PRACTITIONERCHAPTER 07

Risk management and the RAID log

How a TPM keeps one log of risks, assumptions, issues and dependencies that drives decisions: what each entry needs, how to size a risk without false precision, which of four responses to pick, and how an outside approval such as a lender's registration goes in

40 MINTECHNICAL PROGRAM MANAGERUPDATED 2026-11-21
PREDICT

Akua's RAID log has 46 open entries. Most have an owner of 'the team' and no dates. It is reviewed for 40 minutes every Monday, and after a month no entry has changed. Which change helps most?

A programme is a bet that many things go right at once: a partner delivers, a regulator replies, an estimate holds, a test environment is free. A risk log is the record of which of those bets you have noticed, who is watching each, and what you will do if one fails. This chapter covers the log most TPMs use, the RAID log, and the habits that keep it short enough to act on.

It follows dependencies and the critical path, which gave you the dates that matter and the float behind them, and scoping and the programme charter, which fixed what is a must and who decides. The log sits between them: the charter says what you promised, the map says what the date depends on, and the log says what could break either. A TPM’s week set aside a Monday hour for it. The programme management philosophies chapter explains why a risk-driven programme gives dates as ranges; this chapter is the mechanics.

The model: four kinds of entry and how they change

RAID stands for risks, assumptions, issues and dependencies. In some companies the D means decisions, and a log may carry both. The four kinds are worth keeping apart because each is handled differently.

Kind What it is Example from Pay in four What goes wrong if you mix it up
Risk Something that may happen, with a likelihood and an effect Owoleaf’s lending approval may not be confirmed by launch It is logged as an issue, so no one plans for it before it lands
Assumption Something treated as true that nobody has confirmed Lagos will use about 9,000 lending decisions a day It sits unexamined until a test shows it is false
Issue A problem that has already happened Owoleaf’s test environment is booked for the weeks the end-to-end test needs it It waits for the Monday review when it needed a decision that day
Dependency A promise between two owners, with a date Northmere changes Owoleaf’s settlement set-up by week 9 Two teams each think the other has it, as in the previous chapter

Entries move. An assumption becomes a risk when someone gives it a probability: “the approval will be confirmed” turns into “one chance in five it will not”. A risk becomes an issue when its trigger fires. A dependency that slips becomes an issue and often raises a risk elsewhere. The log’s job is to catch each move on the day it happens, which is why every entry needs a date for its next look.

Keep the dependency rows short. The map from the last chapter holds the full table of givers, takers and dates, and the log carries a pointer to it for any promise that looks fragile. Two copies of the same dates drift apart.

What an entry needs

A line is managed when it has these parts.

Field What it holds Why it is there
Statement One sentence: the cause, the event and the effect “Approval late” says nothing; “if the regulator has not confirmed approval by week 14, lending cannot be switched on” can be tested
Owner One named person who can act on it The owner is not you. You own the log; they own the risk
Likelihood A percentage or a band, with the basis A number from a person’s judgement is fine if the entry says whose
Impact Weeks of delay, naira, or a launch criterion lost Impact in weeks lets you compare it with the float on the map
Trigger The early signal that it is turning into a problem You act on the signal, not on the failure
Response Accept, mitigate, escalate or avoid The decision, in the owner’s words
Decide by The date on which the response must be chosen or changed Without it, nothing forces a choice
Status Open, watching, fired, closed, and the date last looked at Old entries show themselves

The test from the philosophies chapter holds here: a risk with no owner, no early signal and no decision date is a worry. Apply it to the whole log once, and close or fix every entry that fails.

Two habits keep the statement honest. Name the cause as well as the event, because the response depends on the cause. “The partner is late” has a different response if the cause is a public holiday, a missing dependency or a regulator’s queue. And say what the entry would do to a launch criterion or to the critical path, not only to a feeling. A risk to a task with three weeks of float is a different size from one to a task with none.

Sizing a risk without false precision

The usual size is exposure: likelihood times impact. A 30% chance of a two-week slip on a task with no float is 0.6 weeks of exposure. Teams use it to sort the list, and it works as a rule of thumb for that.

