Scoping and the programme charter
A charter is the agreement a programme runs on: the outcome, what is in and what is out, the dates and the reasons for them, who owns each part and who decides what. Written before the work, it is what you read the day an estimate doubles
A TPM's first charter draft lists forty features for the programme and says done means 'launched in the first city'. It is signed by every lead. In week three one team's estimate doubles. Which gap costs the most?
A programme has no product to ship and no team of its own, so the first thing a TPM produces is an agreement. The programme charter is that agreement on one or two pages. This chapter covers what goes in it, how to scope honestly so that the charter can be believed, how to get it signed by people who do not report to you, and how to change it without losing trust.
It builds on a TPM’s week, where the charter is one of the programme documents, and on writing the PRD, whose non-goals and metrics habits it borrows. Programme philosophies are in the earlier chapter; this chapter is the document that puts one of them to work. Dependencies and the critical path, the RAID log and launch readiness each have a chapter of their own later in this track, and the charter only points at them.
What a charter is, and what it is not
A charter answers six questions for every person the programme touches: what are we trying to achieve, what is in and out, by when, who owns each part, who decides, and how will we know it is done. It is short because it is read. It is signed because an unsigned charter is a wish.
It is not a PRD. A PRD is one product manager’s decision record for one product, with the problem, the evidence and the requirements. A programme usually contains several of those, each owned by the team that builds the part, and the charter sits above them. It does not say what the checkout screen looks like. It says that a checkout screen showing the shopper’s limit is a must, that Rabiu’s team owns it, and that it is needed by the end-to-end test.
It is not a plan. A plan has tasks, sequences and dates for each. A charter has milestones and the few dates that matter. The plan changes weekly; the charter changes when a fact it rests on changes, and each change is recorded.
It is not a contract with a partner. If your programme includes another company, the commercial terms are theirs and the lawyers’. For a lender at a retailer’s checkout those are in embedded lending and BNPL partnerships. The charter records only what your programme depends on from the partner and by when.
Atlassian’s Team Playbook has a play called the project poster that works the same way: a single page that defines the problem and the intended outcome and is revised as the work goes on. Its IT Project Poster variant is written up on Atlassian’s community pages as a play to use in place of a charter. Use whichever name your company uses. The questions matter more than the title.
The parts of a charter
| Part | What it holds | What goes wrong without it |
|---|---|---|
| Outcome | One sentence, a measure, a number, a date, and a guardrail | The programme ships features and nobody can say if it worked |
| Scope | Items sorted into must, should and won’t, each with a name and a reason | Scope is argued again whenever an estimate moves |
| Dates | A target date, a latest date, and why the latest date is the latest | A slip is a surprise, and a margin nobody can see is spent unseen |
| Workstreams | One named owner each, and one sentence on what each delivers | Two teams each think the other owns a piece |
| Done means | Checks that can be answered yes or no on launch day | Launch day opens with an argument about readiness |
| Decision rights | Who decides each kind of change, and the sponsor for disputes | The loudest voice decides |
| Assumptions and constraints | What you are relying on, with an owner and a date | A partner’s date moves and nobody had written it down |
| Change log | Date, change, who approved, why | Nobody remembers what was agreed in week one |
Take three of these in more detail.
The outcome. Write what will be true for a customer or the business, not what will be built. ‘Pay in four live on Lagos checkout’ is a delivery. ‘Six per cent of eligible Lagos orders paid with Pay in four within 30 days of launch, with checkout completion on other orders no lower than before’ is an outcome with a measure, a target, a date and a guardrail, the same five parts as in the PRD chapter. The guardrail is the one that stops the programme succeeding at its own measure by harming something else.
Workstreams. Name one owner for each and write what the workstream delivers, not what it works on. ‘Seller Wallet takes the 7% deduction on each Pay in four order and shows it on the seller’s statement’ can be checked. ‘Seller Wallet changes’ cannot. One owner means one person, so that a question about the item has one address. If two people share it, you have written down the confusion.
Decision rights. List the kinds of decision the programme will face and name who makes each: a cut to the scope of an item belongs to the item’s owner and the sponsor; a change to the latest date belongs to the sponsor alone; the record belongs to you. Writing this in week one is cheap because nobody is in a hurry or on the defensive. Writing it in week three is a negotiation.
