HEADCHAPTER 14

Building a TPM function

Ration the TPM by programme, not by team, choose a reporting line that sits beside the project office instead of against it, and hire to the demand curve, because the first months are always short of people

45 MINTECHNICAL PROGRAM MANAGERUPDATED 2026-11-21
PREDICT

A bank's technology division has 340 engineers in 28 teams, a project office that runs every programme on one template, and budget for four TPMs. What do heads who build this function well do first?

At practitioner level you ran a programme. At lead level you ran a portfolio of them and programmes that crossed company boundaries, as in portfolio planning across quarters. At head level you decide what the function is made of: how many TPMs, where they report, how they are hired, levelled and paid, which programmes get one, and how they sit beside whatever already runs programmes in your company. You are judged by the head of engineering on whether the organisation delivers what it commits to, and you cannot run every programme yourself.

Why TPMs exist defines the role and says when a company needs one. This chapter assumes you are past that trigger and does not repeat the definition. The artefact is a hiring and engagement model. All salary and cost figures here are illustrative: they are chosen so the sums can be checked, not drawn from a survey, and you should replace them with your finance team’s loaded costs.

The data and AI tracks have chapters on building their functions too: building the data function and building an AI team. They turn on what to buy and what to train. A TPM function has nothing to buy, so the hard questions here are different. Who already owns the work, and what does a TPM add to it? Which programmes deserve the scarce person? How do you say all of that on one page?

The model: ration the TPM, then size the function

A TPM’s value is concentrated in a few programmes. On a programme that crosses two teams, a manager and a shared document do the job. On one that crosses nine teams and a vendor, a TPM earns the salary many times over. So the first act is to count programmes, not engineers, and for each ask three questions.

  • How many teams does it cross?
  • Is an outside party, a partner, a vendor or a regulator, on its critical path?
  • How fixed is its date?

From those answers you write an engagement criterion, a sentence that sorts every programme into one of two piles. Northmere’s is: a TPM is assigned when a programme crosses five or more teams, or has an outside party on its critical path. A programme below the line is not left alone. It runs under its engineering manager on the office’s template, with a monthly look at its risk log from the TPM function.

Next, turn the pile into demand. Count TPM-months: the months each qualifying programme needs a TPM, laid out by calendar month. As a rule of thumb, one TPM carries one large programme at a time, and two only when one of them is in its quiet closing months. That makes the monthly count of qualifying programmes the number of TPMs you need that month. The curve matters more than the total, because hires start late. A first TPM search from outside takes about two quarters in most markets (a rule of thumb), so a plan that needs four people in January has them in July.

Northmere’s 2027 plan has nine engineering-heavy programmes. Six cross four or more teams, and five meet the criterion:

Programme Teams crossed Outside party Months needing a TPM
Settlement change for Owoleaf 6 Owoleaf Apr–Sep (6)
Co-lending with Owoleaf 7 Owoleaf Mar–Dec (10)
Core ledger upgrade 9 The ledger vendor Feb–Nov (10)
Retail app rebuild 5 None Jan–Jun (6)
Data centre move 8 The hosting provider Jul–Dec (6)

That is 38 TPM-months. The monthly count runs 1, 2, 3, 4, 4, 4, 4, 4, 4, 3, 3, 2 from January to December. Ratios will not give you that shape. Writers on the role do give TPM-to-engineer ratios, and Pragmatic Engineer’s account of scaling the role is worth reading for them. Treat a ratio as the data chapter treats analyst ratios: a rule of thumb that carries another company’s constraint. The settlement change and co-lending draw on the same Northmere teams from March to September, so the plan asks Owoleaf for one joint schedule, as portfolio planning across quarters advises.

Four ways to staff it

The seed for Northmere’s choice is a familiar one: the office runs programmes by template, and engineering wants TPMs. There are four routes, and each is right somewhere. Costs use an illustrative loaded cost of ₦39m for a TPM (base ₦30m times a loading factor of 1.3), ₦32.5m for a TPM hired onto the office’s lower ladder, and ₦26m for an office project manager.