It has two weaknesses. First, people’s likelihoods are guesses. A lead who says “30%” has rarely counted anything, and a five-by-five grid of colours implies a precision nobody has. State where the number came from: a past programme, a vendor’s record, or “my judgement, last revised on this date”. Where you must guess, use bands (low, medium, high) with a stated meaning, such as high meaning more than one in three, and do not argue over the difference between 22% and 25%.

Second, an average describes something that will not happen. A 20% chance of a six-week delay has an exposure of 1.2 weeks, but the programme will lose none or all six. Look at the bad case as well as the average and ask whether the programme survives it: do you have six weeks of margin, do you have a plan B, and who would have to agree to use either? A risk with a small exposure and a bad case that breaks the launch date needs a response, whatever its score.

When the programme is large enough, there are methods that go further. The US Government Accountability Office’s schedule guide describes schedule risk analysis, which varies the durations in a schedule by simulation and shows how likely each finish date is, and it warns that the results are inputs to management, not forecasts. For most programmes a range and a short list of bad cases is enough. DeMarco and Lister argue in Waltzing with Bears that risk should be managed in the open and not dismissed with can-do talk, which is the stance this log takes.

The four responses

Every risk gets one of four responses. The skill is to choose on purpose and write down why.

Response What it means Right when Wrong when
Accept Do nothing now, keep watching The effect is small or the float absorbs it, and a response would cost more than the exposure The bad case breaks a must or the date, and “accept” is only a way of not deciding
Mitigate Spend something now to lower the likelihood or the effect, or prepare a plan B that a trigger switches on The cost is small against the bad case and the owner has the means The mitigation needs authority or money the owner does not have
Escalate Take it to someone with more authority The response needs a decision or resource above the owner, or two sponsors must agree The owner can act and has not been asked, so you teach the sponsor you cannot settle things
Avoid Change scope or date so that the risk cannot happen The risk is a must-have’s only threat and the change is cheap, or the risk has fired You give up an outcome the programme exists to deliver, without asking its sponsor

Mitigation and contingency are different. A mitigation costs something now: an extra review, a second supplier, a test that is run early. A contingency costs nothing until a trigger fires, and then the plan switches to B. Most good responses carry both: a small cost now to make plan B possible, and a trigger and a date at which you take it. If the plan B needs work, the work is on the programme’s plan and has an owner, like any task.

The response is the owner’s, and your job is to see that it is chosen. Write it as a sentence the owner would say aloud: “Kintu will hold the lending switch-on until the confirmation is in writing.” If the owner cannot say it, the entry is not ready to be marked as handled.

An outside approval in the log: Owoleaf’s registration

The hardest risks to log are the ones outside your companies. In Pay in four, Ojaline’s checkout offers a loan that Owoleaf makes. A regulator’s approval is a dependency you cannot push, with a lead time you cannot shorten.

Start with the rule, stated no more precisely than the sources allow. The Federal Competition and Consumer Protection Commission’s Digital, Electronic, Online or Non-Traditional Consumer Lending Regulations 2025 cover unsecured consumer lending through electronic, online, mobile or other non-traditional channels, and according to law-firm summaries they require covered lenders to register with the Commission, with existing lenders given 90 days from commencement to do so, and do not allow digital lending without its approval; CBN-licensed institutions are described as applying for a waiveras of 2026-11. Sources disagree on the date the rules took effect, and their status moved during 2026 (a court challenge and an enforcement deadline), which the lending chapter below sets out. The penalty is not confirmed from the Commission’s text, so the log states no figure. The Commission’s own document was not read here, and the summaries are secondary. Treat this as background for the example, not as legal advice. The consumer protection and digital lending rules chapter shows what the rules ask of a lender, licences and structures shows where registration sits among a lender’s permissions, and embedded lending and BNPL partnerships shows how a marketplace’s checkout and a lender share duties.

Whether Pay in four needs a new approval, or falls under one Owoleaf already holds, is a legal question that belongs to Owoleaf’s compliance manager and its lawyers. You do not answer it. You log what you can: who owns the question, what date they expect an answer, and what the programme does if the answer is late.

