Dependencies and the critical path

How a TPM turns six teams' separate plans into one map of who is waiting for whom, finds the one chain that sets the launch date, watches the chains that are one slip away from joining it, and gives every orphaned piece an owner

40 MINTECHNICAL PROGRAM MANAGERUPDATED 2026-11-21
PREDICT

Your dependency map for a 14-week programme has 12 tasks owned by nine teams. The longest chain of dependent tasks finishes in week 13, in time for launch in week 14. Where should you spend most of your attention?

A dependency is a promise between two owners: one will hand over something, the other cannot proceed without it. A programme of several teams is full of such promises, and most are made in passing: in a corridor, in a chat message, in a design meeting where both people nodded. The critical path is the one chain of them that decides when you launch. This chapter is about writing the promises down, finding the chain, and keeping both honest as estimates move.

It follows a TPM’s week, which gave you the hours to look at the programme, and it starts from the programme charter, the subject of the chapter before this one, scoping and the programme charter. The charter says what is in scope and who sponsors it, and the map says what has to happen, in what order, to deliver it. The method is a standard one from project scheduling. The skill is applying it across teams who did not plan together.

The model: a dependency is a promise between two owners

Every dependency has the same parts. A giver owns the thing. A taker needs it. The thing is stated precisely enough to be tested: not “the lending API” but “the contract for the limit decision call, frozen, with sample responses”. A date the taker needs it by, and a date the giver has agreed to. A definition of done both sides accept.

Dependencies come in kinds, and the kind tells you what can go wrong.

Kind Example What usually goes wrong
Finish before start Seller Wallet cannot post a fee until the order event carries one The giver finishes late, or finishes something slightly different
Interface or contract The field name and rounding of a fee amount between two systems Each side builds to its own reading of the agreement
Decision Who owns a piece of work, which design the partner picks Nobody is named to decide, so each waits for the other
Shared resource One test environment, one engineer who knows the ledger Two teams plan to use it in the same fortnight
External A bank’s settlement change, a regulator’s registration You have no authority and a long lead time

The two that hurt most are the decision and the external kind. A decision dependency has no work in it, so it never appears on a team’s plan. An external dependency has work in it that belongs to a company with its own priorities. Both need you to ask early.

A dependency counts as real only when it is agreed on both sides. A taker who writes “needed from Payments by week 8” in their own plan has recorded a hope. When the giver has read it and replied with a date, it is a promise. The difference matters: a promise that slips is a dependency alert, and a hope that slips is a surprise.

Finding the dependencies nobody wrote down

Teams list the dependencies they know about. The ones that hurt are the ones nobody knew about, so you go looking in four places.

Ask in both directions. In a planning session with each lead, ask two questions on separate cards: “What do you need from someone else before you can finish?” and “What does someone else need from you?” The answers rarely match. A lead who lists three things she needs and nothing anyone needs from her has usually forgotten the other side, and the cards that appear on only one side show you the gaps.

Follow the data. Pick one order, one payment, one shopper, and trace it through every system it touches. At each hand-off ask who builds the outgoing side and who builds the incoming side. A hand-off with an owner on one side only is a gap.

Read the designs. An interface in a design document or an RFC is a dependency between the teams on each side of it. You do not need to review the design, only to list its seams. How technical a TPM must be covers reading designs for this purpose.

Ask what needs someone to say yes. Approvals, registrations, contract signatures, security reviews and test-environment bookings all have lead times and owners. They are the dependencies that arrive latest and cost most.

Write each one as a row in one table. A tracker that holds the plan and a separate sheet that holds the dependencies will drift apart; one table, with the date each side agreed, does not. The Artefact below gives the columns.

The critical path, step by step

The method is called the critical path method. It comes from project scheduling in the 1950s, and it needs only arithmetic.

  1. List the tasks with a duration for each, in weeks or days, and the tasks each one waits for.
  2. Forward pass. Work from the start. A task’s earliest start is the week after the latest finish among the tasks it waits for. Its earliest finish is its start plus its duration.
  3. Fix the end date. The launch date is given. The last tasks must finish in time for it.
  4. Backward pass. Work from the end. A task’s latest finish is the week before the latest start of the tasks that wait for it.
  5. Float. The difference between a task’s latest and earliest finish. Tasks with zero float are critical: the chain they form is the critical path.

