Programmes across companies: partner banks, telcos, regulators
How a TPM runs a programme when the critical path goes through companies that owe you nothing: who has standing with whom, how to ask a partner for a piece you can test, how to read a partner's date, and how to press when a bank slips
Ojaline's Pay in four depends on Northmere changing Owoleaf's settlement set-up. Akua will not see Northmere's own plan. Which arrangement gives her the most reliable early warning that the change is slipping?
Most of this track has assumed that the people on your map belong to your company, or to a company with a contract that says what it owes. The harder programmes put a bank, a telco or a regulator on the critical path. Each runs by its own calendar, answers to its own customers and owes your launch nothing. This chapter is about running that kind of programme: working out where you have standing, asking for things a partner can give, reading what a partner’s date is worth, and acting when it slips.
It builds on dependencies and the critical path, which put Northmere’s change on the map with a week of float, and on the RAID log, which logged an outside approval as a dependency you cannot push. Status, escalation and bad news gave the rule for the colour and the route from sponsor to sponsor, and this chapter does not repeat them. It adds what you do before the bad news and after it. The commercial side of these partnerships is in lending partnerships; the settlement mechanics are in settlement and payouts, and Owoleaf’s place behind a sponsor bank is in direct or sponsored.
Standing: who can ask whom
In your own company, authority comes from the organisation. Across companies it comes from contracts, accounts and relationships, and it does not pass along a chain. Before you plan anything, draw who has standing with whom.
In Pay in four there are three companies. Ojaline has a commercial agreement with Owoleaf, which lends. Owoleaf has an account at Northmere and relies on it as its partner bank. Ojaline has nothing with Northmere. The map looks like this.
| Pair | What joins them | Who can ask whom |
|---|---|---|
| Ojaline and Owoleaf | The lending partnership | Akua asks Ezenwa. Murtala asks Owoleaf’s sponsor |
| Owoleaf and Northmere | Owoleaf’s settlement account and the bank’s sponsorship | Ezenwa asks Northmere’s change manager, Imole. Owoleaf’s sponsor asks the executive at Northmere who owns the account |
| Ojaline and Northmere | Nothing | Nobody. Everything goes through Owoleaf |
Two things follow. First, a request from Ojaline to Northmere is really two requests, and the first is to Owoleaf: will you ask? Owoleaf may have reasons to ask differently, or not now, because its own business with the bank is bigger than your launch. Second, the person who can help you most may be the person with the least reason to. Ezenwa leads Owoleaf’s integration work and wants the launch to succeed, but his standing at Northmere is that of a customer’s integration lead. Treat him as an ally with limits, and ask early what he can and cannot request.
Write the map into the plan. It turns “escalate to Northmere” into a route with named people at each step, and it shows the single points of failure: if Owoleaf’s sponsor is the only route to Northmere’s executive, that sponsor’s attention is a dependency of its own.
What each kind of partner has
The three outside parties in this chapter’s title behave differently, and your plan should say which you are dealing with.
A bank has a change calendar. Moving money is its main duty, and it changes its systems on a schedule, with testing queues, release slots and quiet periods. Its engineers have other customers and other deadlines, and a change for one client queues behind the bank’s own work. You cannot make the calendar faster. You can find where your change sits in it, ask for the pieces in a useful order, and agree when each piece is checked.
A telco has acceptance testing and a network to protect. Wrenpost’s direct carrier connection for Kenya, due on 1 March 2027, crosses six groups on Wrenpost’s side and a carrier’s engineers on the other. The carrier decides when its test numbers are ready, when its acceptance tests run and what traffic it allows at the start. Plan its test windows as tasks with owners on its side and ask which of them you can book before you need them.
A regulator has a queue, not a timetable. Owoleaf filed its application with the Federal Competition and Consumer Protection Commission in week 3, and the RAID log treats the reply as a dependency with a probability and a bad case. You cannot push a regulator. You can learn what a complete filing looks like, make sure yours is, record the lead time you were told, log the earliest signal that it is moving, and prepare a plan B that does not need the answer. Whether a filing is needed at all, and what it covers, is for the lender’s compliance staff and lawyers, not for you.
What the three share is that none has a reason to treat your date as theirs. A partner will help, sometimes generously, when helping costs little and the ask is clear. Your job is to make asks that fit that description.
Ask for a piece you can test
A partner’s work arrives as a large, vague item: “settlement change, weeks 5 to 9”. Such an item hides two things: what you need from it and when. Break it apart.
Take Northmere’s change. It gives Owoleaf’s settlement account a reference on every payment, one per Pay in four order, and a file the next morning that lists them, so that Ojaline’s finance team can match the money to Seller Wallet’s credits. Your programme needs two pieces of that, at different dates. The end-to-end test needs a version in Northmere’s test environment, with a test account and a sample file, by the end of week 10. Launch needs the production switch before the readiness review. They are one change to Northmere’s engineers, and two dates to you.
