A TPM's week
Where a technical programme manager's hours go, which meetings earn a place when nobody reports to you, how a written update replaces the status round, and what gives way in the weeks before a launch
A TPM writes the programme's weekly update on Friday afternoon by messaging each of seven workstream leads and asking what changed. It takes three hours and the update is often stale by Monday. Which change fixes the most?
A TPM has no reports, no code of their own to ship and no single team’s rituals to run. The calendar fills from the outside, with a meeting for every pair of teams that has ever disagreed, and the week then becomes whatever the meetings leave. This chapter is about designing that week on purpose: what a TPM’s hours are for, which meetings earn a place, how a written update takes over from the status round, and what gives way when a launch approaches.
It builds on three other weeks. A PM’s week is built on protecting maker time, an EM’s week on the team’s flow, and a head of engineering’s week on a reserve and a drop order. A TPM’s week borrows the reserve and the drop order, and adds a problem none of them has: the people whose work you are accountable for do not report to you.
The model: you own the flow of information
Each team plans its own part of a programme well. What nobody owns is the space between the teams: who needs to know what, who must decide, and whether the date still holds. That space is the TPM’s work, and it is made of information moving between people.
Frederick Brooks gives the reason it grows faster than the programme. In The Mythical Man-Month he counts the pairs of people who must communicate as n(n-1)/2. A programme with eight parties has 28 such pairs. A TPM who tries to cover each pair in a meeting never leaves the room, so the job is to make most pairs unnecessary: a shared tracker, a written update and one place where decisions are recorded, so people learn what they need without a meeting.
Andy Grove’s High Output Management supplies the test for your hours. A manager’s output is the output of the people they influence, so ask of every block whose work it moves. An hour that gets a partner and a checkout lead to agree on one field moves two teams’ sprints. An hour spent hearing seven leads read their status moves none, because each already knew their own.
A TPM’s week holds five kinds of work, plus reserve.
Sensing. Reading the tracker, walking each workstream, reading design documents with an engineer, asking the question that shows a plan is fiction. Nobody asks you for this, which is why it is the first thing to go.
Deciding. Getting a decision made by the person who owns it: two teams that each think the other owns a piece, a partner who must pick between two designs. You rarely make these decisions. You make sure the right person makes them, with the facts, by a date.
Telling. The weekly update, the escalation note, the sponsor conversation. How to write the update and when to escalate belongs to managing across teams and upward; this chapter is about where the hours for it come from.
Programme documents. The charter, the dependency map, the RAID log (risks, assumptions, issues and dependencies) and the launch checklist. Each has its own chapter in this track; here they are a block of the week.
Coordination meetings. The ones you chair or attend. This is the row to hold a ceiling on.
Reserve. Unbooked time. A partner changes an interface, a lead says a date will move, a sponsor wants an answer by lunchtime. The reserve is for these.
Where the hours go
Here is the shape of a 44-hour week for a TPM running one programme with seven internal workstreams, one lending partner and one bank. The ranges are rules of thumb from the shape of the job, not survey data. Measure your own: sort four weeks of calendar into the rows.
| Kind of work | What is in it | Hours a week | What breaks if it goes |
|---|---|---|---|
| Sensing | Tracker, walking workstreams, reading designs | 8–10 | You report what you were told, not what is true |
| Deciding | Partner call, dependency conversations, sponsor one-to-one | 6–8 | Two teams each wait for the other |
| Telling | Weekly update, escalation notes | 4–6 | People rebuild the picture in meetings |
| Programme documents | Charter, dependency map, RAID log, checklist | 4–6 | The plan lives in your head |
| Coordination meetings | Rounds, syncs, readouts | 4–6 | They grow to fill the week |
| Reactive | Messages, requests for dates, ad hoc | 5–7 | It spreads into everything else |
| Own learning | Reading how the systems work | 1–3 | You cannot tell a real estimate from a hopeful one |
| Reserve | Unbooked, spread across the week | 4–6 | Every surprise is paid for from sensing |
The midpoints total 44. If your four-week average shows more hours in coordination meetings than in sensing and deciding together, the calendar is being designed by whoever last asked for a sync.
The meeting test
Meetings multiply in a programme because each solves a real problem once. The trouble is that no one removes them when the problem is gone. Sort every recurring meeting into one of three kinds before you decide anything.
