineering Manager for Payouts: three teams, 22 engineers. Payout Rails (8 engineers) and Corridors (7) have tech leads; Beneficiaries (7) has a first-time engineering manager. She reports to the VP of Engineering. This is her week-7 update of a 13-week quarter.

Headline: The Vietnam corridor moves from week 12 to week 13. The cause is the sanctions-screening dependency on Compliance Platform, which slipped from week 7 to week 11. Sara, her director Pieter and I agreed a recovery on Thursday: two Corridors engineers work in Compliance Platform’s codebase under their review, and screening support now lands in week 9 (range 9 to 10). Nothing needed from you this week; the next decision point is week 9.

Outcomes. Vietnam corridor live for the two signed customers: amber (committed week 12, forecast week 13 to 14; the recovery plan is agreed and needs no new decision). Reconciliation rewrite on Payout Rails: green (committed week 11, forecast week 10 to 11). Bank-detail validation on Beneficiaries: amber (two weeks behind after unplanned leave, still inside the buffer, but its tripwire falls due at the end of week 9).

Dependencies. Screening support for the VND partner’s beneficiary format: owner Sara, need-by week 8, committed week 7, forecast week 9 to 10, slack minus one to two weeks, confirmed Thursday. Partner certification slot: owner the partner bank’s integration lead, moved from weeks 11 to 12 to weeks 12 to 13, confirmed Tuesday.

Risks that moved. Launch is screening plus four weeks. If screening lands in week 10, the top of its range, launch moves to week 14, outside the quarter; I will report that in the week-9 update with options.

Asks. Head of sales: tell the two customers week 13 by Wednesday; I have sent the wording.

Now you

You are a Senior Engineering Manager at Brocade, a fictional residential rentals platform: 140 people, 35 engineers in five teams, software for 900 letting agents managing 62,000 tenancies. You run two teams, 15 engineers. Leasing (8 engineers, tech lead Ingrid) is switching referencing provider; the old provider’s contract ends in week 13 and cannot be extended. At week 6, three of five milestones are done. Rent and Deposits (7 engineers, tech lead Declan) is running an open-banking rent collection pilot with 40 agents, which needs the Platform team’s payments provider upgrade. Platform committed week 5; their manager now says “week 8, maybe”. Declan has reported the pilot green every week because his own team is on schedule. Peak lettings season starts in week 9. The Head of Engineering joined six weeks ago and has asked each senior manager for a written update every Friday; the CEO reads them. Write your first one, for week 6, including the dependency register and your status rule.

Self-check

DECIDE

You are Group Engineering Manager for Payouts at Madras, a 300-person cross-border payouts company: three teams, 22 engineers. The Vietnam corridor launches in week 12 of 13; two signed customers expect it. In week 6 the Compliance Platform manager, Sara, tells your Corridors tech lead that the sanctions-screening change you need, committed for week 7, will land in week 11 because a regulator's request jumped her queue. With two weeks of integration and two of partner certification, that means launch in week 15. Your VP has not heard. What do you do this week?

READING
  1. BOOK
    The Manager's Path Camille Fournier, 2017

    The step from one team to several, written from inside it: what you stop doing, what you delegate to tech leads and how your time moves towards the people around your teams. Read: Chapter 6, Managing Multiple Teams.

  2. BOOK
    An Elegant Puzzle: Systems of Engineering Management Will Larson, 2019

    The systems view of managing several teams, with two short sections that are the core of managing up: what your manager needs to know, and how to present to people who decide quickly. Read: The sections 'Partnering with your manager' in Approaches and 'Presenting to senior leadership' in Tools.

  3. POST
    How to present to executives Will Larson, 2021

    Status as one of the three reasons to talk to executives, the SCQA opening, gathering feedback before the meeting, and why you never bring a problem without a proposed answer.

  4. POST
    Partnering with your manager Will Larson, 2017

    The two-way information your manager and you each need, kept in a shared document, with one-to-ones used to fill the gaps rather than recite status.

  5. POST
    Staying aligned with authority Will Larson, 2020

    Written for staff engineers and as true for group managers: authority is loaned, surprises destroy trust, and you build your own information flow so your sponsor never surprises you either.

  6. POST
    Make your peers your first team Will Larson, 2018

    Why peer managers, not the teams you support, should be your first team, and the five things a peer group needs. The groundwork every dependency negotiation stands on.

  7. BOOK
    The Minto Pyramid Principle Barbara Minto

    The source of answer-first writing for busy readers. Read it once and every status update you write afterwards gets shorter and gets read. Read: The part on writing: building the pyramid and the situation, complication, question introduction.

All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.