Here is how Kintu, Owoleaf’s compliance manager, and Akua put it. Owoleaf filed its application in week 3 and has had no acknowledgement by week 7. Kintu puts the chance that approval is not confirmed by launch at 20%, as his own judgement and not from any record of past waits. If it is not confirmed, Owoleaf cannot lawfully switch lending on, and Ojaline would have a launch with no loan to offer. Kintu thinks the wait could run up to six weeks (an illustrative figure). The exposure is 0.2 times six, or 1.2 weeks, and the bad case is six weeks on a plan with no spare week: launch in week 20, four weeks past the charter’s latest date of week 16. The bad case decides it. The response is to prepare a plan B now: build a switch so that Pay in four can go live at Lagos checkout with the lending call off, and the loan starts when Kintu confirms. The switch costs about three engineer-days in Checkout (also illustrative). The trigger is no written acknowledgement from the Commission by week 10. The decision date is week 11, when the end-to-end test starts, so the switch must be built or dropped by then.

Notice what the entry does not say. It does not say that the regulator is slow, or that Compliance should chase. It does not guess the Commission’s timetable. It states a likelihood with its source, an impact in weeks, a signal Kintu can see, and a date on which Kintu and Akua will decide whether the switch stays in the plan.

Running the log

Four habits keep it alive.

Review it weekly, and only for change. Each Monday, read the entries whose decision date has passed or whose trigger might have fired, and ask each owner one question: what has changed since last week? Do not read the whole log aloud. A log reviewed for forty minutes with no change is a ritual; one reviewed for ten minutes with three changes is working.

Feed the update, not the other way round. The weekly written update, from week 7 for twelve readers, carries the top three entries by what they threaten, each with its owner, the trigger status and any decision needed. The rest stay in the tracker for anyone who wants them. The monthly 45-minute decisions session takes the entries that need a sponsor, and no others.

Close entries. An entry closes when the event can no longer happen, when it has happened and moved to issues, or when you accept it and its date has passed. A log that only grows is not read. Aim for a short list: when a log passes about twenty live entries, ask which are really worries.

Update the number when you learn something. A likelihood set in week 3 is out of date in week 8. When Kintu’s trigger fires at week 10, the entry’s likelihood moves, the status changes to fired, and you tell both sponsors the same day. Keep the earlier numbers in the history, so that you can see how the picture moved.

Who owns what, and fairness

The owner of a risk is whoever can act on it, not whoever is most affected. The risk that Owoleaf’s approval will be late affects Ojaline’s launch, but only Owoleaf’s compliance manager can do anything about it, so Kintu owns it and Akua owns the programme’s view of it. Writing “Ojaline” as owner for a risk that sits inside Owoleaf would give the entry an owner who can only wait.

Be fair to owners. A risk logged against a lead’s workstream is not an accusation. Say so when you introduce the log, and show that your own entries are in it, such as the risk that the update stops being read. People who think the log is a record of blame stop telling you things, and then the log is empty at the moment it matters. If an entry fires, the question is what the response was and whether the trigger worked, not whose fault it was.

Where practitioners disagree

Matrix or ranges? Many companies require a likelihood and impact grid with colours. It is quick and comparable across programmes. Critics say it hides guesses behind colours, and that an average of “medium” for two risks tells you nothing about which could end the launch. A middle path is to keep bands for sorting and add the bad case in weeks in plain words.

A full log or a short one? A full register is what auditors and some sponsors expect, and it records that you looked. A short one is read. Many TPMs keep the full register in the tracker and push only the live, owned entries into the update.

Tell the sponsor early, or when you have a plan? A risk reported with a plan reads as management, and one without a plan reads as alarm. But waiting for a plan can mean the sponsor learns of it late. A workable rule: the sponsor hears of any risk whose bad case breaks a must or the date as soon as its likelihood is more than low, with the plan or the date by which there will be one. How to deliver bad news without losing trust is the subject of status, escalation and bad news, the next chapter in this track, and of managing across teams and upward.