Status. Each person reports their own workstream; the others listen. Nothing is decided. A status meeting passes the test only if it is the sole way the information can move. A tracker and a written update move the same information to everyone at their own pace, and Atlassian’s team playbook describes the same swap: an asynchronous weekly project update in place of a status meeting, with progress, decisions, risks and learnings, and a status marker such as on track, at risk or off track.
Decision. People who disagree, or who own different halves of one choice, settle it. This is worth a room, because tone, objections and the shape of a compromise do not survive in a document. It earns its place if the agenda is a list of decisions and it ends with owners and dates.
Relationship. The recurring conversation between you and another company’s integration lead. It covers contract questions, early warnings, the favour you will ask next month. A relationship meeting often looks like status and is not: the status is the cover for trust and for decisions made live. Keep it, but give it a decision agenda.
Two cautions. First, a meeting can be two kinds at once, and splitting it can be the answer: the written update carries the status, and the meeting keeps the ten minutes of decision. Second, the people in a meeting often value it for a reason you have not heard. A sponsor who likes the Wednesday steering because it is the one time they see all their heads together is telling you its real kind. Ask what it does for them before you cancel it, and offer something that does the same.
The written update
The update replaces the status round only if it is easy to write and worth reading. Four rules make that so.
Leads own their lines. Each workstream lead keeps their own rows in the tracker: status, next milestone, blockers. The deadline is Thursday noon. You do not chase. A lead whose lines are stale is visible to everyone, which does more than your reminders.
You write the judgement. One line of verdict, red, amber or green, with the reason. What changed since last week. The decisions needed, each with an owner and a date. The top three risks, from the RAID log. The forecast date for launch, with the range. A reader should be able to stop after the first screen and know where the programme stands.
One reading time. Say who reads it and how long it takes: ten minutes is a good limit. When the update reaches three pages, people skim it and the meeting comes back.
A decisions list that does not wait. The update goes weekly. A decision that cannot wait for the update goes to its owner the day it appears, with a deadline, and onto the list. The weekly cadence is a floor, not a ceiling.
Writing needs a block, as Paul Graham says of any work that needs thought: a meeting in the middle of an afternoon can break it into two pieces each too small for anything hard. Put the update’s writing in one booked ninety-minute block, with the document named, and not in the gaps. Ninety minutes is a rule of thumb for a programme of this size; larger programmes take longer, because there are more lines to turn into judgement.
Authority without reports
The update only works if people trust it and the decision list only works if owners act on it. Neither is a power you hold. You hold two things instead.
One is a record. A decision with an owner and a date, written where the sponsor can see it, is a quiet kind of pressure that does not need a threat. The other is the sponsor’s backing, used sparingly. An escalation that goes up only after the owner has been asked directly and given a date is one the sponsor will act on. One that goes up as the first move teaches the sponsor you cannot work things out below them. How to escalate without burning relationships is in managing across teams and upward; how a programme that spans companies changes the picture is the subject of programmes across companies.
Fairness runs both ways. The lead who is slow to update the tracker is usually behind on the work, not careless. Treat a stale row as the first signal that the workstream needs help, and go and ask.
Where practitioners disagree
Document or meeting? One school moves nearly everything to writing: it scales across time zones and leaves a record. The other holds that live conversation catches the thing nobody thought to write. The honest answer depends on the audience. Written for readers who will act on it, a document is fastest; for people who need to feel heard, a room is. Most programmes need both, in different proportions at different stages.
A daily stand-up for the last weeks? Some TPMs run a short daily launch stand-up from two or three weeks out, because the number of open items makes weekly rhythm too slow. Others resist, because a daily meeting recreates the status round at seven times the cost. A workable middle is a daily meeting with a written list of open launch items, where only the items are discussed and the room is the owners of those items.
How deep should you go? A TPM who reads design documents spots a fiction early. One who tries to review them is in a second job. How technical a TPM must be is the next chapter of this track, how technical TPMs must be; here, protect an hour or two a week for reading, so that your questions stay good.
Day to day
A week that works for a TPM running one programme with seven internal workstreams and a partner, with the update going out on Thursday.