Route TPMs Cost a year (₦m) Time to a first programme Fits when
Per programme, led from engineering 4 169 One month for an internal move; about six from outside Demand sits in a few programmes that end
One in every engineering team 28 1,092 Six months or more A few teams carry cross-team work every quarter
A pool inside the office, on its ladder 4 130 As outside hiring, with offers below the engineering band The office is led by an engineer and its pay matches
Convert the office’s project managers 4 156, plus 15.6 once About six months: assessment, then pairing Several managers pass the same work sample

Check the sums. Four per programme is one Senior TPM at ₦52m and three at ₦39m, which is ₦169m. Twenty-eight at ₦39m is ₦1,092m. Four at ₦32.5m is ₦130m. Four converts at ₦39m is ₦156m, and the one-off ₦15.6m is the engineers’ pairing time: four engineers at 20% of their time for half a year, ₦39m each, which is ₦3.9m apiece.

Two things about the table. First, the routes are not exclusive. The per-programme route says where TPMs sit; how you fill the four posts is a separate choice, and a sensible plan mixes sources: one internal move, two office staff who pass the work sample, one outside senior hire. Second, the cheapest route is the pool inside the office, and its cost is in the last column, not the third. Offers below the engineering band lose the technical candidates, and you end up with project managers retitled as TPMs. Why TPMs exist names the friction between an office and engineering as a head-level problem. This is where it lives.

The office is a neighbour, not the problem

A project management office is not a caricature. In a bank it holds what engineering lacks and the regulator expects: a portfolio view, finance controls, benefits tracking and an audit trail for every approval. Jorien’s office reports about sixty projects to the executive committee on one template, and nobody else can do that. What it cannot do is judge whether a plan is fiction. A template records that Delivery Reports is green. It cannot see that Delivery Reports needs a sandbox in week three and Routing delivers it in week seven.

So draw the boundary around what each side does best, and write it down.

The office owns the portfolio view, the template, finance reporting, the audit trail and the monthly report to the executive committee.

The TPM owns the programme’s plan, dependencies, risk log, written weekly update and date, as set out in scoping and the programme charter, dependencies and the critical path and risk management and the RAID log.

One source of status. The weekly update is the source. The office extracts its monthly colour from it, by the evidence rules in status, escalation and bad news, and no team writes the same thing twice. If the office needs a field the update lacks, add the field to the update.

The office’s template runs the first month. Its charter template is good at scoping, so let it run a programme’s first month before a TPM arrives, then hand over. This is not a concession. It is the cheapest use of both.

The PMI standard for program management describes the program manager, the sponsor and the programme office as roles. It is the vocabulary your office will use, so learn it and say where you agree.

What to hire for

The track’s own ladder says what you are hiring. A TPM owns programmes across several teams, and is judged on whether they landed, how early the bad news came and whether teams would work with them again. A good loop tests those things, and follows hiring and interviewing for method: same questions for every candidate, written anchors, scores before the debrief. Google’s re:Work guidance on structured interviewing sets out why.

The TPM-specific loop has four rounds, matching what the work involves.

Round Tests Evidence you want
Programme round Judgement under slip ‘Walk me through a programme that went wrong’: when they knew, who they told and what it changed
Technical round Depth to follow the system A system explained at the level of understanding, not building; see how technical a TPM must be
Risk or escalation scenario Telling the truth upward A sponsor asks for amber while the programme is red
Stakeholder round Whether teams would work with them again Run by an engineering manager and a product manager

Add a work sample you can score. Give candidates a one-page plan for a six-team programme with a planted fiction: every team reports green, but one team’s test needs an input in week three that another team delivers in week seven, and one risk belongs to two teams and to neither. Allow ninety minutes. A strong candidate finds the inverted dependency, asks who owns the risk and says what they would tell the sponsor on Friday. A weak one reformats the plan.

Put an engineer and a project office lead on the panel, and have each score alone. If only engineers interview, you hire people who talk like engineers. If only the office interviews, you hire people who talk like the template.

Where TPMs come from

Four sources feed the function: engineers who kept coordinating cross-team work, project managers who built technical depth, engineering managers and SREs who prefer programmes to people, and outside TPMs. Each brings something and lacks something.

Converting the office’s staff deserves care, because it is the choice most likely to be done unfairly. Some project managers are already strong TPMs. Others have run projects well and never had to say a plan is fiction. Give every candidate the same loop and work sample, tell the office it is open to its people, and promise nobody a post. Those who pass need about six months of pairing with a senior engineer to get a sense of the system, as a rule of thumb, and their first programme should be one with a strong engineering manager. If none pass, say so, and recruit from outside. Converting people who fail the sample is how a function becomes a retitled office.

