Launch readiness and cutover
How a TPM turns the charter's definition of done into a readiness review the sponsor can decide on, plans the day itself across teams and partners, and says in advance what can be switched off, what can only be repaired and what cannot be taken back
It is the Wednesday of week 13 of a 14-week programme. Seven workstream leads each say their part is ready. Which single piece of evidence tells you most about whether the whole launch is ready?
A launch is the moment a programme stops being a plan. Until then every date can move at the cost of some margin. On the day, real shoppers, real sellers and real money meet code that several teams and two companies wrote separately. This chapter is about the two things a TPM owns at that point: the readiness review, which decides whether to go, and the cutover, the plan for the day itself, including how to stop.
It builds on the charter’s “done means” section in scoping and the programme charter, which this chapter turns into checks, and on dependencies and the critical path, whose last task, the readiness review, is the subject here. A TPM’s week explains where the hours for it come from.
What the review is for, and what it is not
Two neighbouring practices already exist, and a TPM should use them and not rebuild them. A production readiness review asks whether one service can be run: monitoring, on-call, capacity, restore. Release sign-off asks whether one release meets criteria agreed in advance. Read both. This chapter does not repeat them.
The programme review sits above them. Its question is wider: does the whole thing work end to end, is every team and partner ready on the same day, and can we undo it? It takes the verdicts of the others as rows. The wallet service’s production readiness review is one line. The checkout release sign-off is another. Then it adds what no single review covers: the seams between teams, the partner that is not yours, the people who must answer the phone, and the plan for the day. The PM’s launch chapter covers messaging, tiers and enablement. This one is about readiness.
You do not run the technical checks. You keep the list, make sure every line has an owner and evidence, and put the result in front of the person who decides. The decision is not yours. Hold that line from the start, because a TPM who says go owns the failure, and a TPM who says only that the checks are green has shifted the risk to the sponsor, where it belongs.
Criteria written in week one
The charter already says what done means as yes-or-no checks. In week one you write them out in full and get them agreed. A criterion written in week 13 bends to fit whatever the build looks like, and the person under pressure to ship writes a lenient one. A criterion agreed in week one is neutral, because nobody yet knows whose work it will catch.
A launch with several teams and a partner needs checks of seven kinds. The evidence column shows what each looks like for Pay in four at Ojaline.
| Kind | What it asks | Evidence for Pay in four |
|---|---|---|
| Works end to end | Does one order go through every system and come out right? | A sample of 200 test orders reconciles between the statement and the ledger |
| Money | Is every amount and rounding correct, and does a refund reverse it? | A ₦40,000 order carries fee_kobo of 280,000; every test refund reverses its fee |
| Partners | Is the other company ready, in writing, with a named contact on the day? | The lender confirms its settlement change is live; both companies’ contacts are on the cutover list |
| Load | Can it carry the forecast with room to spare? | A test at 150% of Lagos’s forecast of 9,000 decisions a day, under the lender’s cap of 15,000 |
| People | Are the people who will meet customers ready? | At least 90% of the support desk trained, with a macro for the top questions |
| Customers | Is what they will read true and in place? | Terms and disclosures live; Legal and Compliance has signed |
| Reversal and watching | Can you see a problem and stop it? | A rehearsed switch-off with a timed result; alerts that page a named person |
Four rules make the list usable. Each check is yes or no, with the number written in (150%, 90%), and the numbers are rules of thumb you agree with the sponsor, not constants. Each has an owner who does the work and a second person who reads the evidence, so nobody signs off their own work. Each names its source of evidence as a link, not a statement. And the list is short: ten to fifteen lines is a workable range for a programme this size. A list of sixty is read as a ritual.
Evidence that someone else has read
The review is only as good as its evidence, and evidence goes wrong in a predictable way. A lead says “tested”, and what they mean is that their own tests passed in their own environment, against their own idea of the neighbour’s behaviour. The end-to-end test in weeks 11 and 12 exists to replace that with a run that crosses every boundary.
Three habits make the evidence honest.