Scoping: where the date comes from
The most useful reframe in programme scoping is that you do not estimate the work and then read the date off the end. You usually have a date already, set by something outside the programme, and the question is what fits. Basecamp’s Shape Up calls this setting an appetite and treats time as fixed and scope as variable: the team is told how long the work is worth, and then shapes the work to fit, instead of letting the work set its own length. It writes for a six-week product cycle with a small team, so take the principle and not the numbers. In a programme the fixed point is a sales season, a contract date, a regulatory deadline or a partner’s release.
Find the real fixed point and write down why it is fixed. ‘The sponsor wants it by week 14’ is a preference. ‘The year-end sales start in week 22, and the other cities need six weeks after the first one opens’ is a reason you can show to someone who wants to argue.
Then sort the scope. Start with every ask you collected from the workstreams, put each on a card, and sort three ways.
Must. The programme would refuse to launch without it. The test is a pair: the item and a name. ‘Seller statements show each deduction, because Legal and Compliance reads the sellers’ terms as requiring it’ is a must. ‘Seller statements, because sellers will like them’ is a should with a good story. If you cannot say who would stop the launch, nobody would.
Should. Worth doing if time allows, ranked so that the cut order is already agreed. Rank them in the charter. The conversation about what goes first is calm now and bitter in week three.
Won’t. Things people will ask for that this programme will not do, each with a reason and a place it goes instead. This is the non-goals discipline from the PRD, moved up a level. A programme without a won’t list grows, and the growth never comes with extra time.
Two cautions. First, a must list that is longer than half the scope means nobody has sorted anything; push back on each must until it has a name. Second, a must can be a smaller must. ‘Statements for every seller’ and ‘statements in a downloadable file for every seller, with a page view later’ are different items with different costs. The sorting is also the moment to split items so the part the launch needs is separate from the part that is nice.
Dates: a target, a latest and the margin between
A charter with one date fails in one of two ways. If the date is the plan’s own, the first doubled estimate breaks it and the sponsor hears about a miss. If it is the latest date, the programme has no margin and every team plans to use all of it.
State two. The target is where the plan lands if the estimates hold. The latest is the date after which the outcome is lost, with the reason beside it. The weeks between them are the margin. This is Goldratt’s idea in Critical Chain in a simpler form: safety belongs to the programme, visible and shared, and should not be spread through every team’s estimate, where it is spent on the first task. The philosophies chapter covers the argument and where it fails, for instance with partners who ignore your buffer.
Each team’s estimate goes in as a range with a stated basis, such as a similar piece of work last quarter or a guess. Ask for the person who will do the work, not the manager. Add up the critical items, put the margin after them and check the sum against the latest date. If it does not fit, the charter is wrong, and it is wrong now, which is cheaper than in week eight.
Record which dates you control and which you do not. A partner’s release date, a bank’s change window and a regulator’s response time are assumptions with an owner, and the owner is the contact at the other company. How to handle those is the subject of programmes across companies later in this track.
Done means
Write the launch criteria as checks, each answerable yes or no. ‘Seller statements are correct’ is an opinion. ‘A sample of 200 orders from the test environment reconciles to the penny between the statement and the ledger’ is a check. You do not need all of them in week one, but you need the shape: who signs each one, and which are must and which should. The full process of a readiness review, including go and no-go, is the subject of launch readiness and cutover later in this track and of production readiness reviews. The charter’s job is to say now what the review will ask later, so that no team is surprised by a criterion on launch day.
Getting it agreed
A charter that you write alone and email out has no standing. Three steps give it some.
Interview before you draft. Spend thirty minutes with each workstream lead and ask four questions: what does your team deliver, what do you need from others, what could make your estimate wrong by half, and what would you cut first. Write down their words. The charter is then a summary of what they said, and a lead who sees their own sentence in the document does not argue with it.
Hold one kickoff. An hour, all leads and the sponsor, with the charter read in advance. The agenda is three decisions: the must list, the latest date and the decision rights. Everything else is correction.
Collect a yes from each owner. A line in the document with the name and date beside each workstream, from the owner themselves and not by a manager on their behalf. Silence is not agreement, and a charter signed by the sponsor alone is the sponsor’s wish. Be fair about this: a lead who will not sign is telling you something about the scope, the estimate or the date. Ask what would change their answer.
Changing the charter
A charter that never changes is ignored, and one that changes quietly is not trusted. Change it when a fact it rests on changes: an estimate, a partner’s date, a rule, a person leaving. Do it in four steps.
- Say what changed, in one line, with its source.
- Read the charter, not your feelings: what is must, what is should, what are the dates and the margin. The option that keeps the musts and uses the margin is usually the first to price.