- Monday. First hour: read the tracker before you talk to anyone, and note what looks wrong. Then short check-ins, fifteen minutes each, with the two workstreams that look riskiest, not all seven. Review the RAID log: any risk whose date has passed, any new one. Afternoon: read a design document or a partner’s integration note, with an engineer when you can.
- Tuesday. The partner call, with a decision agenda sent the day before. Afterwards, write down the decisions and who owns them. Dependency conversations: the two teams that disagree, together, with a date to settle.
- Wednesday. Reserve is deliberately left open. Programme documents: update the dependency map or the launch checklist. A short one-to-one with any lead whose tracker line looks stale.
- Thursday. Noon is the deadline for the leads. Early afternoon: read the tracker and decide the verdict. Book your ninety-minute block and write the update; send it before the end of the day, and send the sponsor a heads-up if the verdict has changed.
- Friday. Read replies. A thirty-minute one-to-one with the sponsor: the decisions he needs to make, nothing else. Plan next week: put the writing block and the reserve in the calendar before anyone books them.
- Every day. Triage first thing, the decisions list read once, and a short walk through the tracker before any meeting.
Fortnightly. A look at your own four weeks of calendar against the target, and at the update itself: who still opens it, who asks questions in meetings that it answers. If a reader no longer needs a section, cut it.
Monthly. A programme health review with the sponsor: the critical path and the forecast, which is the subject of the dependencies chapter in this track, dependencies and critical path, and a look at whether the meeting set still matches the work.
When it breaks. A partner slip, a resignation of a lead or a launch-week surge will break the template. Decide the drop order in a calm week: reserve first, then own learning, then documents that are not due, then coordination meetings you can send a delegate to. Do not cut sensing. It is the work that tells you the date is at risk, and it is the first thing you will want to cut. When it breaks, tell the sponsor in two lines that day. How to size and report a slip is in managing across teams and upward. The work of running a cross-team change from start to finish is in cross-team projects and migrations.
There is rarely a TPM. A founder or the most senior engineer holds a programme in their head, and the weekly meeting is the whole company. The risk is not too many meetings but none that cover the work between teams. Keep one short written note a week with three lines: what is at risk, what decision is owed, the date. If a partner or a bank is involved, keep a standing call with their one named contact, and write down what you agree on it.
This is where the TPM role is first built, and where status rounds breed: each new team adds a sync and the programmes overlap. You may be the first person to hold the cross-team view, so you build the tracker, the update and the decision list from nothing. Retire a meeting for every one you add, and agree the update’s readers and length with your sponsor early. The week is mostly sensing and deciding, and the main risk is that people expect you to run every team’s ritual as well.
Programme calendars are institutional: steering committees, change boards, quarterly reviews and compliance gates, each owned by someone with a template. Many cannot be dropped, only prepared for in writing so they stay short. You may work with a programme office whose reports differ from your update. Send one source of truth into both rather than keeping two, and use a delegate for the meetings that do not need you. Expect more up-and-across hours and fewer hours inside the teams.
Template
# My week: <name>, <programme>, week <n> of <n>
Working week: <hours> · Workstreams: <n> · Partners: <n> · Sponsor: <name>
## Meeting audit
| Meeting | Day, length | People | Attendee-hours | Kind (status, decision, relationship) | Keep, replace or cut | Replacement |
|---|---|---|---|---|---|---|
| | | | | | | |
Total attendee-hours before: <h> · after: <h> (include reading time: readers x minutes)
## The weekly update
Author: <name> · Readers: <n> · Reading time: <min> · Leads' deadline: <day, time> · Sent: <day, time>
Sections: verdict, what changed, decisions needed (owner, date), top risks, forecast
## Hours budget
| Kind of work | Target hours | Last 4 weeks (avg) |
|---|---|---|
| Sensing | | |
| Deciding | | |
| Telling | | |
| Programme documents | | |
| Coordination meetings | | |
| Reactive | | |
| Own learning | | |
| Reserve | | |
| **Total** | | |
## The week
| | Mon | Tue | Wed | Thu | Fri |
|---|---|---|---|---|---|
| Morning | | | | | |
| Afternoon | | | | | |
## Drop order when the week breaks
1. <gives way first>
2. ...