Levels and pay

Use the track’s ladder: Associate TPM or Programme Coordinator; TPM; Senior TPM or Principal TPM; Head of Programmes or Director of TPM. Write each level in outcomes and scope, not tools. An Associate runs a workstream under a senior and is judged on tracking and on risks reaching the right person. A TPM owns a programme across several teams for a quarter or two. A Senior or Principal owns the largest programmes, a portfolio, or programmes across companies, and coaches others. Give scope a number, such as teams crossed, so a promotion case is an argument from evidence.

Place TPMs on the engineering ladder, not the office’s. A TPM must be paid close to the engineers whose plans they challenge, or the first hard conversation starts with a pay gap. The cost is that engineering bands run above the office’s in most banks. In the illustration the office’s project manager has a base of ₦20m and a TPM ₦30m. Handle the difference as the AI chapter handles a market premium: approve exceptions in writing with a review date, run a compression check before offers go out, and fix permanent differences in the band at the annual review. The method is in hiring, levelling and compensation.

TPM promotion has a particular hazard. When the work succeeds, little is visible: the slip that did not happen leaves no trace. Ask each TPM to keep a short evidence file: dates held, bad news given and how many weeks ahead, decisions that were forced early, and what the sponsor and the engineers said. Put the sponsor’s and two engineers’ views in every promotion packet.

The engagement rule

Without an engagement rule, a TPM function drifts into being a status layer on every project. Write one page. It should say:

  • The criterion. Which programmes qualify, in a sentence a sponsor can apply.
  • The mandate. The sponsor signs a charter; the TPM owns the plan, dependencies, risks, status and date; the TPM does not decide the design, the product or anyone’s priorities.
  • The load. One large programme at a time, two only at the edges.
  • The exit. A TPM leaves a programme 90 days after launch, or when a migration’s tail has a named owner. See launch readiness and cutover and running a migration programme.
  • What programmes below the line get. Their engineering manager, the office’s template and a monthly risk-log review.
  • Who decides disputes. Usually the head of engineering, in a fixed monthly slot.

The rule also helps you say no. An outside party on the critical path is itself a criterion; see programmes across companies.

What the function reports

Three measures say whether a TPM function works, and each has a baseline.

How early bad news arrives. For each programme that slipped, count the weeks between the first red report and the original date. Northmere’s baseline from last year is poor: five of six slips were green or amber until the final month. A first target of at least four weeks’ notice is a reasonable illustration.

Forecast accuracy. The share of milestones hit within a week of the forecast made a month earlier.

Coverage. The share of qualifying programmes that have a TPM and a signed charter.

Do not report hours in meetings, number of status updates or the share of programmes that are green: the last rewards softening colours, the failure the function exists to prevent.

Where practitioners disagree

Where the function reports. In engineering, TPMs learn the system and earn trust. In the office, programmes are run and reported the same way across the company. A third view puts TPMs under the chief operating officer. The choice follows where the sponsors are and who can protect the honest colour. Wherever you sit, write the interface with the other side.

Embedded, pooled or per programme. Embedding gives TPMs deep context and a risk of idle time. A pool gives flexibility and a risk of shallow knowledge. Per programme gives focus and a risk that the learning leaves with the TPM. Most functions end up with a pool that embeds in a programme for its life.

A smell or a service. Some argue that a large TPM headcount shows the system’s boundaries are wrong, since every feature needs six teams. They are sometimes right, and org design at 50, 150 and 500 gives the staff engineer’s route to fix it. Track the share of programmes that exist only because of one coupling, and send it to the architects.

Contractors or employees. A contractor TPM starts in weeks and takes the learning when the programme ends. Use one to cover a hard gap, such as January to April, with a named employee beside them.

Where it goes wrong

A function justified by headcount. ‘We need ten TPMs’ with no list of programmes. Count first.

Two trackers. The office and the TPMs keep separate status and teams report twice. Name one source.

TPMs without sponsors. A TPM assigned with no sponsor has responsibility and no backing. Do not place one.

The hero. One excellent TPM carries three programmes and leaves. Keep the load rule.

Conversion as a favour. Moving people who did not pass the work sample lowers the bar, and everyone sees.