Read the artefact as the audience reads it. Do not stop at the totals. Open the seller statement as a seller would, the checkout screen as a shopper, the support agent’s view of the same order, and the settlement file as the lender’s finance team. A check that proves two numbers match can pass while the statement beside them says something false. Ask for a screenshot or a sample file as the evidence, not a sentence about it.
Ask who has not seen it. A check read by its builder confirms the builder’s assumptions. Give each piece of evidence to someone outside the workstream for ten minutes, such as a data analyst, a support lead or a lead from another team. Their questions are the cheap version of a customer’s.
Know what the environment hides. The test environment simulates the partner’s side, so a pass there says your side is right and nothing more. Write down, for each check, what the test did not touch: the real bank’s settlement file, real card traffic, the real number of agents on a shift. Each of those is either a condition on launch day or an accepted risk with a name beside it.
The review meeting
Hold it in week 13, one week before launch: after the end-to-end test has finished and while there is still room to fix one thing. For a programme whose critical path runs from contract freeze to wallet build to test to review, with no spare week, the review is the last task on the path, and a slip in it is a slip in the launch.
Prepare the pack in four steps.
- Dry run in the first week of testing. Walk the criteria list with each owner and mark every check that has no evidence yet. These are the items you chase while there is time.
- Send the pack a day before. A single page: each check, its owner, its evidence, its verdict. The decision owner reads it before the meeting, not in it.
- Meet for the exceptions. Greens are not discussed; they were settled by the evidence. The meeting, 45 to 60 minutes, takes the ambers and reds one at a time.
- Record the decision. Who decided, on what date, with which conditions, and who disagreed.
Each verdict has three states. Green means the evidence is linked and has been read by someone other than the owner. Red means the check failed and there is no safe way to launch past it. Amber is the one people misuse. An amber is a condition with four parts: an owner, a date, the milestone it must be done before, and the fallback if it is missed. Without all four it is a red that nobody has admitted. With them, it is a way to launch safely.
You recommend, in writing: go, go with conditions, or no-go, with the reason and the cost of waiting. The sponsor decides. A no-go has to be a recommendation you can make without a fight, and one the sponsor can overrule with their name on the record. The same principle holds in QA sign-off, covered in the chapter linked above.
Go, no-go and the choices between
The review is rarely a yes or no. An open item usually has a shape, and the useful question is which shape. The charter’s levers, which the PM launches chapter sets out as scope, audience, promise and date, are your menu. A fifth sits across them: go with a dated condition.
The QA chapter’s list for a late P1 (is it new, who does it reach, how bad is it, can it be contained, what does a fix cost) applies here too. A TPM adds three of their own.
When does a customer first meet it? This is the most useful question and the one most often skipped. A defect on a monthly statement, a nightly job or a settlement file reaches nobody on launch day. It is a condition with a tripwire, not a blocker. A defect on the checkout screen reaches everyone in the first minute.
What does waiting cost, in margin? Say it as weeks against the charter’s latest date, not as unease. A programme with two weeks of margin can afford one week of delay and still have one left for the next surprise.
Can the fix go through the freeze? A change freeze from the review to launch keeps the tested build as the tested build. A fix made after it is a new change on a path that was reconciled days ago, so it needs its own check, not a trust that it is small. Write the exception rule in advance: who may approve a change after the freeze, and what retest it must pass.
When you choose a condition, write the tripwire with it. “Fix ships by Friday, rechecked by Ochai; if not, statements for Pay in four are held until it does.” The fallback is the part that stops the condition from drifting.
Cutover: the plan for the day
Cutover is the sequence of steps that turns the programme on. A plan that lives in one team’s head fails the moment someone is ill, so write it as a timeline with a named person against every step, including the people at the partners.
| When | Step | Who | Pause point |
|---|---|---|---|
| Day before | Final reconciliation on live configuration; change freeze confirmed; contacts at both partners checked | Seller Wallet, TPM | Checklist read aloud; any red stops here |
| Launch morning | Fifteen-minute go-confirm call, same ten people, same page | TPM leads, sponsor decides | Sponsor says go in terms |
| Switch-on | Per-city flag on for staff accounts, then for Lagos | Checkout | Check one real order end to end before widening |
| First hour | Watch decisions, errors, fee mismatches, tickets | On-call, support lead | Hourly one-line status to the sponsor |
| Next morning | First live settlement file compared with the ledger | Lender’s integration lead, Seller Wallet | Match, or a named owner and an hour |
Several points keep it honest.