- Take the change to its decision owner, with options and a recommendation, within a day.
- Log it, tell every owner the same day and re-read the dates.
Use the margin deliberately. If a doubled estimate is absorbed by the margin, the date holds, and say so; but also say how much margin is left and what you will now watch, because a programme with no margin is a different programme. When the latest date itself is in danger, the conversation moves to the sponsor, as in managing across teams and upward.
Where practitioners disagree
A full charter or a one-page poster? Some TPMs insist on a signed multi-page charter; others prefer a poster that is revised weekly and not signed. The long form helps where there are many parties and a history of disputes. The one-pager helps where trust is high and the work changes quickly. A fair rule: the more companies and the more money involved, the more the signature matters.
Fixed scope or fixed time? Shape Up fixes time and flexes scope, and so do most launch programmes with a hard date. Others fix scope when the scope is the point, for example a regulatory change where everything on the list is required. The charter’s must list is how you tell which kind you have: if nearly everything is a must with a real name, you are in the second kind, and the date moves.
Sign it or not? Signing makes a charter harder to dismiss and harder to change. Some teams read a signature as a threat. If that is your culture, record agreement in the kickoff notes and the change log, and keep the names.
Day to day
A TPM’s charter work follows the programme’s life, with most effort at the start.
- Before the charter, one to two weeks. Collect the asks. Interview each lead. Find the fixed date and its reason. Sort the asks on cards with the sponsor, in an hour, and put names against the musts. Draft the charter in one sitting.
- The kickoff. Read-ahead the day before. Take the three decisions in the room. Collect the yes from each owner within three working days; chase the ones who have not replied.
- Weekly. Read the must list against the tracker before you write the update. A must whose line is stale is the first signal of a slip. Check the margin and say in the update how many weeks remain.
- When an estimate moves. Price the options against the charter within a day, and take them to the decision owner. Log the change and tell all owners.
- Fortnightly. Re-read assumptions: partner dates, bank windows, rules. Ask each owner if their line is still true.
- Monthly. Sit down with the sponsor and read the charter together: outcome, must list, margin. Remove what has been done; do not let it grow into a history.
- When it breaks. A lead leaves, a partner moves, the sponsor changes. Write the change in the log, re-check the musts with their names, and agree again where a name has gone.
There is seldom a TPM, and the charter is a half-page in a shared document that the founder and two leads agree on over coffee. Keep three things: the date and why it is fixed, the two or three musts with a name against each, and who decides when something slips. The risk is not paperwork but silence: five people each carry a different idea of what launches. Write it down in an hour and read it aloud once, and revisit it when anyone says the word delay.
This is where charters are first written and where they meet resistance, because teams that were used to agreeing things in corridors now have an outsider writing them down. Win them by interviewing first and writing their words. Keep the charter to two pages. You may be the person who introduces must, should and won’t to the company, so use it on a small programme first and let the result persuade. Expect to defend the latest date against a sponsor who prefers the target.
A charter often competes with a programme office template: a business case, a governance plan and a stage-gate form. Do not write two documents. Write the charter once and let the template cite it, or fill the template’s boxes from it. Signatures are formal and slow, so start them earlier. The decision-rights section matters most, because several boards claim the same decisions, and naming the one that owns each is half the work. Expect more owners, more won’t items and a longer margin.
Template
# Charter: <programme> · version <n> · <date>
Sponsor: <name> · TPM: <name>
## Outcome
<One sentence.> Measure: <what>, target <number>, by <date>. Guardrail: <what must not get worse>.
## Scope
| Item | Must / Should / Won't | Needed by (name or rule) and why | Owner |
|---|---|---|---|
| | | | |
Cut order if time runs short: 1. <should> 2. <should> ...
Won't, and where it goes instead: <item, reason, where>
## Dates
Target: <date> · Latest: <date> · Why the latest is fixed: <reason>
Margin: <weeks> · Estimates on the critical items: <item, weeks, basis>
## Workstreams
| Workstream | Owner | Delivers (one checkable sentence) |
|---|---|---|
## Done means
| Check | Signed by |
|---|---|
## Decision rights
Scope cut to an item: <who> · Target date: <who> · Latest date: <who> · Dispute: <sponsor>
## Assumptions and constraints
| What we rely on | Whose | By when |
|---|---|---|
## Agreement
| Owner | Agreed (date) |
|---|---|
## Change log
| Date | Change | Approved by | Why |
|---|---|---|---| WORKED EXAMPLE
Ojaline is a fictional online marketplace: 1,400 staff, 300 engineers, delivering in nine cities. Its checkout offers Pay in four, lent by Owoleaf, with a 7% seller fee (illustrative). Akua is the TPM and Murtala, who runs BNPL, is the sponsor. This is her charter in week 1.