Hiring to the total. Four TPMs by December, and nobody in March when the work is at its thickest.

Day to day

Weekly. A 30-minute review with your TPMs: each programme’s colour against its evidence, what is about to turn red, who needs cover. A check of open roles against planned start months. A short call with the office about anything its monthly report would not catch.

Monthly. A decisions session with the head of engineering on disputes, new programme requests against the criterion, and load. A joint review with the office head: the extracted colours against the TPM updates, and any difference explained. A look at the measures: notice, forecast accuracy, coverage.

Quarterly. The demand curve rebuilt against the portfolio, and the supply curve against hires and leavers. A decision on the next hire or none. Promotion and calibration with the evidence files. The engagement rule re-read, and changed only in writing.

Yearly. The hiring plan for the next planning season, with last year’s slips and notice at the top. Where this plan meets the planning calendar is the subject of the engineering operating rhythm.

Whenever a TPM leaves or a programme ends, decide within two weeks whether the post is backfilled as it was, changed or released, because the next programme is rarely the same shape.

BY ORG SIZE
STARTUPunder 30 people

Under 30 people there is no TPM function, and the right move is to write nothing grand. When a launch crosses teams, the most senior engineer or a founder carries it, with a one-page plan and a list of dependencies. Write down the engagement criterion now, as one sentence, so that you can tell later when a programme deserves a person. Do not hire a coordinator for administration. The risk is the programme living in one head, not the absence of a title.

SCALE-UP30 to 300

Wrenpost, with about 55 engineers in seven teams, is at the stage where the function is one person and a written rule. The Kenya carrier connection is due 1 March 2027 and the WhatsApp channel launches in the third quarter of 2027, and one TPM covers both only if they do not peak together. Write the criterion, name the sponsor and hold the second hire until a programme has nobody to run it. Hire the first TPM senior, because that person sets practice for the next.

ENTERPRISE300 and up

The function exists in several forms, and the problem is politics and evidence. At Northmere, with 4,800 staff, change goes through a weekly change advisory board, audit asks for proof that each change was approved and tested, and the office reports to the executive committee. Your work is the seam: one source of status, an interface the office accepts, a ladder the bank’s pay committee will recognise. Open with what the office keeps.

ARTEFACT Write a hiring and engagement model for a TPM function ~75 MIN
YOU PRODUCEA hiring and engagement model: the demand, the routes compared, the engagement rule, the roles and the measures

Template

# TPM function: hiring and engagement model, <company>, <year>
Owner · Sponsor · Date · Review date

## The demand
| Programme | Teams crossed | Outside party | Months needing a TPM |
|---|---|---|---|
Criterion: <one sentence>
Programmes below the line and what they get: <...>

## Demand against supply, by month
| Month | TPMs needed | TPMs in post | Gap and who covers it |
|---|---|---|---|

## Routes compared (assumptions stated, figures illustrative)
| Route | TPMs | Cost a year | Time to first programme | Fits when |
|---|---|---|---|---|
Chosen: <route>, because <reason>. Nearest alternative: <route>, not chosen because <reason>.

## The office and the function
Office keeps: <...>   TPM owns: <...>   One source of status: <...>

## Posts
| Post | Source | Level | Start | Loaded cost | Exception? |
|---|---|---|---|---|---|
Hiring loop and work sample: <...>   Scored by: <...>

## Engagement rule
Mandate · Load · Exit · Disputes decided by

## Measures
| Measure | Baseline | Target |
|---|---|---|

## What would change this
- <trigger>
WORKED EXAMPLE

Northmere Bank, TPM function, 2027. Ejiofor wrote it for the chief technology officer and Jorien. Figures are illustrative.

Demand. Five programmes qualify by the criterion ‘five or more teams, or an outside party on the critical path’: the settlement change for Owoleaf (6 teams, Owoleaf, April to September), co-lending with Owoleaf (7, Owoleaf, March to December), the core ledger upgrade (9, the ledger vendor, February to November), the retail app rebuild (5, January to June) and the data centre move (8, the hosting provider, July to December). That is 6 + 10 + 10 + 6 + 6 = 38 TPM-months. The corporate payroll upload crosses four teams with no outside party, so it runs under its engineering manager on the office’s template, and Ejiofor reviews its risk log monthly.