A short example from the Pay in four programme at Ojaline, in which Akua is the TPM. Three chains lead to the end-to-end test:

  • Owoleaf freezes the lending API contract (2 weeks), then Seller Wallet builds the fee deduction and ledger posting (4 weeks), then the end-to-end test (2 weeks), then the launch readiness review (1 week). The chain is 2 + 4 + 2 + 1 = 9 weeks.
  • Northmere changes Owoleaf’s settlement set-up (5 weeks), then the same test (2 weeks) and review (1 week): 5 + 2 + 1 = 8 weeks.
  • Legal and Compliance reviews the terms and disclosures (3 weeks), then Customer Support training (2 weeks), then the review (1 week): 3 + 2 + 1 = 6 weeks.

Starting in week 5, the longest chain ends in week 13, so launch in week 14 holds with no spare week. The Northmere chain is one week shorter and has one week of float. The terms chain has three. The 9-week chain is the critical path; every task on it has zero float, so one week lost anywhere on it is one week lost at launch.

Three points the method does not make obvious.

The path is about dependence, not effort. The longest task, here the 5-week Northmere change, is not on the critical path. The 1-week readiness review is. Effort and criticality are separate questions.

Fixed delays are tasks too. A partner’s lead time, a regulator’s waiting period and a vendor’s delivery time go in the map with a duration and no owner on your side. They cannot be sped up by pushing your own teams, so they decide how early you must ask.

Estimates are the weak point. The path is only as good as its durations, and durations come from the people doing the work, who round up, round down or guess. Ask each lead for the likely duration and the number that would make them uncomfortable, and note how far apart the two are. A task with a wide gap deserves a second look even when it has float.

Float, near-critical chains and buffers

Float is the part of the map that people skip and that matters most after the first week. Two things follow from it.

A chain with a week of float is close to critical. One slip of a week turns it into a second critical path, and two paths at zero float means twice as many ways to miss the date. Count your near-critical chains. A map with one zero-float chain and one with a week of float is under much more pressure than it looks.

Float is shared, not owned. If Payments’ instalment work (E) uses its one week of float, the Data work waiting behind it (G) has none left, because it is the same week. Say so in writing: float belongs to the programme, and its use is a decision for you and the sponsor, not for whichever team gets there first.

Eliyahu Goldratt’s Critical Chain argues that the usual way of padding each task’s estimate wastes the padding. His reasons are that people use the time they are given, and that the time saved on early finishes is not passed on to the next task. His fix is to take the padding out of the tasks and put it in one buffer at the end of the chain, with smaller buffers where a side chain joins it, and to watch how fast the buffer is used. You need not adopt the whole method to use the idea: ask whether the float in your map belongs to the tasks or to the programme, and who may spend it.

The piece nobody owns

Sooner or later two leads each say a piece of work belongs to the other. It is the most common problem the map exposes, and it usually looks like a quarrel when it is a missing owner.

The pieces that fall between teams are rarely one piece. Take the 7% fee Ojaline charges sellers on Pay in four orders. Seller Wallet says Checkout must calculate it, because Checkout knows the order is a Pay in four order. Checkout says Seller Wallet must deduct it, because the money is the seller’s balance. Both are right, because there are two jobs in the word “deduction”: working out the fee, which needs what Checkout knows, and applying it to the seller’s payout and ledger, which needs what Seller Wallet owns.

When a piece falls between two teams, look for the interface where it divides. Each half goes to the team whose system holds the knowledge or the data. The two agree the contract between them, in a sentence: the field, its unit and its rounding. Then there are two owners and a promise, and the piece is on the map as two rows.

A TPM does not assign the work, because a TPM has no authority over either team. You propose the split, check each lead agrees to their half, and record it. If the leads cannot agree, the sponsor decides, and you bring the question with the facts and the date by which it must be settled. Managing across teams and upward covers how to put that to a sponsor.

Keeping the map alive

A map drawn at kickoff is already out of date by week three, when an estimate has moved or a team has found a new need. Three habits keep it honest.

Recompute weekly. Update the dates of anything that moved, rerun the forward pass, and look at which chain is now longest. It takes twenty minutes in a spreadsheet. The change in the path is itself news: the programme was waiting on Seller Wallet last week and is waiting on Northmere this week.

Watch the near-critical chains. Put the tasks with a week of float or less on a watch list, and ask their owners directly each week how the work is going, not whether it is on track. The question “what would make this late?” gets a better answer than “is it on track?”.

Tell people when the path changes. When the critical path moves from one team to another, tell both leads. The team that has become critical will want to know, and the team that has stopped being critical may want to lend help.

The map also feeds the other documents in this track: the charter’s dates come from it, the RAID log’s dependency entries come from it, and the launch readiness review draws on its end. Cross-team projects and migrations shows the tracking side of the same work at the scale of a migration, and owning a project end to end shows the same problem from the engineer’s seat.

