Portfolio planning across quarters
Every programme has a plan that fits, and the plans together do not. A portfolio view adds them up by team and quarter, shows where the sum breaks, and lets the people who own the money choose what gives
Three programmes at a 200-person company each have an approved plan, and each plan fits the team it leans on most when read alone. You add the three plans together by team and by quarter. What do you most likely find?
A programme plan answers one question: can this be done by this date, in what order? The critical path from dependencies and the critical path is the answer, and it assumes the teams are free when the work reaches them. A portfolio asks the other question: can we do all of this with the people we have? At the lead level your horizon is a year, you own several programmes or the view over all of them, and most of the bad news you can see early is about capacity.
This chapter assumes you have a charter for each programme (scoping and the programme charter) and a map of each one’s dependencies. It adds the layer above: the sum, and what to do when it breaks. The allocation of capacity between running the business and building new things belongs to the head of engineering, and engineering strategy and planning teaches it. The question of what is worth building is product strategy. You supply what neither has: one honest picture of demand against capacity, by team, by quarter.
The model: plans are about time, portfolios are about capacity
A programme plan has time on one axis and tasks on the other. A portfolio view has teams on one axis and quarters on the other, and in each cell it puts two numbers: what the programmes demand of that team in that quarter, and what the team can supply. The unit is the engineer-week.
Gross capacity is headcount times weeks. Owoleaf’s Lending team has 7 engineers, so a 13-week quarter gives 91 engineer-weeks. Net capacity is what is left for programme work after run work, on-call, leave, interviews and meetings. Say a team’s own record shows that takes 40%: 91 × 60% is 54.6, which you round to 55. The 60% is illustrative, so use the team’s measured figure; a team that has never measured it will tell you a number that is too high. The programmes can spend only the net figure. Spending the gross figure is how the three programmes in the Why above all came to be on time on paper.
Two rules of thumb make the numbers usable.
Plan to a ceiling below 100%. A team planned to the last week has no room for the incident, the resignation or the estimate that grows. Donald Reinertsen’s Principles of Product Development Flow argues that queues grow sharply as utilisation approaches 100%, so a team near full use delays everything behind it, including work that is not on your list. Most TPMs pick a ceiling and say so. This chapter uses 90% of net capacity, a rule of thumb and not a standard. Set your own from how your teams have behaved.
Count a new hire at half capacity in their first quarter. The head of engineering’s planning chapter uses the same convention. Hires arrive over months, and a person who starts in week 6 of a quarter contributes little to it.
Capacity, not effort, is what the view is about. A programme that needs 120 engineer-weeks in total can be small or large relative to the teams it touches. What matters is which team the weeks fall on and in which quarter.
The portfolio view on one page
One table carries the whole argument. Each row is a programme. For each programme you record what it is worth, how firm its date is, who owns it, and its demand on each team in each quarter. Under the programme rows sit three more: the total demand on each team, the team’s net capacity, and the load as a percentage of capacity.
The date column does the most work, because it decides what can give. There are three kinds.
| Date | What it means | Example |
|---|---|---|
| Fixed | Set by something outside the company or by the calendar; missing it loses the outcome | A launch eight weeks before year-end sales; a partner’s contract end |
| Committed | Promised to someone inside, such as the board or a sponsor; missing it costs trust, not the outcome | A product the chief executive named in the plan |
| Soft | Wanted, with no one hurt if it moves a quarter | Most internal improvements |
Fix the fixed dates first. A programme with a fixed date is not part of the negotiation; the others are arranged around it. If a sponsor calls every date fixed, ask what happens on the day after, and write down the answer. People who must say it aloud usually find that two of the three can move.
The critical path and the portfolio view fit together. The path says how soon a programme can finish if teams are free when the work reaches them. The view says whether they will be. A programme can have a clean path and a team that is 125% booked in the quarter its critical tasks fall, and the plan is then wrong although every dependency is agreed. Run the view whenever a new programme is proposed, when a date moves and at least monthly.
Getting numbers you can defend
The view is only as good as its inputs, and there are two you will argue about.