Demand against supply. Needed from January: 1, 2, 3, 4, 4, 4, 4, 4, 4, 3, 3, 2. In post: 0, 1, 1, 2, 4, 4, 4, 4, 4, 4, 4, 4, which is 36 TPM-months. The shortfall is six TPM-months, all from January to April (October to December have four spare, so 36 − 38 = −6 + 4): Ejiofor runs the retail app rebuild himself for four months, and the office runs the first month of co-lending (March) and of the settlement change (April) on its charter template.

Routes. Per programme costs ₦169m a year (₦52m plus three at ₦39m); one in each of 28 teams, ₦1,092m; a pool in the office, ₦130m; converting four office managers, ₦156m plus ₦15.6m. Chosen: per programme. Nearest alternative: the pool, rejected because offers on the office’s ladder sit below engineering’s.

Posts. An internal move from engineering on 1 February (₦35.75m in the year), a Senior TPM from outside on 1 April (₦39.0m), two office managers who pass the work sample on 1 May (₦26.0m each): ₦126.75m in the year, ₦169m a year after. The office does not backfill the two. The retail app rebuild’s TPM from May is the first convert.

Office. It keeps the portfolio view, the template and the monthly report; its colour is taken from the TPM’s weekly update.

Measures. Notice before a slip: baseline, five of six slips green or amber until the last month; target, at least four weeks. Forecast accuracy and coverage reported monthly.

What would change this. A sixth qualifying programme before May, or Owoleaf moving the settlement window: add a contractor TPM for six months with a named employee beside them.

Now you

You are the new head of programmes at Larkhollow, an AI agent and data platform with 120 engineers and 12 forward deployed engineers in two pods. Three enterprise customers have signed, and each go-live is a programme: the first crosses six teams and the customer’s own IT group and starts in February; the second crosses five teams and starts in March; the third crosses four teams plus a customer integration vendor and starts in May. Each needs forward deployed engineers from the pods inside the customer. Today two project coordinators in the delivery team track go-lives on a spreadsheet, and a staff engineer coordinates the first programme in her spare time. Finance will fund two TPM posts from March (illustrative loaded ₦39m each). A search from outside takes about six months, and one coordinator has asked to convert. Write the hiring and engagement model: the criterion, the monthly gap and who covers it, the routes with their cost, and how a coordinator is assessed.

Self-check

DECIDE

You are Ejiofor, Northmere Bank's Head of Programmes. The technology division has 340 engineers in 28 teams. Jorien's project office of 24 runs every programme on a stage-gate template, and last year five of the six programmes that missed their dates were green or amber until the last month. Five of the 2027 programmes meet your criterion and need 38 TPM-months, with four TPMs enough from May. Costs per year are about ₦169m per programme, ₦1,092m for one in every team, ₦130m for a pool in the office and ₦156m to convert four managers. The chief technology officer wants a decision this week. What do you recommend?

READING
  1. BOOK
    The Standard for Program Management, Fifth Edition Project Management Institute, 2024

    The vocabulary a project office will use. Read it to say where your TPM function agrees with it and where it differs, before you write the boundary between them. Read: The opening section on the program manager, sponsor and programme office roles.

  2. POST
    Scaling Engineering with the TPM Role Gergely Orosz, 2022

    Part two of a practitioner's account of the role, on when to introduce TPMs, how companies think about ratios and how to hire the first one. Compare its advice with your own count of programmes.

  3. POST
    The engineering executive's role in hiring Will Larson, 2023

    On designing and monitoring the hiring process instead of interviewing every candidate yourself, including levelling and headcount. Read it before you set the loop for a role your company has not hired.

  4. DOC
    Use structured interviewing Google re:Work

    The method for asking every candidate the same questions and scoring against a rubric. Apply it to the TPM work sample so that an engineer and an office lead reach comparable scores.

  5. BOOK
    The Mythical Man-Month: Essays on Software Engineering, Anniversary Edition Frederick P. Brooks Jr., 1995

    The oldest account of why structure and communication, not effort, decide whether a large programme lands. Read it for the case that a function should reduce paths between teams rather than add people. Read: Chapter 7, Why Did the Tower of Babel Fail?, the sections on communication and on organisation in the large programming project.

All companies and people in these examples are fictional. Any resemblance to a real business or person is unintended.