Switch on in order of how well you can undo it. Staff first, then a share of customers, then everyone. A partner’s decision call at 9,000 a day in Lagos against a 15,000 cap leaves headroom of 40% of the cap. Check that figure again before the other cities, because Lagos plus four more at about 1,500 each is exactly 15,000, and the cap, not the calendar, may set the rollout’s pace until it lifts in week 20.
Pause points are real pauses. Atul Gawande separates checklists you read and then do from checklists you do and then confirm. A launch uses both. The day-before list is read and done. The launch-morning call is a confirm: everyone stops, says aloud that their item is true, and only then does the next step run.
One channel, one decision log. The people who know the answer are in four teams and two companies. A single channel with the TPM as scribe means a decision is made once, in writing, with a name and a time, and does not get remade in side conversations.
The partner’s day is part of your plan. The lender and the bank have their own changes, shifts and freezes. Ask each for their calendar for the week before and the week after. A settlement window that closes on a Friday evening is a constraint on your cutover, not a detail.
Rolling back when other companies are involved
Rollback is easy to promise and hard to define, because the thing you ship creates obligations that outlive the switch. Sort everything the launch does into three kinds.
| Kind | Meaning | Pay in four example |
|---|---|---|
| Reversible | Switching off returns the state | The checkout flag; new orders stop |
| Repairable | You can compensate, at a cost | A fee deducted in error is reversed and the seller told |
| Irreversible | Cannot be taken back | A loan the lender has issued to a shopper; an email already sent |
The design rule that follows is that off must not mean broken. Turning Pay in four off at checkout stops new orders and nothing else. The lender keeps collecting instalments on loans already made. Seller Wallet keeps reversing the fee on a refund. Statements still list deductions already taken. If switching off would strand those obligations, it is not a rollback, it is a second incident, and the readiness review should have caught it in the rehearsal.
Write three things down before launch. Triggers as numbers, such as a rate of declined or failed Pay in four orders above a stated level for a stated time, or any single order whose fee does not match its rule. A named person who can pull the switch without a meeting. How long each company needs to stop, because the lender’s stop is on the lender’s clock. Then list what cannot be undone and what you will do instead, which is usually a compensating action and an apology, not a reversal. The incident management chapter covers what happens once a trigger fires.
Hypercare and handing over
A launch does not end at the switch. Agree a hypercare window before launch: a fixed period, two weeks is a reasonable default for a first city, in which the programme team stays on call and the daily rhythm replaces the weekly one. A short daily note of three lines is enough: what the numbers say, what broke, what is owed.
Close the window on criteria, not on the calendar. For example: no red for five consecutive days, tickets back to forecast, the first settlements matched. Then hand over. Each run team takes the pager and the runbook, the programme’s decisions log moves to its owners, and the outcome in the charter, such as the share of eligible orders paid with Pay in four within 30 days, gets measured and reported to the sponsor. Write a half-page closing note on what the review caught and what it missed. The missed list improves the next criteria list.
Where practitioners disagree
Who says go? One camp gives the decision to the sponsor, on the TPM’s written recommendation, which keeps authority with the person who owns the outcome. Another gives it to a launch committee or a standing gatekeeper. Google’s SRE book describes launch coordination engineers, a consulting team that audits launches against a checklist and mediates between stakeholders, which works where a central group has the trust and the staff. Most companies have neither, and a TPM without authority should not pretend to be a gate. Keep the recommendation and the record.
Staged or all at once? Staging limits who is hurt and costs a longer launch and more than one cutover. A single big switch is cleaner for a partner who cannot run a split. Choose by what you cannot undo: the more irreversible the action, the more reason to stage.