Demand. Ask each team lead, for each programme, how many engineer-weeks of that team’s time the work takes in each quarter, as a range. The lead’s first number is usually the effort to build, not the attention it needs: it omits design review, the partner’s questions, testing support and the weeks the programme waits for someone else. Ask for the likely figure and the one that would worry them, as in the dependency session, and plan to the likely one with the gap noted. Where two programmes ask the same team for the same weeks, the lead is the right person to say which they would do first, but not to say which should.
Capacity. Take the measured net figure from the lead and check it against the last two quarters: how much programme work did the team actually finish, in engineer-weeks, against how many it said it had? If the answer is 70% of the claim, the claim is the problem. Ask about the planned absences, the on-call rota, and whether a vacancy is open. A lead who is told that the view will be shared with the head of engineering often gives a more honest number, because the alternative is being blamed for one that was wrong.
Multitasking is not free. A team on three programmes at once finishes each later than a team that does them one after another, which is the argument Eliyahu Goldratt makes in Critical Chain and the reason many teams limit work in progress. A view that shows one team in three programmes for the same quarter is showing a risk even when the percentage looks safe.
A worked case: Owoleaf’s three programmes
Owoleaf has 200 people and 44 engineers in six teams. At the planning round for Q3 and Q4 three programmes ask for the same teams. Every figure below is illustrative.
- Co-lending with Northmere (C). The term sheet under negotiation has Northmere funding 80% of each loan and Owoleaf 20% with a first-loss guarantee. The build is the loan flows, disbursement, repayment and reporting split. It leans on Lending and Transfers.
- Pay in four partner work (P). Owoleaf’s side of the programme in the TPM track’s running example, which Ojaline launches in Lagos in week 14. Count programme week 1 as the first week of Q3, so week 14 is Q4 week 1, week 20 is Q4 week 7 and week 22 is Q4 week 9. Owoleaf freezes the decisions API contract, integrates the settlement change Northmere makes, and lifts the API cap of 15,000 decisions a day in week 20. Lagos uses about 9,000 a day and each other city about 1,500, so Lagos and four cities use the whole cap. Lagos launches in week 14 and four cities follow at about two a week, so the cap is full from week 16 until it lifts. The other four go live in weeks 20 and 21, ahead of the sales. The launch and the year-end sales in week 22 are fixed. It leans on Lending and Transfers.
- USSD expansion (U). Extend the existing USSD channel, which runs through an aggregator, with send-money. No date is fixed. It leans on Transfers and Growth.
Net capacity per quarter is 55 engineer-weeks for Lending, 70 for Transfers and 55 for Growth. With the 90% ceiling those become 49.5, 63 and 49.5. Added by team, the three programmes load Lending to 45 in each quarter, which is 82%, and Growth to 15, which is 27%. Transfers is asked for 85 in Q3 and 75 in Q4, which is 121% and 107%. No programme looks impossible alone. The sum is 22 engineer-weeks above the ceiling on one team in Q3 and 12 above it in Q4. The numbers and the options appear in full in the Artefact below.
This is the common shape: one shared team, over by a few weeks, in the quarter the fixed date falls. It is not a shortage of engineers. It is one team, so the answer is about that team.
When demand is more than capacity
You have five moves, in roughly the order of how cheap they are.
| Move | Right when | What it costs | How long to take effect |
|---|---|---|---|
| Cut scope inside a programme | The charter has a should or a could that is not a must | The item, and the argument to remove it | Days |
| Drop a programme | Its value is the lowest and its date is soft | The value, and the people who proposed it | Immediate |
| Stagger | Dates are soft and the team can take longer | A later date, restart cost, and the same load in a later quarter | A quarter |
| Add contractors | The work is separable behind a stable interface and someone can review it | A review tax, handover risk, and a budget | Weeks to be productive |
| Add headcount | The gap lasts beyond a year | Months before it helps, and half capacity in the first quarter | Months |
Four mistakes recur.
Staggering a fixed date. The programme with a fixed date cannot move, so staggering all three means moving only the other two and loading the shared team in the quarters left. Check where the load went. In the Owoleaf case, pushing C a quarter later leaves Transfers at 100% in both quarters: no longer over capacity, but still over the 90% ceiling.
Dropping the wrong one. Dropping a soft programme feels decisive, but check that it relieves the shared team. Dropping C at Owoleaf leaves Transfers at 100% in Q3, because P and U together still fill it. Dropping U fits.