Splitting does three things.
It shows the real deadline. The earliest piece you need sets the date you must hold the partner to. The production switch may have weeks of room, and the test piece none.
It makes the ask smaller. “Please hurry” asks a bank to change its priorities. “Please put the test environment first” asks it to change the order of work it was going to do anyway. The second is easier to grant, and the person granting it can see what it costs.
It gives you evidence. A piece is done when something you can check works: a sample file with twenty orders, each reference matching a Seller Wallet credit. Agree the evidence when you agree the piece. “Done” from a partner then means a check that can fail, not a feeling.
This is the interface idea from the dependency chapter applied across a boundary. The contract between the companies says what the final system does. The plan needs the smaller promises inside it. Idempotency, the property that makes a retried request safe, is the sort of thing a partner integration must settle early; the idempotency lesson shows why, and Stripe’s public API documentation on idempotent requests shows how one provider describes it to the companies that build on it.
Do not mistake the splitting for second-guessing the partner’s engineering. You are not asking how Northmere builds it. You are asking what you will be able to see, and when.
Reading a partner’s date
A date from a partner carries less than a date from your own lead, for ordinary reasons. The partner’s engineer gave it before the bank’s own priorities for the quarter were set. The person who gave it may not be the person who schedules the work. And a partner has little reason to bring bad news early to a customer’s customer.
Five questions turn a date into something you can plan on.
- Who gave it, and do they schedule the work? A date from a relationship manager is a hope. A date from the person who allocates the engineers is a plan.
- What would make it late? The question from the dependency chapter works here too. Listen for the shared resources: the same engineers, the same test environment, the same release slot.
- What is the evidence, and when will I see it first? The first piece is the early warning. If the partner cannot name one, the date is a guess.
- When does the partner’s calendar close? Find the freezes, the release slots and the holidays between now and your date. A date on the far side of a freeze is a date for the slot after it.
- What do they need from us? Late partners are often waiting for you. A file specification nobody on your side has signed, or a volume forecast nobody sent, costs the partner days and shows up as their slip.
In The Mythical Man-Month Brooks has a subsection of chapter 14 called “The Other Piece Is Late, Anyway”, on how a team that is behind finds comfort in other teams being late too. It is a useful warning in both directions. Do not use the partner’s slip to hide your own, and do not let a partner use yours.
Running the partnership week to week
The mechanics are light and unforgiving.
One call, with a decision agenda. The Tuesday partner call with Owoleaf is the place where decisions are made, and the agenda goes out on Monday. When the settlement change is on the agenda, Imole joins. Keep the rest of the partner’s engineers out of status. The written update from week 7 carries status for twelve readers.
One list of shared items. Keep a short list, visible to both sides, of the pieces that cross the boundary: what, who owes it, the agreed date and the evidence. Do not share your RAID log. It holds your companies’ internal worries, some of them about the partner. Share the dependencies and the decisions, and keep each side’s risks on its own side.
Dates in writing, with evidence. After each call, send the decisions and dates to everyone on it the same day. A partner who corrects your note has told you something useful. A partner who does not reply has told you something too.
Say what you owe. Every partner has a list of things it needs from you. Write it. For Pay in four: Ignatius, the settlement analyst in Ojaline’s seller-payout finance operations (finance, not the Seller Wallet engineers), signs off the layout of the settlement file within two working days of receiving it, and Akua sends Owoleaf a forecast of orders by city each Monday from week 8. A partner who sees you keep your promises is more willing to reorder its own work.
Respect the partner’s controls. A bank’s change process, a telco’s acceptance test and a regulator’s review are not obstacles you are owed an exemption from. Do not ask a partner to skip them. Ask for sequence, for capacity, for an early look, for a date. A request that asks a bank to waive its controls puts a person at the bank in an awkward position, and it will be remembered.
Keep the tone fair in writing. Your updates can name a partner’s date as the cause of a red. They should not describe the partner as failing. The partner’s staff will read them, and the next favour depends on how they felt reading.
When a partner’s date slips
The slip arrives on a Tuesday call. You have the status rule from the earlier chapter: the colour is red if the date depends on something outside your control with no float, and you tell the sponsor first. What the rule does not tell you is what to do about it. A short sequence helps.
Get the facts the same day. Ask what moved, why, and what the new date is, from the person who schedules the work. Ask whether anything about the work itself changed, or only the slot. A slip caused by a moved team is easier to reverse than one caused by a design problem.
Recompute the path. Northmere’s change was planned for weeks 5 to 9 with one week of float. A three-week slip ends in week 12. The end-to-end test, which needed it by the end of week 10, now starts in week 13 and not week 11, which is two weeks late. The readiness review moves to week 15 and the launch to week 16. That is the charter’s latest date, with the margin spent.