Outcome. Six per cent of eligible Lagos orders (₦20,000 to ₦300,000; illustrative) paid with Pay in four within 30 days of launch. Guardrail: checkout completion on other orders no lower than the 90 days before.
Scope. Must: checkout shows the shopper’s limit (Rabiu); Owoleaf decisions and loans through its API (Ezenwa); Seller Wallet deducts the 7% fee that Checkout sends as fee_kobo (Obiomachukwu); seller statements itemise each deduction, because Terwase of Legal and Compliance reads the sellers’ terms as requiring it (Obiomachukwu); order checks for Pay in four in Risk (Tomoko); a support playbook and trained agents (Tuan). Should, in cut order: a Pay in four share on the seller dashboard; the limit shown on product pages. Won’t: any change to the 7% fee; instalments other than four.
Dates. Target: Lagos launch in week 14, the date the whole programme plans to. Latest: week 16, six weeks before the year-end sales in week 22: the other eight cities need about four weeks at two a week, after two weeks of Lagos results. Margin: two weeks. Weeks 1 to 4 are scoping and design. Critical chain: Owoleaf API contract freeze, weeks 5 and 6; Seller Wallet deduction, 24 engineer-weeks, six engineers, four weeks (weeks 7 to 10); end-to-end test, weeks 11 and 12; readiness review, week 13; launch in week 14. Four, two, four, two and one weeks make 13 weeks, so launch is in week 14. The chain has no spare week against week 14, so the margin sits outside the plan: the first slip spends it, and Akua names that as the programme’s top risk. Northmere’s settlement change (weeks 5 to 9) is an assumption owned by Ezenwa’s contact at Owoleaf.
Decision rights. A cut to an item: its owner and Murtala. The latest date: Murtala. Dispute: Murtala. Each owner agreed by day 3.
Now you
You are Akua in week 9 of Pay in four. Lagos launches in week 14. Murtala asks for a charter for the rollout to the other eight cities, all live before the year-end sales in week 22. Your inputs: Customer Support (Tuan) and seller onboarding can each open two cities a week. Terwase wants two weeks of Lagos results before any further city opens. Ezenwa says Owoleaf’s lending API allows 15,000 decisions a day until week 20, when the limit is lifted. Lagos is expected to use 9,000 a day and each other city about 1,500. Murtala wants all eight committed. Tomoko needs one week of Lagos data to tune the Risk rules. Produce the charter: outcome, committed and should scope, dates with the margin, owners, and the one assumption you would ask Murtala to take to Ezenwa.
Self-check
You are Akua, three weeks into Ojaline's Pay in four programme. The charter targets Lagos in week 14 with a latest date of week 16, six weeks before the year-end sales in week 22, and marks seller statements as a must because Terwase says the sellers' terms require them. Obiomachukwu's team of six re-estimates the Seller Wallet deduction at 36 engineer-weeks against 24: six calendar weeks, not four, so weeks 7 to 12 instead of 7 to 10. The plan has two weeks of end-to-end test and one of readiness review after it, and no spare week against week 14. Statements are all of the extra 12 engineer-weeks. Tuan estimates a launch without statements would add about 900 seller tickets a week. What do you do?
- BOOK Critical Chain Eliyahu M. Goldratt, 1997
The source for holding safety as one visible margin instead of hiding it in each team's estimate, which is why the charter shows a target, a latest date and the weeks between them. Read: The passages on padded estimates and the shared project buffer.
- BOOK The Mythical Man-Month: Essays on Software Engineering, Anniversary Edition Frederick P. Brooks Jr., 1995
The origin of the warning that more people make a late software project later. Read it before you offer contractors as the answer to a doubled estimate. Read: Chapter 2, The Mythical Man-Month, on adding people to a late project.
- BOOK Shape Up: Set Boundaries Ryan Singer, Basecamp
A clear account of starting from the time the work is worth and fitting scope to it. It is written for small product teams, so take the principle for a programme and leave the six-week figure. Read: Chapter 3, on setting the appetite and fixed time with variable scope.
- DOC IT Project Poster Atlassian Team Playbook
A living document, filled in over a few sessions, that agrees the problem and the intended outcome before a kick-off. Compare its questions with the charter's parts and borrow what suits your company.
All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.