Where practitioners disagree

Gantt chart or dependency table? A Gantt chart shows the path at a glance and is persuasive in a steering meeting, but it takes work to maintain and hides the agreement behind each bar. A table with one row per promise is dull and complete. Many TPMs keep the table as the source and draw a chart from it when someone needs to see it.

Pad the tasks or buffer the end? Goldratt’s followers hold that buffer belongs at the end of the chain, not inside each estimate. Others find that teams will not give up their padding, and that a task with no padding is a task people avoid committing to. A workable middle: let leads give likely estimates, add a visible programme buffer, and refuse to let it be spent without the sponsor’s agreement.

Map everything or only the seams? A map with every task of every team is accurate and unreadable. A map with only cross-team promises is readable and misses the long internal chains. Most programmes map the seams in detail and each team’s internal work as a single bar, and ask a team to open its bar when it is the one on the critical path.

Day to day

  • At the start of a programme. Run a dependency session with each lead, with the two-card exercise. Trace one order through every system. Fill the table, get each giver to confirm the date, and run the first forward and backward pass. Share the critical path and the near-critical chains with the sponsor.
  • Every week, before the update. Check which dates moved. Rerun the path. Look at the watch list: the tasks with a week or less of float. Ask each owner “what would make this late?” and note the answers in the table.
  • When a dependency slips. Recompute the same day. Say who is affected and by how much, tell the sponsor in two lines, and bring the options and not only the bad news. Float is the first thing to spend, and its use goes in the decisions list.
  • When two teams argue over a piece. Get the two leads together, with the interface in mind. Propose the split, write the contract, and record each owner on the map within a day.
  • Monthly. Look at the whole map with the sponsor: has the critical path changed teams, is the buffer being used faster than the work is done, and are the external dependencies still on their dates?
BY ORG SIZE
STARTUPunder 30 people

There is no TPM and little formal planning, and dependencies live in people’s heads because everyone sits in one room. The risk is the dependency on one person or one outside party: the engineer who knows the ledger, the bank that must switch something on. Write a list of five lines: what is needed, from whom, by when. Review it at the weekly meeting and ask the outside parties first. A spreadsheet is plenty. Avoid chart software, because it takes longer to keep current than the programme runs.

SCALE-UP30 to 300

Teams plan separately and the seams between them are where dates slip. This is where a TPM builds the first dependency table, and where leads resist it as paperwork. Show them what it saves by finding one orphaned piece in the first session. Keep it to cross-team promises, give each a named giver and a date the giver has agreed, and rerun the path weekly. Shared environments and the few engineers who know the old systems are the constraints that most often turn up on the critical path.

ENTERPRISE300 and up

Dependencies cross divisions and vendors, and a programme office may already own a master schedule in a planning tool with its own conventions. Feed that tool and do not run a rival: one source, with float and agreed dates visible. Many dependencies are contractual or regulatory and carry formal change processes, so ask early and record the lead time. Expect the path to run through other people’s roadmaps, and the work to be agreeing priorities as much as dates.

ARTEFACT Build a dependency map and find the critical path ~60 MIN
YOU PRODUCEDependency map: a table of agreed promises, the forward and backward pass, float, the critical path and a watch list

Template

# Dependency map: <programme>, week <n> of <n>
Launch: week <n> · Map covers weeks <a> to <b> · Updated: <date>

## Promises
| ID | Thing needed (testable) | Giver | Taker | Weeks | Waits for | Giver agreed? (date) |
|---|---|---|---|---|---|---|
| | | | | | | |

## Forward and backward pass
| ID | Earliest start | Earliest finish | Latest finish | Float | Critical? |
|---|---|---|---|---|---|
| | | | | | |

## The critical path
<ID> → <ID> → <ID> = <n> weeks, finishing in week <n>
Launch week <n>: spare weeks = <n>

## Watch list (float of one week or less)
| ID | Owner | Float | The question to ask |
|---|---|---|---|

## Pieces with no owner, or two
| Piece | Claimed by | Split at | Owner of each half | The contract (field, unit, rule) |
|---|---|---|---|---|

## External dependencies
| Item | Company | Lead time | Ask by |
|---|---|---|---|

## Note to the sponsor
Path: <...>. Float: <...>. Decision needed: <what, who, by when>.
WORKED EXAMPLE

Ojaline’s Pay in four, week 4 of 14. Weeks 1 to 4 went on scoping and design, so the map covers weeks 5 to 13, with launch in week 14. Durations are illustrative. Akua has run a session with each lead and traced one order through every system.