Look at the pieces. Which piece is late? If the production switch has room and the test piece does not, the slip is one ask and not three weeks.
Lay out the options with their cost in weeks. There are usually four. You wait and spend the margin. You work around the partner with a manual or interim path. You drop or defer the part that needs the partner. Or you ask for something specific, through the people who have standing. The options are not ranked in advance. Each is right in some circumstances.
- Waiting is right when the new date is inside the margin and the other risks are quiet. It is wrong when it spends the last of the margin while a second risk, such as the regulator’s reply, is still open.
- A workaround is right when the manual path is safe and will be needed anyway for a while. It is wrong when it replaces the thing you most need to test.
- Dropping the feature is right when the new date is beyond the latest date, or when nothing can be split.
- Pressing is right when the slip is a matter of sequence or priority and the partner’s engineers say a narrower ask is possible. It is wrong when the delay is a real technical problem that attention will not fix.
Choose the route. An ask to Northmere goes from Murtala to Owoleaf’s sponsor, who has standing with the bank. Prepare it as the previous chapter says: agree the facts with Imole first, tell Ezenwa, and ask for one thing with a date. Ezenwa and Imole should both know before the executives talk.
Prepare the fallback while you ask. If the ask fails, the workaround should already be designed, owned and costed, with a trigger and a date to take it. The RAID log chapter calls this a mitigation. Without it, asking is a hope.
Where practitioners disagree
A joint plan or separate plans? Some programmes build one schedule that both companies edit. It shows everything and is hard to keep honest, because each side wants to own its dates. Others keep separate plans and a shared list of the pieces that cross. The second asks less of the partner and loses the view of the path. Many TPMs keep their own map of the whole and ask the partner for dates only on the shared pieces.
Rely on the contract or the relationship? A service-level clause gives you something to point to and rarely makes a bank deliver sooner. A good relationship works until the partner’s priorities change. Most practitioners use both: the contract for what is owed, the relationship for what is possible.
Escalate early or hold? Going to the partner’s executives early gets attention and spends goodwill. Holding keeps the goodwill and risks asking when it is too late. A workable rule: ask through the sponsor route as soon as the bad case breaks a must or the latest date, and not before.
Day to day
- At the start of a programme. Draw the standing map. List every piece you need from each partner, split by the date you need it, with the evidence. Ask each partner who schedules the work, and get the date from them.
- Every Monday. Send the agenda for the Tuesday call, with the decisions you need. Check each shared piece against its evidence, not against its status. Send your own forecasts and sign-offs on time.
- Every Tuesday. Run the partner call as a decision meeting. Afterwards, write the decisions and dates down and send them the same day.
- When a date moves. Get the cause from the person who schedules the work. Recompute the path, look at which piece is late, and tell your sponsor the same day before the update goes out.
- When you must ask. Agree the facts with the partner’s working-level contact, tell your counterpart who will be asked, and make the ask from the sponsor who has standing. Name one thing and one date.
- Monthly. Review the standing map. Check whether the partner’s calendar has changed, whether you owe them anything, and whether the fallback is still ready. Launch readiness and cutover takes the open partner items into the go or no-go.
There is rarely a TPM, and the founders know the partner’s people by first name. That works, and it hides the standing question, because one founder holds the relationship and everyone else assumes it will serve. Write down who can ask whom, and who steps in if that person is away. Agree the first small piece with the partner in the first fortnight, with a check you can run. Keep your own fallback inexpensive, such as a manual process, because you have no leverage.
Several partners at once, and the first time a slip reaches the sponsor from outside the company. This is where a TPM builds the standing map and the shared list of crossing pieces, and where teams stop treating partner dates as promises. Give partner work a named owner on your side for each partner, make dates carry evidence, and keep the fallbacks in the plan. Sponsors begin to hold the relationships, so ask yours early which doors they can open.
Partnerships have contract owners, vendor managers and formal escalation paths, and the TPM is one voice among several. Learn the existing route before inventing yours, and use the vendor manager rather than going around. Expect lead times set by procurement, security review and change boards on both sides, and log them. The work is often reconciling two companies’ calendars and governance, and the value of a TPM is the one view of the pieces that cross.