A hard freeze or fix-forward? A freeze keeps the tested thing intact and makes a one-line fix wait. Fix-forward lets the team move fast and risks the last-minute change nobody retested. A middle path is a freeze with a written exception rule, a retest for every exception and a record of each.
Day to day
- Week one. Turn the charter’s done-means into a numbered criteria list with an owner, a reader and a link-shaped source of evidence for each. Agree thresholds with the sponsor.
- Weeks 2 to 10. Each week, check the criteria against the tracker. Any criterion that no one has started to work on is a risk in the log. Book the review for week 13 and the rehearsals before then.
- Start of end-to-end test. Dry run the pack with each owner. List checks with no evidence yet and chase them.
- During the test. Read the artefacts as audiences read them. Book the switch-off rehearsal and the support walkthrough.
- Day before the review. Send the one-page pack. Write your recommendation, including the cost of waiting in weeks.
- Review day. Take the ambers and reds. Leave with conditions each having an owner, a date, a milestone and a fallback. Record the decision.
- Launch week. Freeze, final reconciliation, contacts checked, the go-confirm call, the switch-on and the hourly status.
- Hypercare. The daily three lines, a look at the triggers each morning, the first partner files checked, a handover when the exit criteria are met.
- After. The closing note, the thirty-day outcome and an update to the criteria list.
There is no readiness process. The founder or the lead engineer decides in a corridor, and the risk is that nobody has looked at the launch from the customer’s side. Write ten checks on one page, each with a name and a link, and meet for twenty minutes. Rehearse the switch-off once and time it. If a partner is involved, get their contact’s mobile number and their change calendar. The plan can be short, but it must include what stays working after you switch off.
This is where launches first cross several teams, and where a TPM introduces criteria written in week one. Teams used to saying ready in a chat will resist a pack. Win them with a check that finds something real in the first review, and keep the list short. The production readiness review may be new or informal, so you may carry its questions in your list. Set the freeze rule and the exception rule early, because that is where most arguments start.
Readiness already exists as gates: change boards, a release calendar, a risk committee, a regulator’s checkpoint. Do not run a second process beside them. Write your criteria once and let each gate cite them, so one pack answers every audience. Lead times are long, so book the board’s slot when you set the review date. Expect formal sign-off by several owners, and keep the decision record by name. The risk is a launch that satisfies every committee and still fails at a seam.
Template
# Launch readiness review: <programme>, <scope> · week <n> of <n>
Decision owner: <name> · TPM: <name> · Review: <day> · Launch: <day, time> · Latest date: <week>
## Criteria and evidence
| # | Check (yes or no, with number) | Owner | Read by | Evidence (link) | Not covered by the test | Verdict |
|---|---|---|---|---|---|---|
| | | | | | | green / amber / red |
## Amber items
| # | Condition | Owner | Due | Must be done before | If missed |
|---|---|---|---|---|---|
## Cannot be undone
| What | Who is affected | What we do instead |
|---|---|---|
## Cutover
| When | Step | Who (and partner contact) | Pause point |
|---|---|---|---|
## Rollback
Triggers (numbers): <...>
May act without a meeting: <name> · Time to stop: <company, minutes>
Keeps working after switch-off: <...>
## Recommendation
<go | go with conditions | no-go>. Reason: <...>. Cost of waiting: <weeks of margin>
## Decision
Decided by <name>, <date>: <...>. Dissent: <...> WORKED EXAMPLE
Ojaline is a fictional online marketplace: 1,400 staff, 300 engineers, nine cities, about 48,000 sellers. Its checkout offers Pay in four, lent by Owoleaf, with a 7% seller fee (illustrative). It is Tuesday of week 13, the day before the review. Akua is the TPM and Murtala, the sponsor, decides at Wednesday’s review. Launch is Wednesday of week 14; the charter’s latest date is week 16.