Day to day

  • At the start of a programme. Interview each lead with three questions: what could make your estimate wrong by half, what are you assuming that nobody has confirmed, and what outside party can say no? Write the answers as entries with owners. Walk the dependency map for fragile promises and add pointers.
  • Every Monday, ten to fifteen minutes. Look at entries whose decision date has passed or whose trigger might have fired. Ask each owner what has changed. Move entries between kinds, close the ones that can no longer happen, and add what you heard.
  • Thursday, before the update. Choose the top three by what they threaten, check each owner has seen their line, and put the decisions needed in the update with owners and dates.
  • When a trigger fires. Tell the owner and both sponsors the same day. Record the date, move the entry to an issue if it has happened, and start the plan B you prepared. The change goes in the next update and, if it needs a decision, to the person who decides within a day.
  • Monthly, in the decisions session. Bring only entries that need a sponsor: a response above the owner’s authority, a bad case that breaks a must, or a slip in float. Leave with each decision recorded, an owner and a date.
  • At launch readiness. Read the log against the launch criteria. Every open risk is accepted, mitigated or closed in writing. The readiness review, the next chapter but one in this track, launch readiness and cutover, takes it from there.
BY ORG SIZE
STARTUPunder 30 people

Nobody runs a RAID log, and risks live in the founder’s head and in a chat thread. The sharp risks are a single person who knows the system and a single outside party who can say no. Keep a page with five lines at most: what could go wrong, who is watching it, what you will see first, and the date you will decide what to do. Read it at the weekly meeting. Ask the outside party first, because a reply from a regulator or a bank has a lead time no one at the table can shorten.

SCALE-UP30 to 300

Several teams plan separately and the outside parties multiply: a partner, a bank, a regulator. This is where a TPM builds the first shared log and where leads call it paperwork. Win them over with one real catch in the first fortnight, such as an assumption that proves false. Keep to cross-team and external entries, give every one an owner who can act and a decision date, and feed the top three into the update. Leads add their own team’s risks to their own tracker lines.

ENTERPRISE300 and up

A company risk function or programme office already has a register, a taxonomy and a scoring grid, and your log feeds it. Use their scale for what they will read, and keep your own owner, trigger and decision date alongside, because a register’s “medium” does not tell anyone what to do on Tuesday. Many risks cross divisions and need a named executive, so escalation has set routes. Expect regulatory and contractual risks to carry formal change processes with long lead times, and log those lead times.

ARTEFACT Build a RAID log with owners, triggers and decision dates ~50 MIN
YOU PRODUCERAID log: entries typed as risk, assumption, issue or dependency, each with an owner, likelihood and basis, impact, trigger, response and decision date, plus the top three for the weekly update

Template

# RAID log: <programme>, week <n> of <n>
Launch: week <n> · Last reviewed: <date> · Open entries: <n>

## Log
| ID | Kind (R/A/I/D) | Statement (cause, event, effect) | Owner | Likelihood and basis | Impact | Exposure | Bad case | Trigger | Response | Decide by | Status |
|---|---|---|---|---|---|---|---|---|---|---|---|
| | | | | | | | | | | | |

## Moves since last review
| ID | From | To | Why |
|---|---|---|---|

## Top three for the update
1. <ID>: <owner> · trigger: <status> · decision needed: <what, by whom, by when>
2.
3.

## Closed this week
<ID>: <reason>
WORKED EXAMPLE

Ojaline’s Pay in four, week 7 of 14. Akua keeps the programme’s log, with Ezenwa keeping Owoleaf’s half. Likelihoods are the owners’ judgement, and figures are illustrative.