Treating headcount as this quarter’s answer. A request for two engineers is reasonable and may be right for the year. It does not close Q3’s gap, because hires arrive later and count half in their first quarter. Two Transfers hires at the start of Q4 add about 8 engineer-weeks in that quarter and nothing in Q3.
Believing contractors are free capacity. Fred Brooks’s law, from The Mythical Man-Month, says that adding people to a late software project makes it later. The cost is mostly the existing team’s time: explaining the system, agreeing the interface, reviewing the work and taking the pager afterwards. Put the tax in the view as a number. In the Owoleaf case, three contractors supply 33 engineer-weeks a quarter on the USSD build (39 gross, less about 15% for onboarding), and Transfers keeps 12 of the original 45 for review and ownership. That is a 27% tax, in an illustrative case. Contractors work when the scope has a clean edge, a named internal owner, a written interface and a handover that moves the on-call to someone who stays.
Sequencing across quarters
The view shows more than whether the sum fits. It shows the order.
Put external dependencies first. The work waiting on another company has the longest lead time and the least slack. At Owoleaf, Northmere’s settlement change for Pay in four and the co-lending flows ask the same bank for engineering time. Ask Northmere for one joint plan, not two requests. A TPM at this level spends a good part of the week on this; programmes that cross company boundaries are the subject of programmes across companies.
Do not let work straddle a boundary unseen. A programme that needs 25 engineer-weeks from a team in Q3 and 30 in Q4 may be carrying 5 weeks of work from Q3 into Q4 when Q3 runs short. Watch carry-over: it is how a quarter that looked safe becomes the next quarter’s overload.
Leave the slack where the risk is. The quarter containing a fixed date is the one in which an incident hurts most. Plan the shared team lighter then, and heavier in the quarter after it.
Treat people moves as portfolio events. A resignation on the shared team is not a programme risk, it is a change to the denominator for every programme. Re-run the view the week it happens.
Who decides
You do not decide which programme gives way. The head of engineering owns how engineering capacity is allocated, and the product and business owners say what each programme is worth. What you own is the view, the facts in it, and the options.
For each option, say what it costs in the same units: engineer-weeks, quarters, and the named programme that slips. Add what would have to be true for the option to be wrong. Give a recommendation, because a list of five options with no view is a way of avoiding the decision. Then take it to the one meeting where the people who decide are in the room; managing across teams and upward covers how to put a hard choice to a sponsor, and delivery and planning covers how a single manager plans a quarter from the other side.
Once the choice is made, write it down with its reason and the date it will be reviewed. A portfolio decision with no review date becomes a permanent one.
Keeping the view alive
A portfolio view drawn in the planning round is stale by week four. Three habits keep it current.
Re-run it monthly, and on events. The events are a new programme proposed, a fixed date moving, a resignation or a long absence on a shared team, and any team’s actual progress falling more than about 10% behind its estimate (a rule of thumb). Each is a reason to recompute that day.
Track actuals against demand. At the end of each month, ask each lead how many engineer-weeks each programme really took. Over two quarters you learn each team’s real net capacity and each programme’s real demand, and you stop guessing both.
Say what changed. When the view moves, send the people in the decision a short note: what changed, which cell is now over, and what you recommend. Record a portfolio risk as risk management and the RAID log teaches for a programme risk, with an owner and a date.
Where practitioners disagree
Fixed allocation or project by project. Bansi Nagji and Geoff Tuff’s study of innovation portfolios reports that high-performing firms split innovation investment among core, adjacent and transformational work in a rough ratio, which their article’s abstract gives as about 70, 20 and 10. Many engineering leaders turn this into a fixed allocation by category. Others plan programme by programme. A fixed split protects the long bets from the urgent ones. The programme-by-programme view is more flexible and lets the urgent crowd out the long. The ratio is a benchmark from one study, not a rule for your teams.
Quarterly or shorter. Quarterly planning gives teams a stable horizon but commits you to what you knew three months ago. Basecamp’s Shape Up describes a shorter cycle, six weeks, with a betting table where stakeholders decide what the next cycle holds, and a break between cycles. A TPM in a firm on a six-week cycle runs the same view at that cadence. The size of the cycle matters less than how often someone is allowed to say no.