| # | Check | Owner | Evidence | Verdict |
|---|---|---|---|---|
| 1 | 200 of 200 sample orders reconcile, statement to ledger | Ochai, Seller Wallet engineer | Run log, read by a Data analyst | Green |
| 2 | ₦40,000 order carries fee_kobo 280,000; 40 of 40 refunds reverse the fee |
Seller Wallet | Test report | Green |
| 3 | Decisions load test at 150% of Lagos’s 9,000 a day: 13,500 passes; cap 15,000 | Owoleaf’s integration lead | Owoleaf’s report | Green |
| 4 | Settlement change live at Northmere, in writing | Owoleaf’s integration lead | Written confirmation; first live file lands next morning | Amber |
| 5 | Lagos desk at least 90% trained, statement screen included: 44 of 48 (92%) | Lavinia, who leads the Lagos desk | Roster; session held Monday | Green |
| 6 | Switch-off rehearsed in staging on Monday, four minutes | Checkout | Rehearsal log | Green |
The full pack has ten checks; the rest are green. Amber 4. Owoleaf’s integration lead confirms the first live settlement file against the ledger by 10:00 the day after launch; if it does not match, Pay in four is switched off for new orders until it does.
Cannot be undone. Loans issued to shoppers; emails already sent. After switch-off the lender keeps collecting instalments and Seller Wallet keeps reversing fees on refunds.
Recommendation. Go with one condition. A no-go costs a week of the two weeks of margin.
Now you
You are Akua on Monday of week 13, building the pack for Wednesday’s review. Your criteria, agreed in week one: (1) 200 of 200 sample orders reconcile; (2) a decisions load test at 150% of Lagos’s forecast of 9,000 a day; (3) written confirmation from Northmere’s side that the settlement change is live; (4) at least 90% of Lagos’s 48 support agents trained, including statements; (5) switch-off rehearsed and timed. Your inputs: 200 of 200 reconcile. Owoleaf’s test, run in its test environment in week 12, reached 13,500 a day. Owoleaf’s integration lead says the settlement change has been live since Friday, but has no written confirmation, and the first real file arrives the day after launch. Lavinia, who leads the Lagos desk, reports 44 of 48 agents trained, but the statement screen was not ready until week 12, so the sessions did not cover it. The switch-off has been designed but never run. Murtala wants a 15-minute decision. Give each check a verdict, write any conditions with their four parts, and list what cannot be undone.
Self-check
You are Akua, at Wednesday's launch readiness review for Ojaline's Pay in four, week 13 of 14. Every check is green except one found on Tuesday. Ochai, a Seller Wallet engineer, saw that seller statements show the 7% fee under the label Refund. The ledger is right; the 200-order reconciliation compared amounts, not labels. Launch is next Wednesday. Statements run on Mondays, so no seller sees a Pay in four line until the Monday of week 15. Ochai estimates three working days for the fix and a rerun of the check. Lavinia, who leads the Lagos support desk within Customer Support, expects about 150 extra seller tickets a week if the wrong label is live. Legal and Compliance says the label does not meet the itemised wording in the sellers' terms. The charter has two weeks of margin. What do you recommend?
- BOOK Chapter 27, Reliable Product Launches at Scale Google SRE book, 2016
Google's account of a launch process built on a checklist, with a consulting team of engineers who audit launches against it. Read it for how a launch checklist is kept short and tied to real failures. Read: Chapter 27, on launch coordination engineering and the launch checklist.
- BOOK Chapter 16, Canarying Releases Google SRE workbook, 2018
The engineering form of staged exposure: put a release in front of a small share of traffic and compare it against the rest. Use it to judge which of your own metrics would show a launch going wrong. Read: Chapter 16, on canarying and choosing the metrics that judge a canary.
- BOOK The Checklist Manifesto: How to Get Things Right Atul Gawande, 2009
The case that a short checklist with real pause points prevents the failures of experts in complex work. It is the thinking behind the day-before list and the go-confirm call. Read: The chapters on pause points and on checklists to read and do or do and confirm.
- POST Reliable Releases and Rollbacks, CRE Life Lessons Google Cloud blog
A companion piece from Google's customer reliability engineers on releases and rollbacks. Read it with the rollback section here and ask what your own switch-off leaves running.
All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.