Never dropped: sensing; <...>
## Re-check on: <date two weeks out> WORKED EXAMPLE
Ojaline is a fictional online marketplace with its own delivery fleet: 1,400 staff, 300 engineers, delivering in nine cities. Its checkout offers Pay in four, lent by Owoleaf. Akua is the TPM, in week 6 of a 14-week programme to a Lagos launch (the dates are illustrative). Murtala runs the BNPL programme and is her sponsor. She works a 44-hour week.
Meeting audit. Monday workstream round, 60 minutes, eight people: 8.0 attendee-hours, status. Tuesday Owoleaf partner call, 45 minutes, six people (Akua, Rabiu, Obiomachukwu, Ezenwa and two Owoleaf engineers): 4.5, relationship and decision. Wednesday steering status, 45 minutes, six people (Murtala, four heads, Akua): 4.5, status. Friday readout for Legal and Compliance and Customer Support, 30 minutes, three people: 1.5, status. Before: 18.5.
Changes. The three status meetings go. The partner call stays with a decision agenda. Twelve people read a weekly update for ten minutes each: 2.0. Akua’s writing block is 1.5 hours. Murtala says he values Wednesday as the one time he sees his heads together, so a monthly 45-minute decisions session replaces it: six people, 4.5 attendee-hours a month, about 1.1 a week over four weeks. The leads’ tracker deadline is Thursday noon. After: 4.5 + 2.0 + 1.5 + 1.1 = 9.1 attendee-hours, a saving of 9.4 a week.
Hours budget (target; last four weeks). Sensing 9 (6). Deciding 7 (4). Telling 5 (7). Programme documents 5 (3). Coordination meetings 4 (13). Reactive 6 (9). Own learning 2 (0). Reserve 6 (2), as 90-minute blocks on four days. Total 44 either way.
Drop order. Reserve; own learning; documents not due; meetings to a delegate. Sensing is not dropped. Re-check in two weeks.
Now you
You are Akua in week 12 of the 14-week Pay in four programme at Ojaline, two weeks before the Lagos launch. Since week 7 a weekly update has replaced the Monday round, the Wednesday steering and the Friday readout; only the Tuesday partner call remains. This week the calendar has refilled. Ezenwa at Owoleaf wants the partner call twice a week, Tuesday and Friday, 45 minutes, six people each. Murtala wants a daily 20-minute launch stand-up from Monday with ten people. A launch-readiness review on Wednesday takes 90 minutes with ten people. On Thursday you attend a two-hour dry run with Customer Support. Murtala has forwarded the update to the executive team, so it now has 18 readers and runs to three pages; Tomoko says the Risk lines are always stale. Last week’s reserve was one hour of a 44-hour week. Produce the audit, the redesigned week and the drop order.
Self-check
You are Akua, the TPM for Ojaline's Pay in four launch, in week 6 of 14. Your week holds four recurring meetings that carry status: Monday's workstream round (60 minutes, eight people), Tuesday's Owoleaf partner call (45 minutes, six people), Wednesday's steering status with Murtala and four heads (45 minutes, six people) and Friday's readout for two teams (30 minutes, three people): 18.5 attendee-hours in all. A written weekly update would cover the status in all four. Murtala has said he likes Wednesday because he sees all his heads together. Tomoko, who leads Risk, says she has never missed one. What do you do?
- POST Maker's Schedule, Manager's Schedule Paul Graham, 2009
Why a single meeting can cost the people doing the work an afternoon. A TPM sits on the manager's schedule while the teams are on the maker's, so read it to place meetings where they cost the teams least.
- BOOK The Mythical Man-Month: Essays on Software Engineering, Anniversary Edition Frederick P. Brooks Jr., 1995
The source of the n(n-1)/2 count of communication pairs, and the underlying reason a programme of many teams drowns its coordinator in meetings. Read: Chapter 2, The Mythical Man-Month, on how communication grows with the number of people.
- BOOK High Output Management Andrew S. Grove
The frame for judging your hours by the output of the people you influence, and a practical view of what a meeting is for. Read: The chapters on managerial leverage and meetings.
- DOC Weekly Project Updates Atlassian Team Playbook
A short play for replacing project status meetings with an asynchronous weekly update: what to include, when to send it, and how to record status. Compare its structure with the five sections in this chapter.
All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.