A central portfolio office or TPMs inside programmes. A central office sees every programme and can run the view well, but it is far from the work and its numbers go stale. TPMs inside programmes know their own numbers and will protect their own programme. Many companies settle on embedded TPMs with one lead who owns the view.
Day to day
A TPM’s week shows the weekly rhythm for one programme; this is the portfolio layer above it.
- Every week. Ask the leads of shared teams one question: what has taken your time that was not on the plan? Update the actuals column. Read the programme updates for slips that change a team’s load.
- Every month. Re-run the view with fresh actuals and any events. Send the short note to the head of engineering and the programme sponsors: the cells over the ceiling, what moved, what you recommend. Review the decisions that have review dates.
- In the six weeks before each quarter. Collect demand by team for the quarter ahead, as ranges. Collect capacity, with absences, hires and the on-call rota. Build the view, draft options for every cell over the ceiling and agree the recommendation with the head of engineering before the planning meeting, not in it.
- At the planning meeting. Present the view on one page, the fixed dates first, then the options. Leave with a decision for every over-ceiling cell, or a date by which it will be made.
- When a programme is proposed mid-quarter. Add it to the view before anyone says yes. The answer is usually not no. It is a statement of which programme gives way, and who agreed.
Under 30 people there is no portfolio office and the founders hold the portfolio in their heads. The view is a short list: the three things the company is doing this quarter, the two or three people who do them, and the one thing that stops if someone is ill. The danger is the same engineer named on all three. Write it on one page, give one person the right to say no, and look at it monthly. A spreadsheet is more than enough.
This is where the portfolio view is built for the first time, because the teams are shared and the programmes are sponsored by different people. Start with the shared teams only, usually platform, payments and data. Record fixed dates and net capacity. Expect the first round to be resisted as a tax on planning, and win it by finding one team booked at 125% that nobody knew about. Ask the head of engineering to chair the decision.
Several hundred engineers means many portfolios, often a programme office with its own tool, and the political work is agreeing whose number is the capacity. Feed the office’s tool instead of keeping a rival. Fixed dates may be regulatory or contractual, so record the source. Contractors and vendors follow procurement rules with long lead times, so ask early. Expect the view to cross divisions, and the decision to be made by people who did not build it.
Template
# Portfolio view: <company>, <quarters covered>
Updated: <date> · Ceiling: <n>% of net capacity · Author: <TPM>
## Net capacity (engineer-weeks per quarter)
| Team | Engineers | Gross (x weeks) | Share for programme work | Net | Ceiling |
|---|---|---|---|---|---|
## Programmes
| ID | Programme | Value | Date (fixed / committed / soft) | Owner |
|---|---|---|---|---|
## Demand by team (engineer-weeks)
| ID | Team | Q1 | Q2 |
|---|---|---|---|
## Load
| Team | Quarter | Demand | Net | Load % | Over ceiling by |
|---|---|---|---|---|---|
## Options for each over-ceiling cell
| Option | Load after | What it costs | Right when | Wrong when |
|---|---|---|---|---|
## Recommendation
<option>, because <reason>. It costs <...>. It would be wrong if <...>. Review on <date>.
## Note to the decision-makers
Cells over: <...>. Recommended: <...>. Decision needed: <what, who, by when>. WORKED EXAMPLE
Owoleaf, Q3 and Q4, illustrative. Teams: Lending 7 engineers, Transfers 9, Growth 7. Net capacity is engineers × 13 weeks × 60%: Lending 55, Transfers 70, Growth 55. Ceiling 90%: Lending 49.5, Transfers 63, Growth 49.5.
| ID | Programme | Date | Lending Q3 / Q4 | Transfers Q3 / Q4 | Growth Q3 / Q4 |
|---|---|---|---|---|---|
| C | Co-lending with Northmere | Soft | 25 / 30 | 15 / 20 | none |
| P | Pay in four partner work | Fixed: Lagos launch in week 14, year-end sales in week 22 | 20 / 15 | 25 / 10 | none |
| U | USSD expansion | Soft | none | 45 / 45 | 15 / 15 |
Load with all three. Lending 45 and 45, which is 82% each quarter. Growth 15, which is 27%. Transfers 85 and 75, which is 121% and 107%. Transfers is over the 63 ceiling by 22 engineer-weeks in Q3 and 12 in Q4.