Template
# Partner integration plan: <programme>, week <n> of <n>
Partners: <names> · Launch: week <n> · Latest date: week <n> · Updated: <date>
## Standing map
| Pair | What joins them | Who can ask whom |
|---|---|---|
## Pieces we need
| Piece | From | Scheduled by | Needed by (week) | Evidence it is done | Agreed date |
|---|---|---|---|---|---|
## Partner limits and calendar
| Partner | Limit, freeze or lead time | Effect on our dates |
|---|---|---|
## Routine
Call: <day, who, agenda sent when> · Shared list: <where> · Decisions sent: <when>
## If a date slips
Trigger: <what we see, by when> · Slip in weeks: <n> · Route: <who asks whom, in order, for what>
Fallback: <what> · Owner: <who> · Cost: <what> · Choose by: <week>
## What we owe
| To | What | By |
|---|---|---| WORKED EXAMPLE
Ojaline’s Pay in four, week 5 of 14. Akua writes the plan with Ezenwa. Figures are illustrative except the programme’s canonical dates and limits.
Standing. Ojaline and Owoleaf: the lending partnership; Akua asks Ezenwa, Murtala asks Owoleaf’s sponsor. Owoleaf and Northmere: the settlement account and the sponsor bank; Ezenwa asks Imole, Owoleaf’s sponsor asks Northmere’s executive for the account. Ojaline and Northmere: nothing, so every ask goes through Owoleaf.
| Piece | From | Scheduled by | Needed by | Evidence | Agreed |
|---|---|---|---|---|---|
| Decisions API contract frozen | Owoleaf | Ezenwa | End of week 6 | Signed contract, sample responses | Week 6 |
| Settlement change, test part: references on payments and a next-morning file in Northmere’s test environment | Northmere | Imole | End of week 10 | A 20-order sample file whose references match 20 Seller Wallet credits | Week 9 |
| Settlement change, production part | Northmere | Imole | End of week 12 | Written confirmation that it is live; first live file matched the morning after launch | Week 11 |
Limits. Owoleaf’s decisions cap is 15,000 a day until week 20. Lagos uses about 9,000 and each other city about 1,500, so Lagos plus four cities is 9,000 + 4 x 1,500 = 15,000, and the fifth to eighth of the other cities wait for week 20 unless Ezenwa gets the cap lifted; ask by week 10. Routine. Tuesday call, agenda sent Monday; Imole joins when settlement is on it. If it slips. Trigger: no test account by the end of week 9; a slip of one week uses the float; a longer slip puts the launch on week 15 or later. Route: Murtala asks Owoleaf’s sponsor, who asks Northmere’s executive to put the test part first. Fallback: finance operations prepares a manual daily match, costing about two people for the first weeks; choose by week 10. Owed. Ignatius signs off the file layout within two working days; Akua sends a city forecast every Monday from week 8.
Now you
You are Akua at the end of week 4 of the 14-week Pay in four programme, writing the partner plan for Owoleaf and Northmere. The facts: Owoleaf must freeze its decisions API contract in weeks 5 and 6. Northmere must change Owoleaf’s settlement set-up in weeks 5 to 9, so that each payment carries a reference and a file lists them next morning; Imole schedules it. The end-to-end test runs in weeks 11 and 12 and needs a working test version by the end of week 10. Launch is week 14. Owoleaf’s decisions cap is 15,000 a day until week 20; Lagos needs about 9,000 and each other city about 1,500, and the eight other cities follow Lagos at about two a week. Ojaline has no agreement with Northmere. Imole says the engineers who build it also support another client’s release in week 8, and he will not name a date until week 6. Produce the plan: standing, pieces with evidence, limits, route, fallback and what you owe, and say which date you would hold Northmere to.
Self-check
You are Akua in week 8 of Ojaline's 14-week Pay in four programme. Imole, Northmere's change manager, tells the Tuesday call that Owoleaf's settlement change will finish in week 12, three weeks late, because his engineers were moved to another release. The test needed it by the end of week 10, so the end-to-end test would start in week 13, review in week 15 and launch in week 16: the charter's latest date, with no margin. Owoleaf's application to the Federal Competition and Consumer Protection Commission, filed in week 3, is still unconfirmed. Imole says he could put the test part first and have it ready in week 10, but his executive would have to agree, and only Owoleaf's sponsor has standing with that executive. Murtala is waiting for your advice. What do you do?
- BOOK The Mythical Man-Month, chapter 14: Hatching a Catastrophe Frederick P. Brooks Jr., 1995
A classic account of how slips accumulate and why people hide them, with a warning that applies in both directions between you and a partner. Read: Chapter 14, including the subsection 'The Other Piece Is Late, Anyway'.
- DOC Dependency mapping Atlassian Team Playbook
A public 60-minute exercise for listing the systems and teams your work affects upstream and downstream, with an owner and a mitigation for each. Run it with a partner in the room.
- DOC Team Topologies: key concepts Team Topologies
Names three ways teams interact: collaboration, X-as-a-Service and facilitating. Use them to decide how closely you work with a partner and how long that closeness should last.
- DOC Idempotent requests Stripe
One provider's public description of how retried requests are made safe with a key the caller sends. It shows what a partner integration should settle with the other side before launch.
All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.