ID Thing needed Giver Weeks Waits for Start-finish Float
A Lending API contract frozen, with sample responses Ezenwa (Owoleaf) 2 none 5-6 0
C Fee rule and order-event field agreed Ukamaka (Checkout) 1 none 5-5 1
S Seller Wallet deducts the fee, posts it, itemises it on statements, reverses it on refund Obiomachukwu 4 A, C 7-10 0
F Risk limit rules Tomoko 1 A 7-7 1
B Checkout limit display Rabiu 2 F 8-9 1
E Instalment collection and refunds Selma (Payments) 3 A 7-9 1
D Northmere settlement change for Owoleaf Northmere, asked through Ezenwa 5 none 5-9 1
H Terms and disclosures Legal and Compliance 3 none 5-7 3
G Data events and reporting Data 2 E 10-11 1
Cs Support scripts and training Customer Support 2 H, B 10-11 1
T End-to-end test Akua convenes 2 S, E, B, D 11-12 0
LR Launch readiness review Akua convenes 1 T, G, Cs 13-13 0

Critical path: A, S, T, LR: 2 + 4 + 2 + 1 = 9 weeks, weeks 5 to 13, so launch in week 14 holds with no spare week. Watch list: C, F, B, E, D, G and Cs each have one week of float, so any one slipping a week makes a second critical path; D matters most, because Northmere is outside Ojaline’s control.

The orphaned piece. Obiomachukwu says Checkout must calculate the 7% fee; Ukamaka says Seller Wallet must deduct it. Akua splits it at the order event. Checkout works out the fee, 7% of the order value rounded to the nearest kobo (₦40,000 gives ₦2,800), and sends it as fee_kobo. Seller Wallet reads it, deducts it from the payout and posts it. Both agree; C and S are two rows with two owners.

Note to Murtala. The path runs through Owoleaf’s contract and Seller Wallet. One week of float exists, held by seven chains; its use is a decision for him and Akua. Decision needed: none this week.

Now you

You are Akua at the start of week 8 of the 14-week Pay in four programme. Owoleaf’s lending API contract (A) finished in week 7, a week late. The fee rule (C) is done. Remaining work, in weeks, with what each waits for: Seller Wallet deduction S, 4 (nothing); Risk limit rules F, 1 (nothing); Checkout limit display B, 2 (F); Payments E, 3 (nothing); Northmere settlement D, 2 (nothing); Data G, 2 (E); Support training Cs, 2 (B); end-to-end test T, 2 (S, E, B, D); readiness review LR, 1 (T, G, Cs). Launch is week 14. Murtala asks whether it holds. Obiomachukwu says a second engineer from week 8 would cut S from 4 weeks to 3. Produce the forward and backward pass, the critical path with and without the second engineer, the watch list, and a three-line note to Murtala.

Self-check

DECIDE

You are Akua, the TPM for Ojaline's Pay in four launch, in week 4 of 14. Seller Wallet's engineering manager Obiomachukwu says Checkout must calculate the 7% seller fee because it knows an order is a Pay in four order. Ukamaka, who manages Checkout engineering, says Seller Wallet must deduct it because the money is the seller's balance. Neither team has planned the work. The fee rule has one week of float, and the Seller Wallet build, which waits for it, is on the critical path. Murtala is the sponsor and Rabiu's limit display does not depend on the fee. What do you do?

READING
  1. BOOK
    Critical Chain Eliyahu M. Goldratt, 1997

    The case that padding inside each task is wasted, and that float is better held as a shared buffer; read it to argue about who owns the float in your map. Read: The chapters on how estimates are padded and on moving the buffer to the end of the chain.

  2. BOOK
    The Mythical Man-Month: Essays on Software Engineering, Anniversary Edition Frederick P. Brooks Jr., 1995

    On how a project slips one day at a time, and why sharply defined milestones and a view of how they depend on each other show how much any one slip matters. Read: Chapter 14, Hatching a Catastrophe.

  3. DOC
    GAO Schedule Assessment Guide: Float Management US Government Accountability Office

    A public-audit view of why you cannot watch the critical path without also watching float, and what it means when critical-path float is used up.

  4. DOC
    GAO Schedule Assessment Guide: Common Barriers to a Valid Critical Path US Government Accountability Office

    Lists how a critical path goes wrong, including missing activities and wrong float, which are the failures a cross-team dependency map is most likely to have.

  5. HANDBOOK
    NASA Schedule Management Handbook NASA, 2020

    A public handbook with a section on identifying the critical path in a large multi-team schedule; useful for the vocabulary of forward pass, backward pass and float.

All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.