ID Kind Statement Owner Likelihood Impact Exposure Trigger Response Decide by
R1 Risk Owoleaf filed in week 3 and has no acknowledgement; if the regulator has not confirmed approval by week 14, lending cannot be switched on Kintu 20%, his judgement Up to 6 weeks 1.2 weeks No written acknowledgement by week 10 Mitigate: build a switch to start lending after launch (about 3 engineer-days) Week 11
R2 Risk Seller Wallet’s deduction estimate of 4 weeks has a wide gap; refund reversal may need a ledger change Obiomachukwu 30%, his judgement 2 weeks, no float; uses the whole margin to the week-16 latest date 0.6 weeks Reversal design not signed off by end of week 8 Mitigate: design the reversal first Week 8
A1 Assumption Lagos will use about 9,000 decisions a day Ezenwa Owoleaf’s estimate, not measured Sets the cap risk below n/a Test-load count in week 11 Confirm in the end-to-end test Week 12
D1 Dependency Northmere’s settlement change finishes by week 9; one week of float Ezenwa n/a 1 week then critical n/a No progress note by week 7 Ask on Tuesday’s call Week 8
D2 Dependency The cap is 15,000 a day until week 20; Lagos 9,000 plus four cities at 1,500 each is 15,000 on these figures, so a fifth city goes over Ezenwa Certain, from the figures Cities five to eight wait n/a Fifth city scheduled before the cap lifts Ask Owoleaf to raise the cap Week 10
I1 Issue Owoleaf’s test environment is booked by another team in weeks 11 and 12, the end-to-end test weeks Ezenwa Has happened 2 weeks, critical n/a Booking still held at week 9 Escalate within Owoleaf for the slot Week 8

Moves. A1 feeds D2: if Lagos runs above 9,000, fewer cities fit under the cap. Top three for the update: I1 (it has happened and is on the critical path), R1 (bad case six weeks, decision week 11) and R2 (no float). Check: 0.2 times 6 is 1.2; 0.3 times 2 is 0.6; 9,000 plus 4 times 1,500 is 15,000, and 16,500 with a fifth city.

Now you

You are Akua at the start of week 8 of the 14-week Pay in four programme. Kintu now says the chance that Owoleaf’s approval is not confirmed by launch is 25%, because the regulator has still not acknowledged the week-3 filing. A delay would run up to six weeks. Obiomachukwu says the refund-reversal design is signed off, so the ledger-change worry is gone. Ezenwa says Owoleaf’s test environment is held by another team in weeks 11 and 12, and he can ask for the slot but he also owns the cap request and Northmere’s settlement change. Murtala assumed that Legal and Compliance would finish the terms and disclosures in week 7, and nobody has confirmed it. Build the log: type each item, give each an owner, a likelihood with its basis, an impact in weeks, exposure, bad case, trigger, response and decision date. Choose the top three for Thursday’s update, and say what you do about Ezenwa owning three entries.

Self-check

DECIDE

You are Akua, the TPM for Ojaline's Pay in four launch, in week 7 of 14, writing your first weekly update. Owoleaf filed its lending registration in week 3 and has no acknowledgement. Kintu, Owoleaf's compliance manager, puts a 20% chance on approval not being confirmed by launch, and a wait of up to six weeks if it is not. The critical path has no spare week, and the monthly decisions session is four weeks away. Both sponsors, Murtala at Ojaline and Josefine at Owoleaf, will read your update. What do you do?

READING
  1. BOOK
    Waltzing with Bears: Managing Risk on Software Projects Tom DeMarco and Timothy Lister, 2003

    The case for naming risks and managing them in the open, from the authors who argue that can-do thinking leads teams to avoid risk management; read it before you write a date with no range. Read: The chapters on quantifying uncertainty and on the mechanics of managing a risk list.

  2. DOC
    How to create a RAID log to keep projects organized and on track Atlassian

    A public guide to the four-part log, its structure and how teams keep it linked to their work; compare its categories with this chapter's before you adopt one set.

  3. DOC
    GAO Schedule Assessment Guide: Conducting a Schedule Risk Analysis US Government Accountability Office

    A public-audit account of schedule risk analysis by simulation, and of reading its results as an input to management; useful when a sponsor asks how likely a date is.

  4. HANDBOOK
    The Orange Book: Management of Risk, Principles and Concepts HM Treasury, UK government

    A public handbook on how an organisation sets up risk management, including who owns risks; read it when a company risk function wants your log to fit its register.

  5. DOC
    Digital, Electronic, Online or Non-Traditional Consumer Lending Regulations 2025 Federal Competition and Consumer Protection Commission, 2025

    The instrument behind this chapter's registration example, as the Commission hosts it; read the registration and scope provisions yourself before you log a likelihood against them.

All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.

RECALL CARDS Tap to flip. They join your review deck when you mark the lesson complete.
NEXT: Status, escalation and bad news →