Options for Transfers.
- Drop C: Transfers 70 and 55, which is 100% and 79%. Q3 is still over by 7.
- Drop U: Transfers 40 and 30, which is 57% and 43%. It fits, and the USSD expansion is lost for the half-year.
- Stagger C a quarter later: Transfers 70 and 70, which is 100% twice. Over by 7 each quarter.
- Two Transfers hires from the start of Q4, at half capacity: about 8 engineer-weeks in Q4, none in Q3. Q3 stays over by 22.
- Contractors build U: three contractors supply 33 engineer-weeks a quarter (39 gross, less onboarding), and Transfers keeps 12 of U’s 45 for review and ownership. Transfers 52 and 42, which is 74% and 60%.
Recommendation. Run C and P in-house and let contractors build U. It costs three contractors for two quarters and a 27% review tax on U (12 of 45). It would be wrong if U’s scope cannot be separated behind a written interface, or if P’s Transfers demand grows by more than the 11 engineer-weeks of room in Q3 (63 less 52). Review at the month-end re-run in each quarter.
Now you
You are the TPM at a Lagos card-payments company with 30 engineers in four teams: Cards 8, Platform 7, Merchant 8, Mobile 7. Net capacity is 60% of 13 weeks per engineer, a quarter’s figure for each team. Plan to a 90% ceiling. Three programmes ask for Q1 and Q2, with demand in engineer-weeks as Q1 / Q2.
- A, processor move. Fixed: the current processor’s contract ends in week 20. Cards 40 / 30, Platform 30 / 10.
- B, merchant dashboard rebuild. Soft. Merchant 45 / 35, Platform 15 / 15.
- C, savings product. Soft, though a competitor launched one. Mobile 40 / 40, Platform 24 / 20, Cards 10 / 10.
The chief executive wants all three. Platform has no open vacancies. Produce the view, find every cell over the ceiling, and propose the smallest change that brings every cell to or below it without moving A.
Self-check
You are Ayokunle, the senior TPM at Owoleaf, a wallet with 200 people and 44 engineers in six teams. Dorothea, the head of engineering, asks for the Q3 and Q4 plan. Three programmes want the Transfers team: co-lending with Northmere, Pay in four partner work and the USSD expansion. Pay in four has fixed dates, the launch in week 14 and year-end sales in week 22. The other two are soft. Added up, Transfers is booked to 121% of its net capacity in Q3 and 107% in Q4, 22 and 12 engineer-weeks above your 90% ceiling. Finance has approved budget for three contractors for two quarters and no new headcount this year. What do you recommend?
- POST Managing Your Innovation Portfolio Bansi Nagji and Geoff Tuff, 2012
The study behind the core, adjacent and transformational split. Its abstract reports a rough 70, 20 and 10 allocation among high performers; read it as a benchmark to argue with, not a target for your teams.
- POST How to plan as an engineering executive Will Larson
The executive's side of the same problem: an annual plan, a quarterly plan and a financial plan, an allocation of the portfolio across functions and a roadmap. Read it to know what your head of engineering is deciding when you bring them the view.
- BOOK Shape Up: The Betting Table Ryan Singer, Basecamp
A published alternative to quarterly planning, in which a small group decides what the next cycle holds and everything else waits. Read it for how a company says no on a fixed rhythm. Read: Chapter 8, The Betting Table, which describes how stakeholders choose the work for the next six-week cycle.
- BOOK The Principles of Product Development Flow Donald G. Reinertsen, 2009
The argument that queues grow sharply as a team nears full use, which is the reason to plan a team to a ceiling and not to 100%. The catalogue page is a library record; the book is the source. Read: The principles labelled Q, on queues and capacity utilisation.
- BOOK Team Topologies: organizing business and technology teams for fast flow (publisher's excerpt) Matthew Skelton and Manuel Pais, 2019
The case for fitting what a team owns to what it can hold. Read it when you are asked to put a third programme on a team that already has two. Read: The sections on a team's cognitive load.
All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.